This case involves the question of damages caused by the construction of a ditch. Appellant was defendant in the lower court, and, from a judgment of $300, has prosecuted this appeal.
Facts.
In October, 1938, appellant constructed a ditch along the right of way in order to drain surface water. This ditch was adjacent to the eighty acres of land owned by W. H. Martin; and in October, 1940, Martin sued appellant for damages to the land resulting from the construction of the ditch. The complaint in that case alleged that prior to the construction of-the ditch the lands were in a. high state of cultivation and adapted to the growing of cotton and other crops, and free of overflow; but since the construction of the ditch the lands had become “practically useless on account of the overflow water which said ditch pours on the same in enormous quantities after each hard rain, thereby making said land practically useless; . . . that the overflow water has washed deep gullies in the land and has washed the soil from the land to such an extent that the land’ is useless.’’ Martin sought damages in the amount of $1,000.
On April 16, 1941, the court sitting as a jury found for the plaintiff and assessed his damages at the sum of $150 “for damage to the following described land as set out in the complaint . . . ” Judgment was rendered for Martin for $150 and interest and costs; and the judgment was paid and satisfied of record.
While the above-mentioned cause by Martin was pending against appellant, Martin rented the same eighty acres of land to the appellee McGuire. .He planted the land and his crops were destroyed in the Spring of 1941 by reason of the water from the said ditch overflowing the eighty acres of land. McGuire then filed the present suit against the appellant for $1,400 as damages to his crops destroyed in 1941. Appellant pleaded the former suit and recovery by Martin as res judicata. The present cause was tried on a stipulation; and there was no evidence introduced tending to show that any change of any kind had occurred in the ditch or the railroad right-of-way from the original construction in 1938. There are two questions: 1. The nature of the damages. 2. The plea of res judicata.
1. The Nature of the Damages
• The law of this state is well settled that: If the damages from the construction are recurrent, then there may be a recovery after each infliction of damages; but if the damages from the construction are original, then there can only be one recovery. The early decisions are listed in the case of C., R. I. & P. Ry. Co. v. Humphreys,
While the statute of limitations is not involved in the case at bar, still the above-quoted rule is fully applicable when applied to a case like the one here, involving the question of recovery in one action or in a succession of actions. It is clear that when Martin filed his suit in 1940 the nature and extent of his damages were known with reasonable certainty; otherwise he would have had no case to file. So under the authority of the above-quoted case we hold that the damages were original and that the original recovery by Martin is the only one for which the appellant is liable. Board of Directors v. Barton,
Appellee urges that the case of C., R. I. & P. Ry. Co. v. McCutchen,
2. Bes Judicata
Appellee has pleaded the Martin judgment as res jiidicata against the present suit; and we find that this plea is well founded. As stated in
And in
Appellee was the tenant of Martin, so certainly he was Martin’s privy. In the case of C., R. I. & P. Ry. Co. v. Humphreys,
The above case is ruling here; and it follows that the trial court committed error in rendering judgment for appellee.
The judgment is reversed and the cause is dismissed.
