Thе pleadings reveal the following: plaintiffs, Ms. Miller (d/b/a Paragon Plus) and Ms. Kellar, axe two young women who run a small painting subcontracting firm. In September 1993, Ms. Miller, the proprietor of the firm, executed a contract with defendant Two State to paint three separate La Quinta Inns as part of La Quinta’s “Reimaging” project. Two State was the general contractor for the three inns identified in the painting contract. Plaintiffs were the only female subcontractors on the project. Throughout their work, plaintiffs were subject to rude, disparate treatment, i.e., Two State’s employees made lewd remarks regarding them, to the effect that they had traded sexual favors to obtain the contracts; and Two State’s emрloyees “grabbed” the women’s buttocks, and “spanked” them with project notebooks. In general, plaintiffs were treated as inferior to the male contractors.
Additionally, a dispute as to the scope of the work had arisen. The сontract documents called for the paint in most areas of the inns to be applied “full coverage, single coat” [or “one coat”]. In compliance with this language, Ms. Miller had her painters apply a full, but single, coat of paint to the appropriate areas. The result did not suit the owner, and the painters were instructed to apply a second coat. This additional work almost doubled the amount of work that the painters had to perform, but Two State refused to concede that it owed plaintiffs for the additional work. Two State did not execute a change order for the extra work, as the contract Two State drafted required.
Furthermore, as the work progressed, Two State сeased making progress payments and began trying to run Ms. Miller and Ms. Kellar off the project. Two State wanted to keep the “men” painters. This conduct further led to Two State’s employees seizing the business property of Ms. Miller, and seizing the personal property of both plaintiffs. Additionally, Two State reported Ms. Miller to the Charlotte police for stealing a sprayer. Two State took the police to the women’s hotel room, and publicly accused them of lаrceny. After talking with plaintiffs, the police told the Two State employees to leave the premises without the sprayer.
Plaintiffs filed suit in the General Court of Justice on 2 March 1994. In their complaint they sought damages for breach of contrаct, quantum meruit, bad faith, unfair trade practices, slander, conversion, battery and punitive damages. Two State reacted by filing its own demand for arbitration on 22 March 1994 with the American *414 Arbitration Association in accordance with Article 8 of the contract. Two State did not seek to stay plaintiffs’ action. Plaintiffs moved to stay Two State’s demand for arbitration.
Judge William Z. Wood, Jr. entered an order granting plaintiffs’ motion for a preliminary injunction prohibiting arbitration and staying all further arbitration proceedings in the case. Judge Wood concluded that the building construction contract between the parties was an enforceable contract providing for binding arbitration of all claims, disputes or other matters in question аrising out of or relating to the contract. Judge Wood concluded that the arbitration provision “is unconscionable and unenforceable under N.C.G.S. § 22B-10.” Judge Wood further concluded that the arbitration provision in the contract violated Artiсle I § 18 of the North Carolina Constitution as well as Article I § 25 of the North Carolina Constitution. From this order, defendants appeal.
This appeal by defendants is from an order staying arbitration; as such, it is an interlocutory appeal. An “order denying arbitration, although interlocutory, is immediately appealable because it involves a substantial right which might be lost if appeal is delayed.”
Bennish v. N.C. Dance Theater,
North Carolina Genеral Statutes § 22B-10, which became effective 1 October 1993, provides:
Any provision in a contract requiring a party to the contract to waive his right to a jury trial is unconscionable as a matter of law and the provision shall be unenforceable. This section does not prohibit parties from entering into agreements to arbitrate or engage in other forms of alternative dispute resolution. (Emphasis added.)
*415 In the instant case, the parties entered into an agreement whiсh provided:
All claims, disputes and other matters in questions arising out of, or relating to, this Subcontract or the breach thereof shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Associаtion. This agreement to arbitrate shall be specifically enforceable under the prevailing arbitration law. The award rendered by the arbitrators shall be final, and judgment may be entered upon in accordance with applicable law in any court having jurisdiction thereof.
