57 Pa. Super. 14 | Pa. Super. Ct. | 1914
Opinion by
The contract of the plaintiffs with the defendant as shown by the plaintiffs’ proposal of March 7, 1910, and the acceptance thereof by the borough on March 15, 1910, embraced three subjects: (1) compensation at the rate of $200 per year for “routine engineering work of streets and sewers;” (2) disposal plant construction for which compensation was to be allowed at the rate of two and one-quarter per cent of the cost; (3) for other construction work two and one-quarter per cent for plans and specifications and two and one-quarter per cent for engineering and superintending construction complete. The contested part of the plaintiff’s claim is for compensation under the third paragraph of the contract, the work performed being the preparation of plans and estimates
The stipulation filed at the argument by the learned counsel for the respective parties relieves- us from a determination of the question of practice raised by the appellant with respect to the action of the trial court, in reducing the amount of the judgment to the extent of the plaintiffs’ claim for compensation for plans and estimates on the thoroughfare, in entering judgment on a motion for judgment non obstante veredicto in favor of the defendant. Our understanding of that stipulation is that if this court should not be of the opinion that the plaintiff is entitled to a verdict for the compensation claimed for the plans and specifications under the pleadings the judgment may be affirmed without regard to the regularity of the modification of the verdict. This leaves the way open to the plaintiffs to proceed in an action of assumpsit on a quantum meruit if they are entitled to recover anything.
The judgment is affirmed.