126 Iowa 606 | Iowa | 1905
On June 20, 1900, the defendant county entered into two separate written contracts with the Western Bridge Company, by the terms of which the latter agreed to furnish the materials and erect for the former two bridges across the Des Moines river, as follows: One at the town of Selma for $12,050, and one at the town of Kilbourne for
The petition alleges the letting of the bridge contracts by the county to the bridge company, and the contract of the latter with the plaintiff, pursuant to which it furnished materials to the bridge company, on which there was an unpaid remainder of $6,099, with interest. It is further alleged that within thirty days after the last of said materials was furnished plaintiff filed a duly verified statement of its account with the auditor of said county, which account and claim is still unpaid, and that under the terms of the contract between the bridge company and county the latter was required to withhold all of the contract price except seventy-five per cent, of the cost of the materials for the purpose of meeting such claims as the one now made by the plaintiff. Plaintiff therefore asks to recover from the county the full unpaid balance of its account against the bridge company. Nor answer to this claim the county admits letting the bridge contract to the Western Bridge Company, but denies that said bridges ever were erected according to
On December 11, 1901, the Western Bridge Company intervened, setting up its contracts with the county to build the bridges and with plaintiff to furnish the materials therefor, and alleges that such materials were substantially of the character and weight called for by the contracts with the county. It also pleads the inspection and approval of the materials and of the bridges by the agents and representatives of the county, and asks judgment for the unpaid balance of the contract price. As against the plaintiff it sets up various claims for,damages on account of delays and expenses occasioned by the fault of plaintiff in the completion of the work. Taking issue upon the petition of intervention, the plaintiff denies the bridge company’s claims for damages, and demands judgment against it for the unpaid balance of the account for bridge materials. The county answering said petition, sets up in detail the aforesaid charge of fraud in the construction of the bridges and in the failure of the intervener to perform its contract, and denies the authority of Booth or any other person to consent to any material departure from the agreement.
The issues were tried to the court as in equity. The
The value of the difference in the steel of the Selma bridge would be as follows:
Deficiency in superstructure, 46,440 lb., at 3.3 cents... $1,532 52
Deficiency in substructure, 38,370 lb., at 3 cents. 1,151 10
Total '.. $2,683 62
Add 15 per cent. 402 50
Total . $3,096 16
In the Kilbourne bridge, the difference in the superstructure is 18,180 lb., worth 3.3 cents per pound, making .. $ 599 94
Substructure, 31,002 lb., at 3.... ¡. 930 06
Total . $1,530 00
Add 15 per cent, profit.... 229 50
Total . $1,759 50
Against the aggregate of these damages, $4,855.66, the court set off the unpaid remainder of the contract price of the bridges, $3,905.60, leaving a balance due the county from the bridge company of $950.06, for which sumj with interest, judgment was accordingly entered. In explanation of the court’s estimate above quoted it should be said the testimony tends to show that in the construction of bridges a fair margin of profit to the contractor is at least fifteen per cent, upon the cost of materials in place in the complete structure. It is the contention of the appellant that this
By reason of its fraud and failure to perform, the bridge company could maintain no action and recover no compensation on the contracts made with the county. The utmost limit of its right to recover in any form of action would be the contract price, reduced by the damages which the breach of its contract had occasioned to the county. If, on account of the fraud or failure of .the bridge company, the contract is without legal vitality in the company’s hands, it cannot be imbued with life for the benefit of the subcontractor. The stream cannot rise higher than its source. The payments made to the bridge company may have been improvident in the failure of the supervisors to withhold a sufficient margin to cover all possible damages to the county, but they were not made in wrong of the plaintiff. If we should adopt plaintiff’s theory that the Selma bridge was completed and accepted on January 24, 1901, then, if the contract is to be considered, the entire consideration for that bridge became at once due and payable, and plaintiff, having filed no statement of its claim, cannot complain that such payment was in fact made. Treating the price of the Selma bridge as having been fully paid, there remained payments for which the county was entitled to credit upon the Kilbourne bridge, amounting to $11,294.46. This sum in-
What Ve have already said makes it unnecessary to discuss other questions argued by counsel. The decree of the district court appears to effect justice between the parties as nearly as such result is.possible under the complication of circumstances, and it is affirmed.