211 Pa. 127 | Pa. | 1905
Opinion by
There was ample evidence submitted to the jury to justify
The learned counsel for the defendants, however, insist in their argument that there was no evidence to support the contention that the accident was caused by the improper mixing of the concrete or premature removal of the centres. The concrete used in this building was composed of certain proportions of cement, cinders and sand. Improper mixing results in “voids” which are open spaces in the body of the concrete and weaken the material. The more numerous the voids the weaker the concrete necessarily is. Essick, the city building inspector, examined the concrete immediately after the roof and wall fell. He testified that it had not been properly mixed, was full of voids, and that none of it had the proper set. It also appeared by the testimony that the concrete was not inspected by any person after it was made by the laborers ; and as to the care with which they prepared it, one of the laborers testified that “ the quicker they mixed it up the more time we would have to ourselves.”
There was likewise sufficient testimony to go to the jury on the question of the negligent removal of the “ centres.” They were placed under the entire roof. The work of laying the concrete and tamping was begun Wednesday afternoon and finished Thursday morning. On the following day, Friday, according to the testimony of Branson, the defendants’ employee, the “ centres ” were removed from the north end of the building where the roof fell on the following Monday afternoon causing the death of the plaintiff’s husband. The roof at the south end of the building, from which the “ centres ” had not been removed, remained intact. The testimony of the defendants’ own witnesses shows that the “ centres ” should not have been removed • in less than three or four days after the cement had been laid, while the testimony of the plaintiff’s witness leads to ‘the belief that a longer time should have elapsed, one
Under this and other testimony in the case, it was clearly a question for the jury to determine whether the defective concrete and premature withdrawal of the “ centres ” caused the roof to fall, which resulted in the death of the plaintiff’s husband. If the testimony alluded to is credible, the “ centres” should have remained in position for at least three days to support the weight of the floor. The tamping and additional weight of the heavy material placed on the roof for constructing the drainage grade required that the “ centres ” should continue in place much longer. There is also the significant fact, in support of the verdict, that only that part of the roof fell from which the “ centres ” had been removed. It is true that one of the plaintiff’s witnesses testified on cross-examination that the absence of tie-rods between the I beams permitted the arches to flatten and push the wall out and that caused thfe accident. This, like the other testimony introduced to establish the cause of the accident, was submitted to the jury who were distinctly told by the court in affirming a point that “ if '.you find that the accident resulted from the absence of tie-rods, .... your verdict inust be for the defendants.” They were also instructed that “ if you, after examining all the reasons, cannot find what did produce the effect, then the defendants are not to be charged, because negligence must be affirmatively proved.” The jury, therefore, found that the accident was not caused by the absence of tie-rods, but by the improperly prepared concrete and premature removal of the “ centres ” from the part of the floor which fell.
It is further contended by the defendants that Miller was guilty of contributory negligence, that he knew the conditions at the place of the accident and assumed the risks; and further, that defendants’ employees acted under his supervision and according to his instructions in performing the work. The learned court, however, left these questions, with proper instructions, to be determined by the jury. He told the jury there could be no recovery if Miller participated in or supervised the preparation of the concrete, or the “ centres ” were removed at the request or by direction of Miller, or he had knowledge of their removal, and that “ if Wilbur Miller really acted so that these
It is also contended by the defendants that they were the agents of the Bell Telephone Company to obtain the workmen and furnish the material for the work to be done, and that Miller was the agent of the telephone company to direct the workmen in the use of the material, and hence, he and the employees of the defendants were fellow servants of a common master, the telephone company. It is, therefore, claimed by the defendants that the relation of independent contractor did not exist between them and the Bell Telephone Company which employed them to construct the floors and roof of the building. As we have seen, the jury found that Miller did not supervise the mixing of the concrete or direct the defendants’ workmen in laying it or in removing the “centres.” Those were questions for the jury: Pender v. Raggs, 178 Pa. 337. It is contended, however, that under the contract with the defendants this authority was vested in the telephone company and its employee, Miller, and that, therefore, the defendants were not independent contractors. If the telephone company stood in relation to the defendants of master and servant or principal and agent, then the defendants are not liable for the injuries to Miller caused by the negligence of their workmen. If, on the other hand, the defendants were independent contractors, they are responsible for the negligence of their employees resulting in Miller’s death. The relation of the parties to each other must be determined from the contract which created it. The contract provides that, for the consideration of $2,549, the defendants shall furnish all the material and labor for, and erect, the floors and roof of the building in accordance with the revised plans and specifications within two weeks after notice to proceed with the work. If the defendants neglected to do tire work or furnish the materials in accordance with the agreement, the telephone company was authorized to do so at their expense, or to declare the contract forfeited and to reaward it, the defendants being liable for any damage caused by their default. The contract further provides that the telephone company should have the right to change any part of the plans of the building
The practical effect of the whole agreement, we think, is to authorize the defendants to furnish the materials and to do the work in constructing the floors and roof of the building according to their own method without being subject to the control or direction of the owner except as to the result to be obtained. In the performance of the work, therefore, the defendants were independent contractors and not servants of the owner: Hunt
The argument of the learned counsel for the defendants is devoted to a discussion of the refusal of the learned trial judge to affirm their point that under all the evidence the verdict should be for the defendants. It would have been error to affirm this point, as the case was clearly for the jury. It was submitted in a charge, full and explicit, and to which no exception was taken.
The judgment is affirmed.