This agreement was enforceable under North Carolina General Statutes § 1-567.2 (1983) which states:
(a) Two or more parties may agree in writing to submit to arbitration any controversy existing between them at the timе of the agreement, or they may include in a written contract a provision for the settlement by arbitration of any controversy thereafter arising between them relating to such contract or the failure or refusal to perform the whоle or any part thereof. Such agreement or provision shall be valid, enforceable, and irrevocable except with the consent of all the parties, without regard to the justicia-ble character of the controversy.
The parties to the contract in the instant case agreed to submit any disputes for arbitration. Accordingly, an agreement to arbitrate exists. Plaintiffs argue that enforcing an agreement to arbitrate limits access to the courts. This argument is without merit. Once an agreement to arbitrate is found, courts should compel arbitration on a party’s motion and then “step back and take a ‘hands-off’ attitude during the arbitration proceeding. The trial court then reenters the dispute arena to confirm, modify, deny or vacate the arbiter’s award.”
Henderson v. Herman,
An agreement to arbitrate does not cut off a party’s access to the courts. On the contrary, an action compelled to arbitration must have the arbiter’s deсision confirmed by the court. . . . The ACT [Uniform Arbitration Act, Article 45, North Carolina General Statutes §§ 1-567.1 through 1-567.20] provides parties with a means to bypass the morass of judicial litigation, while still main- *416 taming the judicial doors ajar for recalcitrant disputes. Hencе, it would appear that the legislature intended the courts to send certain predetermined issues to arbitration and then to step back until the arbitration proceeding is complete.
Id.
at 485,
North Carolina has a strong public policy favoring arbitration of disputes between parties.
Servomation Corp. v. Hickory Construction. Co.,
An agreement to arbitrate a dispute is not an unenforceable contract requiring waiver of a jury; thus, the trial court erred in concluding that because the arbitration provision did not provide for trial of facts by a jury that it was unconscionable and unenforceable under North Carolina General Statutes § 22B-10, and in violation of Article I §§18 and 25 of the North Carolina Constitution.
Although our Courts have not explicitly said that arbitration violates the North Carolina Constitution in that it deprives parties of their right to a trial by jury, this Court in
Bentley v. N. C. Insurance Guaranty Assn.,
In arguing against enforcement of the arbitration clause, [plaintiffs] attempt to appeal to “the old judicial hostility to arbitration.” ... Over time ... the judicial view of arbitration has evolved from hostility to eager acceptance. In part, the сhange has been *417 fostered by a recognition of the efficiency and specialized expertise available in an arbitral forum. . . .
... In short, the public policy of this state favors the resolution of disputes through arbitration.
Bentley,
Plaintiffs next argue that defendants waived arbitration. Plaintiffs base their waiver claims on the fact that defendants withheld payments, seized plaintiffs’ property, barred plaintiffs from the project, and sought to have them arrested. In addition, plaintiffs say that defendants’ delay in seeking arbitration should act as a waiver, and that dеfendants should be estopped from enforcing the provision.
Our Supreme Court in Cyclone Roofing Co. v. Lafave Co. stated:
Waiver of a contractual right to arbitration is a question of fact. Because of the strong public policy in North Carolina favoring arbitration, courts must closely scrutinize any allegation of waiver of such a favored right. (“[A]ny doubts concerning the scope of arbitrable issues should be resolved in favor of arbitration whether the problem at hand is the construction of the contract language itself or an аllegation of waiver, delay, or a like defense to arbitrability.”) Because of the reluctance to find waiver, we hold that a party has impliedly waived its contractual right to arbitration if by its delay or by actions it takes which are inconsistent with arbitration, another party to the contract is prejudiced by the order compelling arbitration. (Citations and footnote omitted.)
Because we hold that North Carolina General Statutes § 22B-10 does not invalidate arbitration in the instant case, we need not address the other issues raised by defendants. The agreement in the instant case is a valid written agreement to arbitrate disputes according to North Carolina General Statutes § 1-567.2. Thus, the trial court erred in staying arbitration. The decision is reversed and remanded.
Reversed and remanded.
