Miller v. Benton

55 Conn. 529 | Conn. | 1887

Lead Opinion

Loomis, J.

The defendants hired of the plaintiff certain rooms for manufacturing purposes in a building owned by him, for a term beginning July 1st, 1884, and ending May 1st, 1887, at an agreed monthly rent, and entered into the occupancy of the leased premises. In October, 1884, the building was so damaged by fire that the rooms in question *543became untenantable, and the defendants were compelled to seek new quarters for the prosecution of their business, an immediate continuance of which was of great importance to them. The plaintiff, in January, 1885, began to repair the building, and on the 14th day of February following notified the defendants that it was repaired and that he should hold them responsible for any loss that he should sustain from their breach of contract. They refusing to occupy or pay further rent, the plaintiff brought suit for the breach of their contract, which the court below decided against him, and he brings the case before this court by appeal.

The court below made a finding of the facts, and the following appear as the special ones affecting the question. The plaintiff, on the 20th of October, 1884, two days after the fire, wrote the defendants that he should “ proceed with all reasonable dispatch to restore the premises to good condition ”; to which they replied on the same day that they should not again occupy the premises. On the next day the plaintiff wrote them that he should require them to reimburse him for any loss in consequence of their breach of the covenants of their lease. The plaintiff had several conferences with his architect as to plans for the reconstruction of the building and the architect drew two or three different plans, and the contract for the work was not signed till December 20th, and the work was not completed till February 14th, 1885. The court finds that if the work had been begun at once after the fire it could have been completed in two months from that time, and if all practical speed had been used it could have been done in six weeks'; and that “the restoration of the building was not begun within a reasonable time after the fire, nor, after it was begun, was it completed within a reasonable time.” After the plaintiff had completed the work of restoration he wrote the defendants on the 14th of February that the building was repaired and that he should hold them responsible for his loss of rent. To this they replied on the 16th of February—“ We herein give you notice, as we have *544done before, that we shall not again occupy premises Nos. 84 to 94 Temple st., and we shall pay no loss which you may incur by reason of your premises not being again occupied.” On the"first of January the plaintiff, without consulting the defendants, had made a written lease to a third party for sixteen months of a room that had been but little injured by the fire and was a part of the space that had been leased to the defendants, and had put the lessee into possession ; but at the time the defendants wrote their letter of February 16th, to the plaintiff, they did not know of this lease.-

The plaintiff claims to recover under the provisions of the statute originally passed in 1869, but which appears in the General Statutes of 1875, p. 354, sec. 17, as follows :

“The tenant of any tenement which may be, without his fault or neglect, so injured as to be unfit for occupancy, shall not be liable to pay rent after such injury, so long as such tenement is untenantable, if he continue to occupy, unless it be otherwise expressly provided by written agreement ; and in case of such injury he may quit possession of such tenement; but if the same shall become fit for occupancy during the continuance of his lease, he shall then pay the rent and may again occupy it.”

A question is made whether a leased room is a “tenement” within the meaning of this statute. We see no reason to doubt that it is. The terms used are “tenant” and “ tenement ”—two words applied, both in popular and legal usage, to parts of a building leased without the land upon which the building stands, as well as to an entire building. We think the term covers everything that may be occupied under a lease; everything for which an action for use and occupation would lie at common law.

The action is brought to recover damages for the defendants’ breach of their contract. But there was no breach of contract in their removal to new quarters, and none in their mere refusal in advance to pay any damage which the plaintiff might suffer from their non-occupancy of the premises. The case is unlike that of a party contracting to perform *545certain work and before the time arrives giving notice of his determination not to perform it. Here the defendants were to do no act. Their occupancy or non-occupancy did not affect their obligation to pay the rent. The plaintiff did not join with them in rescinding the contract. It was the mere case of a debtor declaring beforehand that he should not pay his debt when it fell due. This would not be a breach of his contract. The breach would be committed only when the debt became due and was not paid. A notice by a tenant that he will pay no more rent does not vary the relations of the landlord and himself. He owes no duty and can violate none till the rent becomes due, and then if it is not paid he can be sued for it. The only breach of contract by the defendants was when the building was repaired and they were notified of the fact and a month’s rent had fallen due and they had refused to pay it.

