73 W. Va. 352 | W. Va. | 1913
Plaintiffs, A. B. Mitchell and A. E. Adkins, partners in a logging contract, recovered a judgment against H. A. Davis,
This action was brought on 6th April, 1911, to recover the price claimed for logs delivered in December, 1910, and in January and February, 1911. Plaintiffs had delivered 139,191 feet in those months. The action was brought in a justice’s court and, after judgment by the justice, appealed to the circuit court. Summons was issued for $300.00, and plaintiffs’ account filed showed a balance due them of $318.70. It is argued that this fact shows that the amount was beyond the jurisdiction of a justice. Defendants moved to dismiss the action on this ground, and the court overruled the motion. This was not error. In civil actions, the amount demanded by the summons determines the justice’s jurisdiction. Moore v. Harper, 42 W. Va. 39; Todd v. Gates, 20 W. Va. 464. Plaintiffs had a right to release a part of their claim, which they did, in order to bring it within the jurisdiction of a justice. Richmond v. Henderson, 48 W. Va. 389.
Defendants sought to recoup damages on account of plaintiffs’ shortage in delivery of logs, and filed a claim of recoupment and offsets amounting to-more than plaintiffs’ demand,
Plaintiffs stipulated in writing what they should forfeit for failing to deliver 8,000 feet of logs per day. It is virtually admitted by plaintiffs’ counsel that this was intended by the parties as liquidated damages, and was not a penalty to secure performance of the contract, in which latter case defendants’ recovery would be limited to a less sum than that stipulated, provided their actual damages were less. That plaintiffs failed to deliver 8,000 feet per day is admitted. There are seventy-seven work days in the three months covered by plaintiffs’ claim, and if they had delivered an average of 8,000 feet per day for that number of days, the total amount would have been 616,000 feet; whereas they delivered only 139,190 feet, thus falling short 476,810 feet. That quantity, at seventy-five cents per thousand, would amount to $357.60, which is more than plaintiffs demand; and, unless plaintiffs have proven, to the satisfaction of the jury, a lawful excuse for their failure to comply with that part of their contract, the verdict should have been for defendants, and they should have been discharged. The principal question is: Does the evidence justify the jury in concluding that plaintiffs’ failure was due to the acts and conduct of defendants, or their agents and employees? It is not claimed that plaintiffs were providentially hindered. But there is evidence tending to prove that a sufficient quantity of logs were cut and placed on the skids along the tramroad; that the man employed to truck them to the mill failed to deliver them; and that this trucker was employed and paid by defendants.
By the terms of the agreement plaintiffs were to use defendants’ tramroad to get the logs to the mill; defendants also used it, at the same time, to haul their lumber from the mill to market. They trucked the lumber up the tramroad to a point where it was carried over the mountain by an hoisting engine to a railroad on another stream. There being but one line of tramroad, it was impracticable to have two men trucking over it in opposite directions at the same time. One trucker would
“Where the performance of a contract according to its terms has been prevented by the obligee therein, he will not be permitted to recover the liquidated sum stipulated to be paid on a breach.” 19 A. & E. E. L. (2nd ed.) 423. This question arose in Dodd v. Churton, 1 Q. B. Div. (1897), 562. There plaintiff agreed to complete certain building works, according to specifications and drawings, by June 1, 1892, or forfeit two pounds a week for every week the work remained unfinished after that date as liquidated damages. The contract also provided that he should make any alterations or additions, not contained in the drawings and specifications, that might be directed by the architect, and that such alterations should not vitiate the contract, but that deductions from, or additions to, the contract price should be made according to the schedule of prices in the specifications for like work. The building was not completed until December 5, 1892; and the contractor had performed additional work to the amount of more than twenty-two pounds. The contractor sued for the balance due him, and defendant sought to recoup liquidated damages for the delay at the rate of two pounds per week. The court held that the additional work, which was shown to require at least two or three weeks additional time, was a lawful excuse for not completing the work in the time specified, and exonerated the contractor from liability to pay the liquidated damages.
Willis v. Webster, 1 Hun. (N. Y.) 301, decides the same principle. There a contractor had agreed to complete certain buildings by a certain day, and if not completed by that time he was to forfeit $250.00 a day, as liquidated damages, for every day thereafter until the work was completed'. He sued to recover a balance claimed to be due him, and defendants set up a counterclaim for liquidated damages, alleging that the completion of the contract had been delayed about a month. Plaintiff replied that the delay had been caused by defendants, their agents, contractors and mechanics; that defendants had given other contractors possession of portions
Such we understand to be the effect of the court’s holding in the English case above cited. There was no apportionment in that case, although the delay had continued for six months and the evidence showed that the extra work, relied on to excuse delay, could have been performed in two or three weeks.
In Welch v. McDonald, 85 Va. 500, the supreme court of appeals of Virginia applied the same rule. McDonald Brothers had a contract with the City of Roanoke to build a jail and jailor’s house, and subcontracted with Welch and Dull to furnish the stone for the walls of the building, the stones to be dressed and marked, so that each stone would fit into its proper place, at the price of $8.50 per cubic yard. All the stone was to be delivered by the 22nd of June, 1886, and if not Welch and Dull were to forfeit $5.00 a day for each day thereafter the contract remained1 unfulfilled. The contract was not completed at the time stipulated, and McDonald Brothers thereupon took the work out of the hands of their subcontractors and completed the buildings themselves. On the 1st of October, following, McDonald Brothers brought an action against Welch and Dull, claiming damages, at the rate of $5.00 a day, from June 22nd until the time of bringing their suit, amounting to $500.00. They also claimed additional damages, the whole of their claim aggregating $4,758.87. Under the instructions of the trial court, the jury found for the plaintiffs the sum of $1,907.38, and the court
Applying the law to the state of facts which the jury evidently found to exist, it results in an affirmance of the judgment.
Affirmed.