144 N.Y.S. 351 | N.Y. Sup. Ct. | 1913
This action- is brought to foreclose a mechanic’s lien for a balance claimed to be due under a contract for installing certain heating apparatus in a house erected by the defendants. The defendants proposed the erection of a house, drawing their own plans for the building. These plans, so far as prepared, only showed in a general way the size of the house and the arrangement and size of the various rooms of' the dwelling. They did not show -any arrangement of the heating apparatus, and there were no specifications of any kind touching those matters. Carl Winters, the husband of the defendant, took these general plans to the plaintiffs, who are plumbers and engaged in putting in heating apparatus. He stated he proposed to build a house of the character shown, and asked for figures on the heating and plumbing. In a few days after this, the plaintiffs sent Winters the following letter:
“M/20/10.
“Mr. C. Winters, Tonawanda, N. Y.—Dear Sir: We will agree to furnish the following fixtures and do all sewering inside of house for the connection of those fixtures, also leaving connections for four conductors; for 1. 5 ft A. bath tub 1. Lowdown washdown closet,
1. Hopper “
1. 18x30 A. White Enam. Sink 1. 22 “ “ “ “ Basin.
“All the bath room fixtures to have N. P. pipes and traps above the floor and the sink to have N. P. Bibbs. The hot water boiler to be 40 gallon and connected with the other fixtures to hot and cold water pipes. The heating boiler to be an 18-2 W. Niagara boiler,-and the radiation to be three col. 38", to the amount) of 325 feet. The boiler and all piping in cellar to be covered with asbestos covering and the radiators to be neatly bronzed. The plumbing and heating as above to be done in a workmanlike manner and for the sum of three hundred and eighty (§380) dollars.
“Respectfully yours, Miller Plumbing Co.”
Winters later called on the plaintiffs and told them that the job was theirs. That constituted the transaction so far as the agreement of the parties is concerned- The plaintiff supplied the parts contracted for, and connected them up with the necessary piping. When, however, it was attempted to operate the heating system installed, it would not heat the house, and it was impossible to maintain the temperature of the rooms to a degree of warmth necessary to be comfortable in ordinary cold weather. In other words, the system as installed failed to properly work, and, in order to make it work, it became necessary to tear out and rearrange the piping, change the position of some of the radiators, and also to supply some additional radiation. When this was done, the heating worked properly. The necessary expense of making these changes the defendants seek to counterclaim against the plaintiffs. The defects complained of go to the system or arrangement
The plaintiffs contend that they supplied everything they contracted to supply, and there is no express warranty that the system installed would heat, and that the law will not infer any implied warranty or guaranty that it would work, and therefore the counterclaim cannot be upheld.
On the other hand, the defendants contend that they were not familiar with what was required to properly heat the house in question, and left those matters entirely to the knowledge and judgment of the plaintiff, not presuming to say or dictate as to how the result should be accomplished. That there was not only an express warranty of good workmanship which covers the defects complained of, but, if the warranty is not broad enough to cover defects as- to the system, the law will imply such a warranty.
I reach the conclusion that the plaintiff is entitled to a lien on the premises described in the notice for the sum of $127.73, less the sum of $60 allowed upon the defendants’ counterclaim, leaving a balance due the plaintiffs of $67.73. Inasmuch as each party has prevailed in part, no costs of this action are allowed to either party.
Let a decision be drawn in accordance with the views above expressed.