179 P. 980 | Utah | 1919
The plaintiff brought this suit as assignee of H. 0. Blu-menthal Company, a corporation, and of Provo Foundry & Machine Company, a corporation, against the defendant, as successor to Central school district No. 5 of Millard county by legislative enactment consolidating into one body corporate all of the school districts of said county. The amended complaint, in separate causes of action, alleges that during the year 1914 two contracts were entered into by said Blumen-thal Company, and one by said Provo Foundry & Machine Company with said Central school district No. 5 for the installation of certain heating, plumbing, and ventilating fixtures in the A. C. Nelson school building then in the course of construction by said district. By the terms of the first contract with Blumenthal Company the district was to pay $5,600 upon the installation of certain plumbing, heating, and ventilating fixtures, with interest at 8* per cent, per annum, payable quarterly; by the terms of the second contract with said Blumenthal Company the district was to pay the sum of $730.57 upon the installation of certain additional plumbing, heating, and ventilating fixtures; and by the contract with Provo Foundry & Machine Company the district was to pay $225 for certain dampers installed in said system.
The amended complaint further alleges full performance in good faith of the terms of said contracts by the assignors or the plaintiff, and the acceptance of the installed property by said district before May 17, 1914, since which time the said district and its successors have had possession and the use of said property; that certain payments wrere made in the first contract with the Blumenthal Company, leaving a balance due on said contract of $2,378.75, and that no further payments have ever been made on any of said contracts nor for said property; that said Central school district No. 5 and the defendant held out to the assignors of the plaintiff that the said property would be paid for until March 6, 1917, when
The complaint prayed as follows:
“Wherefore this plaintiff asks that the defendant Millard county school district pay to this plaintiff the sum of $3,394.66, with interest thereon at 8 per cent, per annum, payable quarterly from the date of the beginning of this action until paid, or that said defendant, Millard county school district, be declared to hold the property installed by said H. G-. Blumenthal Company and by Provo Foundry & Machine Company as above set out as a constructive trustee, as having obtained said property through mistake of fact and constructive fraud, and that said defendant and said plaintiff be placed in the positions which they, or their predecessors in interest, occupied before said mistake or said fraud occurred; that upon the payment to said defendant by this plaintiff of a sum equal to all amounts paid to this plaintiff or his predecessors in interest by this defendant or its predecessors in interest, with legal interest thereon, said defendant shall turn over to this plaintiff all of said property which can be removed from said school building without unreasonably damaging or unreasonably injuring said building, other than by the damage or injury caused through the loss of said property, together with a reasonable rental for the use of said property by said school district from the time of installation of said property until the delivery of same; and this plaintiff asks such further and additional relief as the court deems just, proper, and equitable.”
By its answer the defendant admits the installation of said property nnder the said purported contracts; the payments as alleged by the plaintiff; that demand had been made upon it for payment, and also for removal of said property and its refusal to comply with either of said demands; that said Central school district No. 5 was beyond its debt limit at the time of making the contracts; and that the contracts were null and void.
The answer further alleges that at the time of the installa
Upon a finding that the property sought to be removed was permanently affixed to, and in, the said A. C. Nelson school building as a part and parcel of the same, and that it was an essential and necessary part of the building, and that it was so attached to the building as to form a part and parcel of the real estate, and that it could not be detached or removed from the said building without permanently and materially injuring the building and destroying its usefulness as a school building, the court entered its judgment dismissing plaintiff’s complaint; hence this appeal.
Section 3 of article 14 of the Constitution of this state reads as follows:
“No debt in excess of tbe. taxes for tbe current year shall be created by any county or subdivision thereof, or by any school district therein, or by any city, town or village, or any subdivision thereof in this state; unless the proposition to create such debt, shall have been submitted to a vote of such qualified electors as shall, have paid a property tax therein, in the year preceding such election, and a majority of those voting thereon shall have voted in favor of incurring such debt.”
It is conceded that under the provisions of our Constitution the plaintiff cannot recover upon the express contracts entered into for the installation of the property
Appellant cites the case of Superior Mfg. Co. v. School District No. 63, 28 Okl. 293, 114 Pac. 328, 37 L. R. A. (N. S.) 1054, as stating the rule applicable to this class of cases. That was an action by a vendor to recover the purchase price of school supplies and furniture which were furnished when the district was beyond the debt limit, and in its decision the court said:
“While, under the circumstances arising in this class of cases, all the authorities deny the right of recovery either on the contract or quantum meruit, still all agree that the municipality cannot keep the property, and that plaintiJBE is entitled to retake it. This seems to he the only remedy available.”
