34 Minn. 71 | Minn. | 1885

Gilfillan, C. J.

This was an action brought by plaintiff to recover compensation, at the rate allowed by its charter, for running defendants’ logs through its booms above the Falls of St. Anthony, in the years 1881 and 1882. The questions in the case arise on a counterclaim set up by defendants. The charter makes it the duty of plaintiff, on a specified notice, to turn loose all logs in its booms destined below the falls. The counterclaim is for neglecting *75their duty in respect to defendants’ logs in the years 1880, 1881, and 1882. The plaintiff insists that this is not, under the statute, a counterclaim; that the court erred in its charges and refusals to charge with respect to it; and that an improper rule of damages upon it was adopted in the court below.

The first of these objections the plaintiff waived in the court below by omitting to demur on that ground, and taking issue on the facts. Walker v. Johnson, 28 Minn. 147.

Of the other two, we will first consider the second, as it is by far the more important. The measure of damages adopted by the court below is fully stated in the seventh request of the defendants, which was given to the jury as follows: “If the defendants wanted their logs to manufacture into lumber, and had the facilities for doing so, and depended upon getting their logs for that purpose, and did not have other logs, and could not get a sufficient supply from other sources to manufacture, and these facts were known to the plaintiff when notified to turn them over the falls, then, if the plaintiff was in fault in not delivering the logs, and defendants could have manufactured them if delivered, the defendants are entitled to damages, to the difference between the market value of the manufactured lumber from the logs at defendants’ mills and the market value of the logs in plaintiff’s boom at the time they should have been turned out, adding thereto the cost of manufacturing the same into lumber, and the boom charges, and the cost of getting the logs to defendants’ mill if they had been duly turned out.”

The evidence tended to establish the facts specified in the request, and that the defendants, during the time covered by the counterclaim, had on the river, below the Falls of St. Anthony, a mill and all facilities for manufacturing logs into lumber, lath, shingles, etc., and had procured these logs above the falls for the purpose of so manufacturing. The substance of the request is that if defendants intended the logs for manufacture at their mill, had there all the facilities for such manufacture, and could not get elsewhere logs to supply their mill, and these facts were known to plaintiff when notified to turn the logs loose, then the defendants are entitled to recover, as damages for failure to turn them loose, the profits defend*76ants would have made by manufacturing them if they had had them to manufacture.

The rule in Hadley v. Baxendale, 9 Exch. 341, that the damages for breach of a contract “should be such as may fairly and reasonably be considered, as either arising naturally, — i. e., according to the usual course of things, — from such breach of contract itself, or such as may reasonably be supposed to have been in the contemplation of both parties, at the time they made the contract, as the probable result of it>” has been accepted and acted on in this court. Converse v. Burrows, 2 Minn. 191, (229;) Paine v. Sherwood, 19 Minn. 270, (315,) and 21 Minn. 225; Beaupre v. Pacific & A. Tel. Co., 21 Minn. 155. The rule is not denied in this case, but the objection is made that the damages which the request allows are too remote, uncertain, and conjectural. Under either branch of the rule the damages must be certain, both in their nature and in respect to the cause from which they proceed, and must not be the remote, but the proximate, consequence of the breach, and must not be speculative or contingent. They must appear with reasonable certainty, and not as matter of conjecture. Absolute certainty, however, is not required.

In Simmer v. City of St. Paul, 23 Minn. 408, an action for interruption to plaintiff’s business, it was held that gains and profits of the business were not a proper element of damages, because it did not appear whether they were such as might be taken into account in estimating the value of the business, or such as were merely anticipated and conjectural. On the.other hand, in Gœbel v. Hough, 26 Minn. 252, also a claim for interrupting a business, it appearing that it was a regular and established business, it was held that its value could be got at with reasonable certainty by showing its profits for a reasonable time prior to the interruption, and that the ordinary profits of such a business are not contingent or- speculative in the sense that excludes profits from consideration as an element of damages. Although such a business is liable to mishaps and contingencies, it may be assumed, with as much certainty as can ever be assured in judging of the affairs of men, that if profitable in the past, it will, under similar conditions, be profitable in the future. So, *77upon a contract to drive logs at an agreed price per thousand which defendant prevented plaintiff from performing, the profits that would have accrued from its performance were taken as the general measure of damages, although from the nature of the business the amount of profits could not be fixed with absolute certainty. Glaspie v. Glasgow, 28 Minn. 158.

