152 Wis. 520 | Wis. | 1913
The following opinion was filed January 7, 1913:
The plaintiffs contend that the court erred in excluding part of the conversations that took place between the defendant and the plaintiffs relating to the work before they had complete plans for the barn, milk house, and the manure pit. The prior interviews are not essential to ascertain what was embraced in the contract finally and actually made. True, some of these prior interviews referred to part of the structures covered by the contract as found by the jury, but they were in the nature of preliminary negotiations and not essential to an understanding of the contract finally made by the parties. The vital question litigated was this: What work and material was embraced in the contract for which the defendant agreed to pay the plaintiffs the sum of $4,946 % These prior conversations had only a very slight bearing on this question, for it appears that the parties thereafter included them in their subsequent negotiations for the erection of a barn. The evidence adduced sufficiently explained what relation these prior negotiations had to the contract finally made, and no substantial injury was done by the exclusion of this evidence.
It is furthermore contended that the court erred in refusing to admit a memorandum book as evidence. This book
The next question argued is to tbe effect that tbe appellants were prejudiced by tbe reception of evidence of tbe reasonable cost of the work done and tbe material furnished by tbe plaintiffs in erecting and constructing tbe barn, milk bouse, and manure pit. Tbe purpose of this evidence was to aid tbe jury to ascertain what the contract based on plaintiffs’ bid to do work for $4,946 actually included. We are unable to perceive bow plaintiffs could be prejudiced thereby. Tbe evidence would aid tbe jury in resolving the wide discrepancies in tbe respective claims of tbe parties as to what was tbe actual value of tbe work performed as compared with tbe value of the work tbe parties claimed was embraced in tbe contract.
By tbe answer to question 1 of tbe special verdict tbe jury found that tbe minds of tbe parties met as to what work was to be performed and what material should be furnished by the plaintiffs for tbe sum of $4,946, and by question 2 that tbe contract so made by tbe parties included tbe work, labor, and material plaintiffs were to furnish on tbe milk bouse and tbe manure pit. Appellants aver that tbe court erred in refusing to change tbe answer to question 1, for tbe reason that the evidence does not sustain tbe jury’s conclusion that there
The court, after verdict, stated, upon the facts it deemed to be undisputed, the result of the trial to be:
Plaintiffs’ credit by contract. $4,946 00
For iron, cement, hardware, and waterproofing... 141 02
Total . $5,087 02
Defendant’s credit on casli paid.$4,693 31
Labor of men. 122 40
By unfinished work on barn. 150 00
Total. $4,965 71 $4,965 71
Balance due plaintiffs. $121 31
The court found that defendant’s claim for unfinished work on the manure pit was undetermined, having been omitted from the verdict, and on this account held that the defendant was entitled to a new trial, if he desired one, and therefore gave him the right to elect to have a new trial on account of this error or to submit to judgment against him for $121.31, the balance due plaintiffs according to the account as above stated. Defendant elected to have judgment •awarded against him for such amount. The appellants in
By the Court. — Judgment affirmed.
A motion for a rehearing was denied, with $25 costs, on March 11, 1918.