90 Va. 523 | Va. | 1894
delivered the opinion of the court.
This suit grows out of a contract, under seal, between the said Mills & Fairfax, plaintiffs, and the Norfolk & Western Eailroad Company, defendants, dated the'1st day of February, 1887, whereby the plaintiffs agreed with the defendant to build a certain specified portion of the Elkhorn branch of the Flat Top extension of the said defendant’s line of railroad, including the tunnel through the"Flat Top mountain on the “ No. 3 ” coal bed.
The said, contract is very voluminous, but the whole controversy depends upon. the.price-to be paid for the excavation of certain sections of the tunnel, according to the specifications in said contract especially relative thereto; the plaintiffs maintaining, that they are entitled, by the express terms and intendment of the said contract, to $3 50 per cubic yard, instead of $1 75, the amount or price allowed to them. And this suit is to recover the difference between these prices, for the work done, and admittedly well, and acceptably, done, by the .plaintiffs for the defendant, under the contract, amounting to the sum of $23,100, and the reserved per centum retained, viz: $9,'709 20.-
There was a coal vein running through the Flat Top mountain,
“ Payment is to be made by the party of the second part for work done and materials furnished under this contract, on or aboutthe 15th of each month, upon proper estimates rendered on the last day of the preceding month for the work done and the materials furnished during the preceding month, to the extent of and not beyoud 85 per cent of the amount of such estimates; and such monthly estimates, to be valid, must be accompanied by
“IV. When the engineer in charge has furnished his certi-cate that all the work embraced in this contract has been completed agreeably to the specifications and in accordance with the directions and to the satisfaction and acceptance of the said engineer, there shall be a final estimate made of the quality, character, and value of said work, according to the terms of this agreement; when the balance appearing due to the said parties of the first part according to the certificate of said engineer, shall be paid to them within thirty days thereafter, upon their giving a release under seal to the party of the second part from all claims and demands whatsover, growing in any manner out of this agreement, and upon their procuring and delivering to the party of the second part full release in proper form and duly executed, for mechanics and material men, of all liens, claims, and demands for materials furnished and provided, and work and labor done and performed upon or about the work herein contracted for under this contract.”
It is alleged in the declaration that the “ No. 3 ” coal bed did not only become of a less thickness than four feet, exclusive of the slates, &c., but that it entirely disappeared from the tunnel for the distance of 1,200 lineal feet, equal to 13,200 cubic yards; and that this fact is evidenced by the profile of the tun
And this contention of the Norfolk & Western Railroad Company, the defendant, is approved and sustained by the order of the circuit court of Roanoke city complained of, and now under review — which dismisses the plaintiffs’ suit on demurrer, without any investigation of the merits of their claim.
The grounds of the demurrer to the plaintiffs declaration, and to each count thereof, as stated in the brief of the appel-lee’s counsel, are: 1. “ Because the contract between the parties makes the estimates and certificates of the engineer as to the amounts due under the contract conclusive and binding
This ground of demurrer is neither true nor tenable. The contract makes the parties fix the price at $8 50 per cubic yard: “ If the 3 oal bed should become of a less thickness than, four feet, exclusive of slates and coal not usually mined in run of mine coal in adjoining collieries, this will entitle the contractor to a price of $8 50 per cubic'yard for the entire section of the tunnel, instead of the prices for coal and other excavations mentioned herein.” And the contract, so far from leaving the price to the estimate or discretion of the engineer, guarded by and imperatively,provides “there shall be a final estimate made of the quality, character, and value (not price per measure) of said work, according to the terms of this agreement: thus making the terms of the contract imperative upon the engineer, as the fixed basis of his calculation of the amount or value of the work according to the price fixed by the contract. There is no dispute or question as to the quality or character of the work, or as to its completion to the approval, satisfaction, and acceptance of the engineer: but the predication is, that, though the price is fixed by the contract, it emasculates itself — commits felo de se — and makes the engineer the absolute, final and arbitrary dictator of the price, or rate of compensation, which the contractors shall receive; and which, only, his principal shall pay. Even if this absurdity can be predicated of the monthly estimates provided for by the 3d section of the contract, there is nothing, whatever, said in the 4th independent section, as to the finality and binding force of the engineer’s decision or estimate; nor, indeed, is there any provision that-the engineer, as such, shall make any estimate. The provision
