OPINION OF THE COURT
Defendant Andrew R. Mancini Associates Inc. (hereinafter defendant) was hired as a subcontractor to perform improvements on a building owned by Cornell University in the City of Ithaca, Tompkins County. After obtaining this job, defendant entered into an agreement with plaintiff whereby plaintiff was to furnish defendant with all materials required to complete the project. Athough plaintiff also agreed to furnish all field measurements that were required, these measurements were eventually provided by defendant for reasons disputed by the parties. Plaintiff used these figures to determine the quantity of tachable wall panels that were to be shipped to defendant.
The first shipment of panels was delivered in August 1988. Defendant notified plaintiff that they were the wrong size and that there was inadequate Velcro adhesive attached to them. Despite these complaints, plaintiff invoiced the shipment approximately one month later and defendant made the payment within two months of its billing. Thereafter, the second and third shipments were delivered together in October 1988 and invoices were sent out approximately one week later. After requesting and receiving additional information from plaintiff regarding calculation of the square footage delivered, defendant paid the invoices. Plaintiff delivered the final shipment of panels in early January 1989 and invoiced it shortly thereafter. Defendant retained this invoice for approximately six weeks before sending a letter of protest to plaintiff stating that there was a discrepancy between the square footage of panels received and the amount invoiced. Defendant requested a refund of this alleged overcharge and payment for labor purportedly required to reinstall panels with additional Velcro.
Thereafter, plaintiff commenced this action seeking payment for the final shipment of panels delivered to defendant. Defendant answered and interposed a counterclaim for damages. The parties then cross-moved for summary judgment.
Initially, defendant contends that Supreme Court improperly granted summary judgment to plaintiff on its claim for the final shipment of 664 square feet of wall panels that defendant accepted but did not pay for. We must agree. Because the instant action involves the sale of goods, we must look for guidance to UCC article 2. Notably, rejection of nonconforming goods must take place within a reasonable time after their delivery and reasonable notice must be given to the seller (UCC 2-602 [1]). Acceptance takes place when the buyer informs the seller that the goods are conforming, or that in spite of their nonconformity they will be retained, or fails to reject them after a reasonable opportunity to inspect them or acts inconsistently with the seller’s ownership (UCC 2-606 [1]).
Here, plaintiff put forth admissible evidence that defendant used all the panels delivered to the job site and paid for 3 of 4 shipments. Significantly, defendant admitted that it never rejected any of the panels and indeed did use them at the job site. In fact, defendant does not seriously dispute that acceptance of the goods occurred. This apparent acceptance would normally obligate defendant to pay the contract price for the goods (see, Zappala & Co. v Pyramid Co.,
Next, as indicated, we conclude that Supreme Court inappropriately dismissed defendant’s counterclaim for damages. Defendant’s counterclaim alleged that plaintiff failed to perform its contractual obligations by not performing the field measurements for the site, allegedly delivering unsatisfactory
With respect to the field measurement controversy, we note that plaintiff avers that it tried to perform these obligations but was prevented from doing so by the fact that defendant did not have the job site ready. As a result, plaintiff claims that defendant eventually agreed to voluntarily perform the measurements. In contrast, defendant’s president avers that it repeatedly requested plaintiff to do the work and only did so itself as a last resort. Defendant also claims that it had to pay laborers extra to do plaintiff’s work. As for the allegedly nonconforming wall panels, plaintiff acknowledges that there was a problem, but asserts that it provided the additional Velcro at no cost to defendant. Defendant disputes this claim and asserts that it requested additional Velcro, but that plaintiff failed to provide it. Therefore, defendant allegedly had to procure its own Velcro and again pay for extra labor to perform the work. Finally, regarding defendant’s claim that plaintiff charged it for more square footage than was actually delivered, we note that plaintiff states that it arrived at its figures by using the "rounding up” method standard in the industry and that this method was explained to defendant. However, defendant denies being told of this method and claims that the method it used to perform the calculations is correct.
Clearly, these issues all presented questions of fact that would more appropriately be resolved at trial as opposed to on a summary judgment motion (see, B-S Indus. Contrs. v Town of Wells,
Mikoll, J. P., Yesawich Jr. and Crew III, JJ., concur.
Ordered that the order is modified, on the law, without costs, by reversing so much thereof as granted plaintiffs motion for summary judgment against defendant Andrew R. Mancini Associates Inc. and dismissed said defendant’s counterclaim; motion denied; and, as so modified, affirmed.
