44 Wis. 126 | Wis. | 1878
It is objected on the part of the plaintiff, that the exceptions are insufficient to enable this court to review the evidence. Exceptions were duly filed to the referee’s findings of fact and law, but no exception was taken to the order of the circuit court confirming the report. It is claimed that such an exception was necessary to enable this court to review the decision of the circuit court. The case of Riley v. Mitchell, 37 Wis., 612, which is relied on to sustain this position, presents a different question. There, it did not appear that any exceptions were filed in the circuit court to the findings of the referee, though an exception was taken to the ruling of the court refusing to set aside the report and grant a new trial. But this court said it was impossible to determine from the record what exceptions taken before the referee were acted upon by the circuit court. But here, exceptions were filed to the report, which it would seem the circuit court must necessarily have considered on the motion to confirm.
The main questions in this case turn upon the construction of the contract. If the contract did not require the plaintiff to furnish materials and build the foundation for the engine and boilers, but did impose that duty upon the defendants, then it is obvious that their claim for damages on that ground must fail. So, too, must fail all claim for damages by reason of any defect in the foundation or for delay in building the same. What, then, is the true construction of the contract? Ry the contract, the plaintiff promised and agreed to make, and deliver to the defendants on the cars at Port Howax-d, by a time specified, a stationary engine and three boilers, according to a certain description and of a certain quality, together with a second-hand siding mill, then in its shop. The ma-chinei’y was for operating the defendants’ mill in Jackson county. Then follows this clause in the contract: “ The above to be set up and connected, with steam on (with exception of the siding mill), when delivered at the mill, by the party of the second part. Transportation to be furnished men to and from the mill, and board during the time employed in setting-up, as aforesaid, said machinery.”
Now, the contract being silent as to which party should provide the foundation, the question arises, Does this clause require the plaintiff to build it? Is such an intention fairly to be inferred from the language used by the parties? It seems to us not. The contract is to be read in the light of surrounding circumstances and the relations of the parties to the subject matter of the contract. Lyman v. Babcock, 40 Wis., 503. It appears that the plaintiff was engaged in manufacturing -and selling machinery at a considerable distance from the place where the defendants’ mill was situated. It was not
The finding of the referee that the engine and boilers were of the quality, dimensions, design and workmanship called for by the contract, cannot be disturbed. There is some conflict in the evidence upon this question; but the weight of testimony is in favor of the finding, that there were no defects in the machinery when it was delivered and set up. The same observation must be made in respect to the findings of the referee that the items charged in the plaintiff’s bill of particulars were furnished outside of the contract, and vTere admitted to be correct by the agents of the defendants, to whom the matter was referred for adjustment.
This disposes of all the material questions in the case which we deem it necessary to notice.
By the Court.— The judgment of the circuit court is affirmed.
A motion for a rehearing was denied.