274 P. 269 | Kan. | 1929
The opinion of the court was delivered by
This was an action to recover upon a drilling contract. S. J. Safford and son were the owners of oil lands and they entered into a contract with I. N. Money and H. E. Musser to drill an oil well on their land. The contract was executed and the well proved to be a producer. A second contract on the same terms was made between the parties to drill another well to a depth of 2,600 feet, certain parts of the casing to be furnished by the drillers and other parts by the Saffords. The drillers were to furnish all equipment, fuel, water and labor necessary to drill the well to the depth of 2,600 feet, or to what is termed the Varner sand, for which they were to receive $11,000, and also to dig a slush pond to take care of all water, and to mud off gas and oil encountered before reaching the Varner sand. There was a provision that if oil was not found at the depth of 2,600 feet, or the Varner sand, the drillers were to drill to an additional depth of 100 feet at the price of $70 per day. They were to furnish the equipment used in the extra drilling, and in case it turned out to bé a dry hole, to pull all the
Plaintiffs alleged that they drilled the well to a depth of 2,602 feet in good workmanlike manner and at that depth the well was in good condition and free from water, and that upon the request of defendants they afterwards drilled to a lower depth and the well was accepted; that they continued to drill under the supervision of defendants for three and one-half days. They alleged that, on September 1, 1925, it was drilled in as a producing well, when it was taken over by the defendants. It was further alleged that $5,000 of the contract price had been paid, leaving due $6,000 more, for drilling to a depth of 2,600 feet, and $245 for three and one-half days’ work done while working for the defendants. They asked judgment for $6,245.
The defendants denied that the well had been drilled in a workmanlike manner, alleged that the casing was set at a depth of 2,552 feet, leaving an uncased hole between the depth of 2,552 feet and the 2,600 feet through which water entered the well, that in placing a casing in the well joints were bent so that it was necessary to swage out the joints in order that drilling tools could be gotten through, and that this operation weakened and damaged the joints and thus permitted water to escape into the well from outside of the casing. That by reason of the failure of plaintiffs to properly complete the well, the defendants were obliged to pay out large sums of money' in an effort to shut off the water. They asked damages for nonperformance of the contract and for the material and labor furnished by defendant to protect the well from incoming water. The plaintiffs replied denying averments of nonperformance and alleging that the defendants accepted the well as a complete fulfillment of the contract and proceeded with drilling under their own supervision.
The only matters argued were as to questions of fact relating to the breach or fulfillment of the contract and whether there was
“Q. 1. Do you find that plaintiffs drilled the well to a depth of 2,602 feet? A. Yes.
“Q. 2. Do you find that Safford and son took over the well on August 31, 1925, at a depth of 2,602 feet? A. Yes.
“Q. 3. If you answer the foregoing question in the affirmative, state if Safford and son continued drilling thereafter, under their own direction and supervision? A. Yes.
“Q. 4. Do you find that the well was in good condition and free from water at a depth of 2,602 feet? A. Yes.
‘'Q. 5. Do you find that Money and Musser set the 6§-inch casing at the direction of Safford and son? A. Cannot answer (lack of evidence).
"Q. 6. Do you find that the water complained of was ‘bottom of the hole’ water? A. Yes.
“Q. 7. Do you find that the water complained of in said well was the result of drilling done by Safford and son after the 2,602-foot depth had been reached? A. Yes.”
The court also submitted to the jury other questions which were answered as follows:
“Q. 1. At the time the plaintiffs claim they ceased work on the well about August 31, 1925, was the 6-|-inch casing set in a good and workmanlike manner. A. Yes.
“Q. 2. At the time the plaintiffs claim they ceased work on the well about August 31, 1925, was the 6|-inch casing so set as to keep the water out of the well? A. Yes.
*523 “Q. 3. At the time the well reached a depth of approximately 2,602 feet did the defendants accept the well as having been completed by the plaintiffs in accordance with the contract, or tp the satisfaction of the defendant? A. Yes.
“Q. 4. At or before the defendants took charge of the well and began directing the work to be done thereon, did they make any claim to the plaintiffs that the plaintiffs had not performed their contract? A. No.
“Q. 5. What sum, if anything, do you find that the plaintiffs are entitled to recover for work done after the well had been drilled to 2,600 feet? A. $245.
“Q. 6. If you find the defendants are entitled to recover damages, then state the total sum you may find them to have reasonably and necessarily expended in. work on said well after it reached 2,600 feet and in an effort to shut off the water. A. $542.29.
“Q. 7. If you find the defendants are entitled to recover damages, then state how much you have deducted for their damages on account of the present value of the 5%6-inch casing and all the other tools, equipment and fittings that they may now have on hand and for which you allowed them a charge against the plaintiffs. A. None.”
Besides the special findings the jury returned a verdict finding for the plaintiffs and assessing the amount of their recovery at $5,702.71 with interest thereon.
As stated, only questions of fact are presented on this appeal. Much testimony was produced relating to the performance of the contract by plaintiffs, and also as to the alleged acceptance of the work as complete by the defendants. A reading of the testimony satisfies us that there was substantial performance and, more than that, there was evidence tending to show an acceptance by the defendants as a fulfillment of the contract. The evidence is sufficient to show that the water which entered and injuriously affected the well did not come from the upper part of it which had been drilled while plaintiffs were in control, but rather that it did come from the bottom while the defendants were in control of the well, and when they probably drilled too deep into a stratum of water. It is contended that under the evidence the matter of acceptance of the well by the defendants should not have been submitted to the jury. Acceptance was definitely pleaded and there was competent testimony tending to show the turning over of the well to and acceptance by the defendants with an understanding of conditions. Defendants or at least one of them, Gene Safford, was frequently at the well during the drilling and completion of it. He was experienced in the matter of drilling of other wells on the same land and cannot