38 Iowa 286 | Iowa | 1874
— The written contract provides that Mitchell & Sexton agree to do the grading on “the Des Moines & Indianola Bailroad from stake No. 240 to stake No. 270 at the agreed price of twenty cents per cubic yard, excavation measurment, to be paid upon engineer’s estimates, the same as upon' the said Kavanagh’s contract,” &c. It was subsequently orally agreed that jfiaintiffs should grade from the stake last named to stake 271, for the same price and on the same terms as stated in the written contract.
Under this contract the estimates of the defendant’s engineer are to be taken, between these parties, as at least paima facie.-
The plaintiffs undertook to show the incorrectness of the engineer’s estimates by one B. Callan, who testifies that he was a surveyor and engineer by profession. He shows by his testimony that some time after the work was completed he called at the office of the chief engineer of the railroad company, where he' obtained from that officer certain figures from which, with some measurements made by himself, he made an estimate of the work done by the plaintiffs on the sections included in their contract, which shows a large excess of excavation over the engineer’s estimates. It is evident that the verdict of the jury is based upon Callan’s calculation of the amount of work done by the plaintiffs. Appellant insists that the verdict is not sustained by sufficient evidence. In this I feel bound to concur. It seems patent that the verdict is not supported by sufficient evidence. In the first place, this witness, Callan, shows by his own testimony that he did- not have sufficient data upon which, with only some five or six actual measurements made by him, to make a correct estimate of the-work actually done. He also shows by his testimony that he found the figures which he obtained of the chief engineer, as far as they went, to be correct. It is also showp that the further data requisite to a correct estimate of the. grading was in the possession of the engineer of the defendant who made the estimates at the time of making the same.
Secondly. Callan shows by his testimony that he did not measure any excavations, but took the figures of the engineer furnished him and made some intermediate measurements of émbankments, from all of which lie- computed the number of cubic yards in the- embankments, and then-added ten peícent. to this amount. The contract provides for “excavation measurement.” In the absence of any custom or usage as to the mode or manner of making this measurement, it is plain
The testimony of the engineer who made the estimates under the contract shows that in making the estimates he measured the excavations, and allowed the plaintiffs pay for the work thus shown to have been done. He further testifies that he also measured the embankments, and for the excess found in the embankments over the excavations, he allowed the plaintiff pay for that also. This method of measurement conforms to the language of the contract, while that adopted by the witness Callan does not. There is' nothing to show that the engineer was mistaken in any of his computations.
Thirdly. It was admitted that, at the time of making the contract, Sexton alone had already done grading between stations 241 and 271 to the amount of 3071 cubic yards. Now the witness Callan estimated the total of the work done between these stations, added ten per cent, thereto, and then
Reversed.
— The other members of the court very readily concur in the conclusion reached by the Chief Justice in the foregoing opinion, but prefer to rest that conclusion upon another basis.
What is the effect of the agreement by plaintiffs that they are “to be paid upon engineer’s estimates? ” In Easton et al., v. The Penn. & Ohio Canal Co., 13th Ohio, 79, the contract provided that the “engineer shall estimate the value of the work done and upon his certificate” payment should be made, etc.; and in a subsequent part of the contract “it is mutually agreed that the decision of the said engineer shall be final and conclusive, in any dispute which may arise between the parties.” In deciding the case the court said, per Wood, J., “the engineer is the umpire between the parties. His determination ends the contract, and exempts the company from its obligations. The agreements of the parties are the law by which their rights are to- be determined, and I am
We have made these extracts more extended than usual, because they are fair exemplars of the general course of decisions upon the same question, and set forth with clearness the reasons upon which they rest. .The following cases fully support the same doctrine: The Board of Trustees etc. v. Lynch, 10 Ill. Rep. (5 Gilm.), 521; McAvoy v. Long et al., 13 Ills., 117; The Alton etc. R. Co., v. Northcott; 15 Ills., 49; (see also as bearing remotely, Hennessey v. Farrell et al., 4 Cush., 267); The Del. & Hud. C. Co. v. Dubois, 15 Wend., 87; Smith v. Briggs, 3 Denio, 73; Smith v. Brady, 17 N. Y., 173; Butler v. Tucker, 21 Wend., 117; The U. S. v. Robeson, 9 Peters, 319; Mills v. Weeks; 21 Ills., 561, (i. e.) 570; Mickles v. Thayer, 14 Allen, 114; Boston Water Power Co. v. Gray, 6 Met., 131 (i. e.) 169; Vanderwerker v. Vermont Cent. R. Co., 27 Vermont, 125 (i. e.) 137; Smith v. The B. C. & M. R. Co., 36 N. H. Rep., 458 (i. e.) 490; Palmer v. Clark, 106 Mass., 373 (i. e.) 389; Commonwealth v. Clarkson, 3 Penn. St., 277, and very many other cases.
Since, therefore, the plaintiffs concede that they have been fully paid for their work upon and according to the engineer’s estimates, and there being a total absence of pleading as well as proof, tending to show either fraud, mistake, undue influence, or want of good faith, such as would entitle the plaintiffs to relief upon the principles of equity, it follows that the judgment must be ;
Reversed.
After the foregoing opinions were filed, the counsel for appellees presented a petition for a rehearing, evincing much of earnestness and ability. The manifest misunderstanding of the real basis of the two opinions before announced, seems
Beversbd.