268 Conn. 429 | Conn. | 2004
Opinion
The dispositive issue raised by this appeal is whether a written agreement (agreement) entered into by the plaintiff, MJM Landscaping, Inc., and the named defendant, Paul R. Lorant,
The evidence adduced at trial revealed the following relevant facts. In 1992, the defendant, a resident of Japan, purchased residential property located at 43 West Brother Drive in Greenwich for investment purposes. In 1998, a departing tenant informed the defendant that there was a problem with the property’s septic system. Upon the recommendation of a real estate broker with whom the defendant previously had done business, the defendant retained an engineer to design a new septic system.
The defendant subsequently hired Greenwich Design and Build, LLC
Greenwich Design solicited bids from a number of companies for the construction and installation of the septic system. As part of this process, Adam Ross of Greenwich Design, and Rene Bastías, a site engineer and principal of the plaintiff, met at the property to review the design plan for the septic system. The plaintiff subsequently prepared a handwritten proposal for Greenwich Design providing for the construction and installation of the septic system at a price of $58,000. Ross asked Bastías to forward a typed version of the proposal to the defendant in Japan so that the defendant could review and execute it, and Bastías did so.
Upon completion of the project,
The defendant failed, however, to remit any additional payments to the plaintiff.
“The [act] is a remedial statute that was enacted for the purpose of providing the public with a form of consumer protection against unscrupulous home improvement contractors. . . . The aim of the statute is to promote understanding on the part of consumers with respect to the terms of home improvement contracts and their right to cancel such contracts so as to allow them to make informed decisions when purchasing home improvement services.” (Citation omitted.) Wright Bros. Builders, Inc. v. Dowling, 247 Conn. 218, 231, 720 A.2d 235 (1998). To promote this purpose, the act provides that no home improvement contract shall be valid or enforceable against a homeowner unless the contract contains, among other things, a starting date, a completion date and a notice of the homeowner’s cancellation rights. General Statutes § 20-429 (a) (6) and (7).
There is no dispute that, in the present case, the agreement between the plaintiff and the defendant fails to meet those requirements. Thus, if the agreement is
Before addressing the merits of the defendant’s claim, we first must determine the applicable standard of review. The defendant asserts that the determination of whether a home improvement service provider is acting as a contractor or a subcontractor involves a question of law subject to de novo appellate review. The defendant’s claim is foreclosed by our determination in Meadows that that question is one of fact. See id., 168, 171-72. The defendant has proffered no persuasive reason, and we know of none, why we should reconsider that determination. Thus, our review of the trial court’s determination of that issue is limited by the deference we afford factual findings. “A finding of fact will not be disturbed unless it is clearly erroneous in view of the evidence and pleadings in the whole record.” (Internal quotation marks omitted.) State v. Nosik, 245 Conn. 196, 205, 715 A.2d 673, cert. denied, 525 U.S. 1020, 119 S. Ct. 547, 142 L. Ed. 2d 455 (1998). “A finding of fact is clearly erroneous when there is no evidence in the record to support it ... or when although there is evidence to support it, the reviewing court on the entire
Applying this highly deferential standard of review, we conclude that the trial court’s finding that the plaintiff acted as a subcontractor of Greenwich Design in constructing and installing the septic system was not clearly erroneous. The record discloses that, as the trial court found, the defendant retained Greenwich Design to find a contractor to build and to install a septic system on the defendant’s property and to oversee that project. Greenwich Design thereupon solicited bids from a number of contractors, including the plaintiff. The plaintiff responded to the solicitation by submitting a proposal to Greenwich Design. Greenwich Design then met with one of the plaintiffs representatives at the property and thereafter selected the plaintiff to construct and to install the septic system. At the direction of Greenwich Design, the plaintiff transmitted its proposal to the defendant, who agreed to it. In accordance with the defendant’s wishes, the plaintiff started the project promptly and completed it expeditiously. At all times, however, Greenwich Design remained responsi
The defendant contends that the trial court’s finding that the plaintiff was acting as a subcontractor was clearly erroneous because the defendant did not have a written agreement with Greenwich Design but did have one with the plaintiff, and because the plaintiff engaged in certain conduct in filing the mechanic’s hen that would suggest that it considered itself to be a general contractor. We are not persuaded.