It is expressly, distinctly, and positively charged in the declaration, that both the monthly and final estimates, made by the engineer of the company, were not made according to the terms of the contract; but were made in open and direct violation of the terms and intendment of the agreement under seal between the parties. That, by the estimate of the engineer, the price of $3 50 per cubic yard, fixed by the agreement, for the section of the tunnel in which the coal bed No. 8 became of less thickness than four feet, (and, in fact, wholly disappeared from the said tunnel,) was altered by the engineer and put at $1 75 per cubic yard; and that, in so doing, the said engineer made a mistake so gross as to amount to a fraud upon the plaintiffs, depriving them of the enormous sum of $23,100, to which they are justly entitled under the contract. The second count is like the first, except that, instead of charging that the estimates and certificate of the engineer were a mistake so gross as to amount to a fraud, it alleges that “the engineer, at the time said certificate and estimates were made, knew that the said ‘ No. 3 ’ coal bed not only became of a less thickness thau four feet, as aforesaid, but entirely disappeared, which said conduct on tlio part of the said engineer is a fraud upon the rights of the said plaintiffs.” .
The third count is like the others except that, instead of charging mistake, as in the first count, and. fraud, as in the second count, it charges that in making said certificate and estimates the said engineer did consult, confer, and advise with certain officers and employees of the said defendant company,
The second count charges that the estimate and certificate of the engineer are founded on falsehood and a fraudulent perversion of fact, and are therefore not conclusive or final; that the engineer knew that the coal bed No. 3 had, in fact, wholly disappeared from the tunnel excavation, when he inferentially certified that it had continued to be four feet thick in the tunnel, by estimating and certifying that the plaintiffs were entitled to ouly the price of $1 75 per cubic yard instead of the price of $3 50 per cubic yard fixed by the contract to be their due if the coalbed, No. 3, should become of less thickness than four feet in the course of the tunnel. And this action of the engineer is charged to be actual fraud, and a deprivation to them of $23,100 of their just dues under the contract fully performed by them.
The third count charges such misconduct on the part of the engineer as would vititate and set aside an award in ordinary arbitration case, and, a fortiori, in this case.
These counts are all good and sufficient; and the court erred in sustaining the demurrer and denying to the plaintiffs the opportunity to make good their allegations by proof.
But, even though no fraud, mistake, or misconduct is alleged in the declaration, still it is alleged that the estimates and certificate of the engineer are not within the terms of the submission, but are in violation of the contract; and are, for that reason, void and inconclusive. The declaration alleges, that the contract fixed the compensation of the plaintiffs, under the circumstances admitted, at $3 50 per cubic yard, and that the estimate of the engineer fixed the compensation at $1 75 per cubic yard. If this be true, the engineer has exceeded his authority and abrogated the contract between the parties.
The second ground of demurrer is, that “ the plaintiffs show
The principle is, that, if the estimates are proper and show the correct amount due, the release must be tendered to entitle the contractors to recover: but if, on the contrary, the estimates, are .not correct because fraudulent, or because not within the terms of the contract, the tender of a release is not necessary. The reason for the failure to tender the release is alleged in the declaration to be the refusal of the defendant to pay the amount due; and because fraud is charged in the declaration. And the declaration further says that all the mechanics and material men employed by said work, or having any claim or demand in reference thereto, have long since been fully paid, and that the time has long since expired, within which such mechanics and material men could assert any liens, claims, or demands upon or against said work, or upon or against said defendant; and, in fact, no such liens were ever filed or asserted. The plaintifis must be allowed the opportunity to prove their case made by their declaration; and the circuit court of Eoa-noke city erred in sustaining the demurrer to the declaration, and to the several counts thereof.
For the foregoing reasons we are of opinion that the judg7 ment of the circuit court of Eoanoke city complained of is erroneous, and the same must be reversed and annulled; and the case will be remanded to the said court for further proceedings upon the merits.
JüDGMENT REVERSED.