delivered the opinion of the court:
Defendant Reed appeals from a decree awarding plaintiff Miller a mechanics’ lien against co-defendants Reed and Payne and from a decree awarding counterplaintiff Payne a judgment against counterdefendant Reed.
Plaintiff-contractor Miller (hereafter called “contractor”) entered into an oral contract with defendant Payne (hereafter called “tenant”), although not actually a tenant but rather a person in possession of premises under an arrangement with the owner to do certain electrical work on defendant-owner (hereafter called “owner”) Reed’s premises. Tenant and owner agreed to lease certain property for the operation of a restaurant and tavern after certain improvements were made. No written lease was entered into, and no period of time for the lease was agreed upon, but rent was agreed to be $175 per month. Owner provided the work which he had agreed to do, and gave tenant keys to the premises so that tenant could do the work he had agreed to do. Tenant orally contracted with contractor to do the electrical work. Contractor performed some of the work with owner’s knowledge and approval. Contractor performed general work until he felt he could go no further without more specifications as to the particular equipment that would be instaHed. After several more months had passed, owner leased the premises to another person for $250 per month. Contractor brought an action against both tenant and owner. The circuit court filed a memorandum opinion finding that the contract was not permitted to be completed “due to the delay and düatory action of the co-defendants and each of them” and that “defendant Payne’s delay was compounded by action of defendant Reed in obtaining another lease without notice, preventing the plaintiff MiHer from completing the contract.” The court awarded a mechanics’ lien in favor of the contractor in the amount of $1738.96, representing the value of the approximately 50% of the agreed work which had been completed, and awarded a judgment to counter-plaintiff-tenant in the amount of $869.48 based on the enhanced value of the owner’s premises in the event the tenant subsequently be required to pay for the total cost of the improvements.
Owner first contends that the tenant did not have such an interest in the property as would give rise to a mechanics’ hen. The applicable statute is section 1 of the Mechanics’ Lien Act (Ill. Rev. Stat. 1971, ch. 82, par. 1):
“Any person who shaH by any contract or contracts, express or impfied, or partly expressed or implied, with the owner of a lot or tract of land, or with one whom such owner has authorized or knowingly permitted to contract for the improvement of, * * * shaH be known under the Act as a contractor, and shall have a Hen upon the whole of such lot or tract of land * * * for the amount due to him for such material, fixtures, apparatus, machinery, services or labor, and interest from the date the same is due. * * *” (Emphasis added.)
The object and purpose of the Mechanics’ Lien Act is to protect those who in good faith furnish material or labor for the construction of buüdings. While the statute must be strictly construed with respect to aH matters on which the lien depends, the courts have held that after the Hen claimant has complied strictly with the statutory requirements to establish a Hen, then the court should give the statute a liberal construction so that justice wiH be done between the parties. The suit is one in equity and equity principles apply. Gunther v. O’Brien (2d Dist. 1937),
Owner claims that tenant Payne lacked a sufficient interest in the property to contract for a mechanics’ hen because he was in possession of the premises in the capacity of a tenant at sufferance, citing Proctor v. Tows (1885),
Owner next contends that the contractor’s failure to render substantial compliance with the contract by virtue of his non-completion of the contracted-for work means that no mechanics’ Hen can attach. NormaUy, it is a prerequisite to a mechanics’ Hen that the contractor complete performance of the contract. (See Love Mechancis’ Liens in Illinois, par. 58, at 129 (1931).) In Gottschalk Construction Co. v. Carlson,
“The contract is the basis of the Hen and to maintain a mechanics’ Hen suit, petitioner must show either performance or excuse for non-performance which must result from the owner’s breach of contract.”
In the present case the plaintiff-contractor completed only approximately one half of the work. However, the trial court found that the contract was not permitted to be completed “* * * due to the delay and dilatory action of the co-defendants and each of them.” This is an excusé for non-performance within the meaning of the quote from Gottschalk.
Furthermore, section 4 of the Mechanics’ Lien Act (Ill. Rev. Stat. 1971, ch. 82, par. 4) provides that a contractor who is prevented from performing his contract by default of the owner shaU be entitled to enforce bis Hen for the value of what has been done. Although the trial court found both the owner and tenant at fault here, we observe that the hen would be equally valid if the tenant was the only party who prevented completion of the contract. In Cooper v. Palais Royal Theatre Co. (1926),
Owner next contends that the items instaUed by the contractor were “trade fixtures” which are not lienable. Trade fixtures are not lien-able improvements even though they may be attached to the building at least in part. Our supreme court in Fehr Construction Co. v. Postl System of Health Building (1919),
Owner’s final contention is that the trial court improperly decreed an “equitable lien” against his property in favor of tenant. However, the pertinent part of the court’s order stated:
“IT IS FURTHER ORDERED that in the event that Defendant, Tommy Payne, Jr., becomes liable or pays the entire judgment, either by virtue of deficiency or sale of the property under this Decree or by payment of said amount in the first instance of said judgment, he shall be entitled to recover from Defendant, Guy D. Reed, the sum of $869.48.”
It is readily apparent that this order did not create or impose an equitable lien.
Finding no error, we affirm the decree of the Circuit Court of Franklin County.
Decree affirmed.
EBERSPACHER, P. J., and CREBS, J., concur.
