275 Minn. 433 | Minn. | 1966
Action by Missouri Valley Steel Company to recover $15,000 for steel sold to Lundquist Constructors, Inc., a Minnesota corporation. Included as a defendant in the action is New Amsterdam Casualty Company, a corporate surety on a public contractor’s bond furnished by Lundquist Constructors, Inc., on a contract for the construction of a water-treatment plant for the city of Fairmont. It is the contention of defendants that the sum due to plaintiff from Lundquist Constructors, Inc., is only $4,834.72. The difference arises because payments made to plaintiff by Lundquist Constructors, Inc., in the sum of $10,165.28 were applied by plaintiff on debts owed it by Lundquist Construction Company, a copartnership comprised of Robert A. Lundquist and Eugene Coil, and by Robert A. Lundquist personally.
The court found that defendants were indebted to plaintiff in the full amount of $15,000 in that “Plaintiff was justified in applying the payments made by defendant Lundquist Constructors, Inc., as it did” and because Lundquist Constructors, Inc., had acquiesced in the procedure described.
This appeal is from an order denying defendants’ motion for a new trial. It is defendants’ contention that the stockholders and directors of Lundquist Constructors, Inc., had not authorized plaintiff to apply the payments on the debts of the prior business; and that there was nothing in the corporation’s conduct which would estop it from questioning this application of the payments by plaintiff.
The facts are as follows: Prior to February 11, 1958, Robert A. Lundquist and Eugene Coil were engaged in business as a partnership under the name Lundquist Construction Company at LeMars, Iowa. The latter firm had purchased steel supplies from plaintiff for use in various construction projects and on the date mentioned was still indebted to plaintiff for such purchases. The copartnership had ceased to do business
The office of the new corporation was located at Fairmont, Minnesota. At the time of its formation Lundquist individually was working on an uncompleted contract begun by the copartnership for the construction of the Emmet County courthouse at Estherville, Iowa. A public contractor’s surety bond had been furnished by the copartnership on this project for the protection of plaintiff and others furnishing material under the contract. After formation of the corporation Lundquist continued to work on this contract to its completion and payments made upon it were placed in the account of the corporation to the extent of $25,564.02. Subsequent to the formation of the corporation two new contracts were entered into — one for the construction of a water-treatment plant at Fairmont and one for the construction of the Trimont School between Triumph and Monterey, Minnesota. On these two contracts New Amsterdam Casualty Company furnished the public contractor’s bond required by Minn. St. 574.26. Plaintiff furnished steel to the corporation for these two projects.
On June 11, 1958, Lundquist Constructors, Inc., received $31,027.50 on the Trimont School project. This was deposited in its account in the Martin County National Bank of Fairmont. After this deposit had been made, the corporation paid to plaintiff the sum of $7,000 on June 13, 1958, and $6,000 August 13, 1958. These sums were applied by plaintiff on the previous indebtedness of the copartnership and Lundquist. At that time no billing had been made to the corporation for work on either the Trimont School or the Fairmont water-treatment project. The corporation had ordered steel from plaintiff for the Trimont School project, but very little of this had then been delivered.
There was evidence which would establish that Lundquist said nothing to plaintiff as to how these payments were to be applied, from which the implication could be drawn that plaintiff was justified in applying
Lundquist testified that none of the directors or shareholders of the corporation ever authorized him to apply corporate payments on other than the corporation’s accounts, but there was evidence that the other officers and directors had placed complete control of the corporation in the hands of Lundquist and that the bylaws of the corporation provided:
“* * * The President shall be the chief executive officer of the corporation; he shall preside at all meetings of the Shareholders and Directors; he shall have general active management of the business of the corporation, and shall see that all orders and resolutions of the Board are carried into effect. He shall execute all bonds, mortgages and other contracts, but all construction contracts shall be approved by the Board of Directors. He shall be ex-officio a member of all standing committees, and shall have the general powers and duties of supervision and management usually vested in the office of President of a corporation.”
The evidence established that Lundquist Constructors, Inc., referred to herein as Lundquist, Inc., after its formation at all times held itself out to plaintiff as successor to the previous copartnership and to Robert Lundquist individually. Plaintiff’s prior accounts with the co-partnership and Lundquist were carried over as accounts against the corporation on a continuous basis and the corporation was so billed each month. At no time did anyone protest this procedure on behalf of defendants. Lundquist, while president of the corporation, continued to perform and complete the work previously undertaken by the copartnership on the Emmet County courthouse project for which plaintiff had furnished the steel. Payments made by Emmet County officials to the co-partnership on this work to the extent of $25,564.02 were accepted by the corporation and deposited in its bank account. Its accountant made
The evidence also established that prior to the time that defendant New Amsterdam Casualty Company furnished the public contractor’s bond on the Fairmont water-treatment project it had available to it information which would have disclosed an amount due from the corporation to plaintiff entirely consistent with that ultimately made the basis of this action. Its representative had examined the books of account of the corporation prior to the issuance of the bond. It further had required a financial statement from the corporation as well as from Lundquist individually. Examination of either of such statements would have disclosed that the amount claimed by plaintiff had been arrived at by application of the corporation’s payments upon the previous indebtedness of the copartnership and Lundquist.
Likewise, a letter from plaintiff sent to this surety company on June 17, 1959, would have disclosed to the surety company that the amount claimed due by plaintiff on the Trimont project could have been arrived at only by the application of the corporation’s checks of June 13, 1958, and August 13, 1958, on the copartnership indebtedness. Notwithstanding this the surety company made no protest and was content to issue the bond in June of 1959, almost a year after the corporate payments had been made.
In reliance upon the payments and induced by the corporation’s conduct to assume that they could properly be applied to the account for materials furnished Lundquist and the copartnership, plaintiff took no measures to enforce payment of the account due it on the Emmet Coun
“* * * [wjhether we call it estoppel or by some other name, it would seem to be clearly inequitable to permit the stockholders and directors of Lundquist Constructors, Inc., to successfully plead ignorance when they made no attempt to inform themselves as to what was going on or to protect themselves from just what happened here. Lundquist had several opportunities to inform Plaintiff of the change in his status. If his failure to do so was due to ignorance, that would not shift to Plaintiff the burden of ascertaining his status. If it was due to his deliberate defalcation, that is one of the hazards covered by the bond.”
We find the fact situation here distinct from the facts involved in Ganley v. City of Pipestone, 154 Minn. 193, 191 N. W. 738, relied upon by defendants. Here there is evidence that Lundquist, Inc., through its active officer, held itself forth as a successor to the copartnership and Lundquist individually by taking over and completing their contracts and by accepting payments due for them as well as by consummating a transfer of their assets in exchange for corporate stock. Here there was also evidence that would establish that at the time it furnished its bond
“It is urged that plaintiff had no knowledge of the transfers by Storr [plaintiff’s officer] to defendant until after they had been made. This is not decisive. The transfers were within the authority conferred upon Storr. * * * The general authority comprehends the particular case. * * * Plaintiff is charged with Storr’s knowledge under these circumstances.”
Under these principles we hold that plaintiff has established its right to collect the full amount of its claim against defendants as alleged in its complaint, and as determined by the trial court.
Affirmed.