It may be assumed with reasonable certainty that if the plaintiff had, on receiving the notice, turned the logs loose, they would have come to the defendants’ mill, and that the defendants, as they had the means and were prepared and intended to do, would have manufactured them, and would have had the lumber; and it is also reasonably certain that the detention of the logs prevented defendants’ being in that situation, and deprived them of the advantage or profit which it would have given them. That such would be the effect of the detention must have been in contemplation of the parties if the plaintiff had the notice mentioned in the request. The difference between the value of the logs in the boom, with the boom charges, the cost of getting the logs to the mill, and the cost of manufacturing added, and the value of the manufactured lumber, was not, at the time of the trial, matter of speculation or conjecture, but of as much certainty as the value of personal property and the cost of labor or manufacturing at a time past can ever be. That difference represents the loss of defendants in consequence of plaintiff’s neglect to turn the logs loose. To that extent they were worse off because of such neglect. The request correctly stated the rule of damages.

It being for the court, and not for the jury, to determine what in any case is the proper rule of damages, and when damages are speculative, so that they should be excluded, the plaintiff’s nineteenth, twentieth, and twenty-first requests were properly refused. We also see no error in the refusal to give plaintiff’s twenty-second and twenty-third requests, the court having in its general charge given the jury in clearer and better terms all that is correct in those requests.

Plaintiff’s twenty-seventh request was: “If you find from the evidence, in respect of any logs herein claimed to be the property of the defendants, that any portion thereof were, when turned out of plaintiff’s boom, the property of H. Houlton individually, and not of *78Prince & Houlton, then you cannot include in any estimate of damages any such part of said logs as you shall find to have been the property of H. Houlton when so turned out, notwithstanding the same may have been, after being turned out of plaintiff’s boom, scaled to Prince & Houlton.” This the court declined to give, and instructed that the logs were to be regarded as under the control of the plaintiff until scaled, and if they were, as claimed, to become the property of Prince & Houlton when sealed, that is sufficient for the purpose of this suit to authorize the defendants to recover.

In respect to the logs referred to, the evidence tended to prove this : that they were bought or cut by H. Houlton for himself, for manufacture at a mill of his on the river above the limits of plaintiff’s jurisdiction, and that, prior to their coming down the river, he and Prince & Houlton agreed that all his logs which came into plaintiff’s boom should belong to the firm, and upon being scaled should be paid for by them and become their property. This arrangement defendants appear to have made for the same purpose with which they procured their other logs, to wit, for manufacturing at their mill. Had the plaintiff done its duty on receiving notice to turn loose the logs, (and the notice seems to have been signed both by the firm and Houlton,) they would have been scaled and turned out within the time specified by its charter, and within that time, under the agreement between Houlton and the firm, the legal title to Houlton’s logs would have vested in the firm. That it did not vest in them within that time was due to the fault of plaintiff. Under that agreement nothing further was to be done by the parties to it to pass the title. That gave the firm an interest in the logs sufficient to raise a duty on the part of plaintiff towards the firm, as well as towards Houlton. It is therefore immaterial, as affecting defendants’ right to recover, that the legal title to the logs remained in Houlton as a consequence of plaintiff’s default during this detention. The result to defendants was the same as though the legal title had previously vested in them.

Order affirmed.

© 2024 Midpage AI does not provide legal advice. By using midpage, you consent to our Terms and Conditions.