115 P. 33 | Mont. | 1911
delivered the opinion of the court.
This action was begun in Missoula county by W. H. Charnley to foreclose a mechanic’s lien. After trial Charnley died, and Mills, as his administrator, was substituted. In discussing the case we shall refer to Charnley as the plaintiff. The complaint alleges that the defendants Lacasse were the owners of certain lots in the city of Missoula; that they made a contract with Olsen & Johnson to erect a building thereon; that the latter contracted with Charnley to do the lathing and plastering, for which they promised to pay him at the rate of thirty-six cents per square yard; that Charnley agreed to furnish all materials used by him ; that Olsen & Johnson should advance the money necessary to pay for materials as needed, the remainder of the contract price to be paid for as the work progressed; that, if Olsen & Johnson could purchase materials cheaper than could Charnley, they were to do so, and give him the benefit of such reduction in price; that they were to do all hoisting of materials without expense to Charnley, and were to pay him the reasonable value of all extra work; that plaintiff did 17,087 yards of plastering and performed extra work, “ all of which amounted to the sum of $6,432.42, no part of which has been paid except the sum of $3,740.13, leaving a balance due of $2,692.29, for which amount plaintiff filed and claims a lien upon the building. We shall
1. Appellants’ first contention is that plaintiff’s notice of lien is fatally defective, in that it fails to state under oath that it contains a just and true account of the amount due him after allowing all credits, as provided by section 7291, Revised Codes. As a matter of fact, the notice of lien sets forth the contract
2. The second contention is that the evidence is insufficient to justify the findings,- and that the amount found due the plaintiff is excessive.
At the trial, Mr. Tolan, one of the defendants’ attorneys, made this statement: “There is no doubt that the plaintiff -will testify that the items set out in this mechanic’s lien are correct; that is, with reference to the extra work and all about it.” This
We have never examined a less satisfactory record, and feel that a proper disposition of the case would be to remand it for a new trial, which action would be taken were it not for the fact that Charnley is dead, and such a course would perhaps result in placing his representative at a disadvantage. And we are also reluctant to order a new trial in view of the circumstance that the appellants here had it in their power to clear matters up in the court below by requesting a special verdict and specific findings of fact. It is impossible from the record to tell whether Charnley had any credit balance in his favor on either the university library building contract or the Deschamps building. He admitted receiving two carloads of cement from Olsen & Johnson. As to this cement, which he claims was sixty tons at $11 per ton, he first said that he gave credit for it on the university library work and the Deschamps building. Afterward he said that he allowed it on “this Lacasse job contract,” and still later he testified that he “did not give them credit for the amount paid for the plaster on his job in the Lacasse building.” The court ruled, as we understand it, that Olsen & Johnson were entitled to credit for the whole of it in any event.
Having carefully studied the evidence, we are unable to ascertain how the court and jury arrived at the amount awarded the plaintiff. His counsel offers no figures to justify it. Consequently it is of no significance. We shall therefore dispose of
1. Balance overdrawn on previous contracts........$ 380 38
2. January 9, 1909, Cash....................... 250 00
3. January 6, 1909, “ 300 00
4. January 23, 1909, “ ....................... 600 00
5. January 30, 1909, “ ....................... 282 50
6. February 1, 1909, “ ....................... 200 00
7. February 13, 1909, “ ....................... 200 00
8. February 20,1909, “ ....................... 200 00
9. February 27, 1909, “ ....................... 100 00
10. April 3, 1909, “ ....................... 135 00
11. March 22, 1909, “ 175 00
12. January 31, 1909, amount paid plasterer........ 53 25
13. January 2, 1909, amount paid lathers.......... 66 60
14. * * * amount paid for lime................ 32 50
15. April 20, 1909, check........................ 165 00
$3,140 23
Olsen testified that Charnley received the following cash payments :
1. December 16, 1908, check for freight on plaster. .$ 210 00
2. February 26, 1909, cheek..................... 100 00
3. April 2, 1909, “ 135 00
4. January 2, 1909, “ 50 00
5. January 9, 1909, “ 282 50
6. January 9, 1909, “ 250 00
7. January 16, 1909, “ 200 00
8. February 5, 1909, “ 200 00
9. January 23, 1909, “ 600 00
10. January 30, 1909, “ 550 00
11. February 20, 1909, “ 350 00
12. February 13, 1909, “ 200 00
13. March 20, 1909, “ 175 00
14. April 20, 1909, “ 165 00
15. April 12, 1909, “ 53 25
16. April 2, 1909, “ 66 60
$3,587 35
A great deal of testimony was taken as to whether the $210 cheek of December 16, 1908, should be charged against Charnley. He testified, in substance, that he received a car-load of cement from one Dally in Spokane, and that this check was given him by Olsen & Johnson to pay the freight thereon. He further said, however, that he told them he would not consent to be charged for cement any greater sum than he was obliged to pay Dally, to-wit, $11 per ton laid down in Missoula. And he
The sum of the additional cash payments which we think should be charged to Charnley, as above stated, viz., $210, $50, $550, and $350, is $1,160, which, added to the amount he admitted having received ($3,140.23), makes $4,300.23. He also received lime to the amount of $48.50, for which he credited them with only $32.50. The balance of $16 should be charged to him. If we accept his last statement on the subject, he used sixty tons of cement on the Lacasse building, and gave them credit on other contracts for $660. He says he credited them with all they furnished; but in this he is mistaken, for the record shows that he used all they delivered to him, which was 1,416 sacks. This cement at $14 per ton would come to $991.20. As he credited but $660, the balance of $331.20 should be now credited.
Let us revert for a moment to his original statement of account. He there gave credit for $3,740,13, of which $3,140.23 was cash, leaving a balance of $599.90, which must have been for material; and this material must necessarily have been lath and common lumber, as he received no other, except as above stated. The total value of the lath furnished him was $775.72, and common lumber $29.28, making a total of $805. He swore that he credited it all on the old contracts, but this statement
Summary.
Cash to be credited to Olsen & Johnson..............$4,300 23
Balance on lime account.......................... 16 00
Balance on cement account ........................ 331 20
Value of material admitted to be a proper credit...... 599 90
Total.....................................$5,247 33
The difference between $6,432.42, the total amount due under Ms contract, and $5,247.33, credits allowed Olsen & Johnson, is $1,185.09, or $162.91 less than the amount of the verdict. In this sum the verdict against Olsen & Johnson and the judgment against them are excessive.
So far as the lien is concerned, Charnley had no right to
Lath and common lumber................$805 00
Lime................................ 16 00
Cement.............................. 991 20
- $1,812 20
Add to this cash received....................... 4,300 23
Total....... ,............................$6,112 43
Deduct this amount from $6,432.42, and we have $319.99, the amount which is a lien against the building.
It is contended that section 7166, Revised Codes, giving lien claimants an attorney’s fee, is unconstitutional. This court in Wortman v. Kleinschmidt, 12 Mont. 316, 30 Pac. 280, held a similar statute valid. Since that case was decided, however, the supreme court of the United States in Gulf etc. R. Co. v. Ellis,
The order denying a new trial is affirmed, and the cause is remanded to the district court of Missoula county with directions to modify its judgment against Olsen & Johnson by deducting therefrom the sum of $162.91. The balance is affirmed. That part of the judgment relating to the lien upon the building
Modified and affirmed.