With respect to the defendant’s first contention, the fact that the defendant never entered into a formal written agreement with Greenwich Design does not alter the fundamental nature of the relationship between them. The evidence indicated that the defendant hired Greenwich Design to complete the tasks normally assumed by a general contractor, thereby providing the trial court with an adequate foundation on which to base its finding that Greenwich Design, and not the plaintiff, had assumed the role of general contractor. Furthermore, although it undoubtedly is more often the case that a party hired to perform subcontracting work
In support of his claim that certain circumstances associated with the plaintiffs filing of the mechanic’s lien reflected the plaintiffs own belief that it was acting as a general contractor, the defendant notes that the plaintiff filed the mechanic’s lien without providing written notice of its intent to do so either to the defendant or to Greenwich Design. General Statutes § 49-35 (a)
In sum, we conclude that there was sufficient evidence to support the trial court’s finding that the plaintiff acted as a subcontractor of Greenwich Design when it constructed and installed the septic system. Consequently, the defendant cannot prevail on his special defense alleging a violation of the act because the act is inapplicable to agreements, such as the one at issue in the present case, between a subcontractor and a homeowner. In view of the inapplicability of the act, the defendant’s CUTPA claim also must fail because that claim is predicated entirely upon the plaintiffs alleged violation of the act.
The judgment is affirmed.
In this opinion the other justices concurred.
Greenwich Design and Build, LLC, which claimed an interest in the named defendant’s real property by virtue of a previously filed mechanic’s lien, also was named as a defendant. Greenwich Design and Build, LLC, did not participate in this appeal, however. All references throughout this opinion to the defendant include the named defendant only.
General Statutes § 20-429 (a) provides in relevant part: “No home improvement contact shall be valid or enforceable against an owner unless it: (1) Is in writing, (2) is signed by the owner and the contractor, (3) contains the entire agreement between the owner and the contractor, (4) contains the date of the transaction, (5) contains the name and address of the contractor, (6) contains a notice of the owner’s cancellation rights in accordance with the provisions of chapter 740, (7) contains a starting date and completion date, and (8) is entered into by a registered salesman or registered contractor. . . .”
The defendant’s counterclaim also contained a count alleging negligent workmanship. The defendant withdrew that portion of his counterclaim, however, prior to trial.
In its memorandum of decision, the trial court indicated that the defendant had withdrawn his counterclaim in court at the conclusion of the trial. In fact, the defendant withdrew the count of his counterclaim alleging negligent workmanship; see footnote 3 of this opinion; but not the count of the counterclaim alleging a violation of CUTPA. Inasmuch as the defendant’s CUTPA claim depended entirely upon the viability of his claim under the act, however, the trial court’s determination that the agreement is not subject to the act necessarily was fatal to the defendant’s CUTPA claim. For purposes of this appeal, we treat the judgment of the trial court rendered in favor of the plaintiff as pertaining both to the plaintiffs complaint and to the defendant’s counterclaim.
The defendant appealed from the judgment of the trial court to the Appellate Court, and we transferred the appeal to this court pursuant to General Statutes § 51-199 (c) and Practice Book § 65-1.
On appeal, the plaintiff also claims, as an alternate ground for affirmance, that the defendant is barred from asserting a defense predicated on noncompliance with the act because the evidence adduced at trial established, as a matter of law, that the defendant repudiated the agreement in bad faith. See, e.g., Rizzo Pool Co. v. Del Grosso, 232 Conn. 666, 680 n.22, 657 A.2d 1087 (1995) (“[a] homeowner cannot in bad faith invoke the contractor’s . . . violation [of the act] as a basis for his own repudiation of the contract”). Like the trial court, we do not reach this claim because the act does not apply under the circumstances of this case.
See footnote 1 of this opinion.
According t,o Bastías, the proposal submitted to Greenwich Design and later sent by facsimile to the defendant was identical in format to proposals normally submitted by the plaintiff to general contractors.
Bastías testified that the plaintiff orally had informed the defendant of his right of cancellation.
The plaintiff completed the installation of the septic system on or about September 30, 1998.
There is no indication in the record as to whether the plaintiff made any additional payments to Greenwich Design.
General Statutes § 49-35 (a) provides in relevant part: “No person other than the original contractor for the construction, raising, removal or repairing of the building, or the development of any lot, or the site development or subdivision of any plot of land or a subcontractor whose contract with the original contractor is in writing and has been assented to in writing by the other party to the original contract, is entitled to claim any such mechanic’s lien, unless, after commencing, and not later than ninety days after ceasing, to furnish materials or render services for such construction, raising, removal or repairing, such person gives written notice to the owner of the building, lot or plot of land and to the original contractor that he or she has furnished or commenced to furnish materials, or rendered or commenced to render services, and intends to claim a lien therefor on the building, lot or plot of land . . . .”
Although § 49-35 (a) was subject to technical amendments in 2000; Public Acts 2000, No. 00-99, § 100; 2001; Public Acts 2001, No. 01-195, § 46; and 2003; Public Acts 2003, No. 03-224, § 7; those amendments have no bearing on the merits of this appeal. For ease of reference, we refer to the current revision of § 49-35 (a).
We note that the defendant does not claim that the plaintiffs failure to provide notice of its intent to file a mechanic’s lien pursuant to § 49-35 (a) rendered the lien invalid.