Respondent concedes the principle announced in that case, and admits that, “if the property which plaintiff seeks to recover has not been installed in the building, and permanently affixed to the same, then a seller may.rescind the contract and recover back the goods.” Respondent therefore plants its case squarely upon the doctrine of fixtures, and appellant denies the application of the rules governing fixtures to the facts of this case.
It might be conceded that most, if not all, of the property sought to be removed by this action would be classed as fixtures in a contest between parties where the application of the rules of law governing fixtures was admitted, such as between landlord and tenant, mortgagor and mortgagee, etc. A ease of that kind is the case of Filley v. Christopher, 39 Wash.
This controversy is betwéen the parties to the transactions (or their successors in interest) by which the property claimed by the plaintiff was affixed to that of the defendant, and no third party’s claims or rights have intervened so as to involve a question of fixtures as understood in the law. See 19 Cyc. 1048; also Snouffer & Ford v. City of Tipton, 161 Iowa, 223, 142 N. W. 97, L. R. A. 1915B, 173, wherein this language is found:
“Some confusion has arisen over the meaning of this term ‘fixture.’ As a rule, the question only arises where the party making the annexation is claiming the right to remove property which he had annexed to a freehold against a stranger to the original contract. In other words, the doctrine of fixtures applies, as a rule, to chattels annexed to a freehold in actions between vendor and vendee of the real estate, landlord and tenant, mortgagor and mort*150 gagee, the seller of the fixture and a purchaser, mortgagee or creditor of the freehold. As a rule the owner of land and the seller of personal property make any agreement they choose regarding personal property to he annexed or attached to the land. [Citing cases.] A different question arises when rights of third parties intervene, and the subject of fixtures then becomes of great importance.”
There are a number of cases where bridges have been constructed on public highways under contracts with public officials which were ultra vires, and therefore void, and in that class of eases the courts have permitted the removal of the material used in their construction as the only remedy available to the party furnishing the same. Clearly in such cases the material would be as firmly attached to the freehold, and the inconvenience to the public as great as in the case at bar; the latter being also urged by the respondent as a reason why the removal of the property should not be permitted in this case. See Floyd County v. Owego Bridge Co., 143 Ky. 693, 137 S. W. 237; Salt Creek Tp. v. King Iron Bridge & Mfg. Co., 51 Kan. 520, 33 Pac. 303.
In the case at bar, the evidence shows that the greater part of the property sought to be recovered may be removed by merely taking out screws by which it is fastened to the building and uncoupling joints by which.it is attached together, and, as to the sectional boiler, by dividing it into sections so as to permit of its being removed through the doors the same as it was brought in, and without any permanent injury to the structure of the building itself. The effect of such removal would be merely to leave the building incomplete the same as it would have been without the installation of the \ materials under the void contracts, and there is nothing to prevent the defendant school district from now taking such steps as are necessary to replace the same with similar materials and appliances obtained elsewhere, nor, indeed, from entering into a valid contract with the plaintiff for the purchase of the material as presently installed. It might require a vote of the taxpayers to authorize such purchase if the school district is without sufficient current funds, but it is scarcely conceivable that the taxpayers would not prefer to
¥e do not wish to be understood as holding that under any circumstances should the defendant be compelled to pay under the terms of the void contracts, nor the plaintiff permitted to profit thereby.
However, to deny removal of this property, which is clearly subject to identification, easily removable without material injury to the structure of the building, not subject to any liens, when it is conceded that the plaintiff has no other remedy, would clearly be a subversion of the purpose for which the constitutional and statutory provisions in question were framed and would permit the taxpayers of the defendant school district improperly, because unnecessarily, to shift the burden of the education of the children of the district to the shoulders of those who in good faith have furnished the material for the completion of the school building, to the extent of the value of this property, which we think they would not desire, nor should they be permitted to do. See Bardwell v. Southern Engine & Boiler Works, 130 Ky. 222, 113 S. W. 97, and annotation to same in 20 L. R. A. (N. S.) 110.
If the material- furnished had been supplies which had been used or had been property which had become mingled with other property as to be not subject .to identification, or have been so affixed as to be irremovable, that result might necessarily follow, because the plaintiff would be without remedy.
The chief difficulty with this ease is to determine just what the judgment should be in view of the fact that a part of the purchase price has been paid and in view that
The judgment therefore reversed, and the, cause is re-