We have said that the plaintiff did not join with the defendants in rescinding the contract, and they of course had no power to do it without his assent. It is found that he accepted their conduct as a final breach of their covenants in the .lease, and “ accepted the premises, but did not intend thereby to in any way release the defendants from his claim against them for damages arising from said breach.” If this is to be construed as a rescinding of the contract on his part, which of course the conduct of the defendants would have justified, it would have left nothing of the contract as a basis for a recovery of either rent or damages. Ordinarily the surrender of leased premises by the lessee and the acceptance of them by the lessor would constitute a mutual rescinding of the contract of lease, and it would cease to exist for every purpose. But it is manifest that nothing of the sort was intended by the plaintiff here. He accepted the possession of the premises, but did not intend thereby to relinquish his right to damages. But his right to damages would be gone if he accepted the possession as a rescinding of the lease on his part. We must therefore qualify his acceptance by his intent in making it. It is to be observed that the statute provides expressly that *546the tenant, after such an injury to the tenement, may “ quit possession.” Of course when lie does so the possession falls to the landlord. It is also necessary that he should have possession for the purpose of making repairs. And the statute does not make the liability of the tenant depend upon his reoccupying. It says—“ if the same shall become fit for occupancy during the continuance of his lease, he shall then pay the rent and may again occupy.” In any case of the abandonment of leased premises by a tenant, especially with a declaration that he will never occupy again, the landlord must havé the fight to take possession for the purpose of caring for the property and of leasing it to others, and is not to be prejudiced by doing so. The rescinding the contract is wholly a matter of intent on his part, and that intent will not be inferred from his merely taking possession, especially Avhen it is found that he did so Avith no intent to relinquish his rights under the lease, even though he might conceive his right to be only to damages.

The suit is brought for the recovery of damages for the breach of their contract by the defendants, but Ave think the complaint, though drawn with reference only to a recovery of damages, yet contains all that is necessary under our Practice Act for the recovery of the rent that was due when it Avas brought.' It states all the important facts of the case—the lease, the occupancy of the defendants under it, ■the injury to the building by fire, the removal of the defendants from it, its reparation by the plaintiff, the notice of it given the defendants, their refusal to occupy, and their continued neglect and refusal to pay the plaintiff anything further. It is true that the complaint demands a certain sum as “damages,” but we think, under our present liberal practice, any sum due under any name upon the facts stated could be recovered. The plaintiff can therefore recover upon it whatever rent was due at the bringing of his action, unless his right of action is defeated by other facts in the case that are to be considered.

And we will .say here in passing that, although the land*547lord’s right to the renewed rent in a case like this is dependent upon the statute, yet it is not properly a statutory obligation that is created and which is to be declared on as such, but a contract obligation revived by the statute, and to be declared on as a contract obligation. It is very questionable whether it is necessary in the complaint to set out anything more than the contract, it being a matter of no importance, so long as the contract is in force, how it became so. If in the case of a ten years’ lease there had been a month’s interruption of occupancy and rent during the first year, and the lease had then been revived by the statute, it could not be necessary to set out this fact in every suit for rent during the whole ten years.

But the most serious question in the case is as to the legal renewal of the liability of the defendants for the rent, upon the special facts of the case. The statute provides for such a renewal of liability if the premises “shall become fit for occupancy during the continuance of the lease.” But it is clear that the reparation must be made within a reasonable time. The landlord must not be negligent in the matter. He must not let his tenant suffer from any want of activity on his part. Here the court finds that the building was not repaired within a reasonable time—both that the repairs were not begun within a reasonable time, and that when begun they were not completed within a reasonable time.

And it is further found that a lease was made on the 1st of January to a third party for sixteen months of a portion of the space that had been occupied by the defendants and which of course they would have had a right to demand if they had returned to the occupancy of the premises after their reparation. It is clear that by this lease the plaintiff had put it out of his power to restore the possession of the premises to the defendants, and they of course were under ■no obligation to accept a part.

Here are two facts, either of which would in ordinary circumstances have barred the plaintiff of all right of recovery. But we think the defendants had placed themselves in a position where they could not avail themselves of either *548of these facts. They had in the most emphatic manner declared to the plaintiff in writing, immediately after the fire, and this in reply to his notice that he should immediately repair, that they should not occupy the premises again. It is found that the plaintiff accepted their refusal to occupy again as a final one and as a breach of their contract. He had a right to take them at their word. Doing so, the question how rapidly he should push the work of reparation was one which they had no interest in. Indeed the longer he delayed the better it was for them, for it saved them from liability for rent during the period of delay. We think the finding of the court that the repairs were not made within a reasonable time has reference only to what would be a reasonable time in an ordinary case, where there was nothing to excuse the landlord from prompt action. It cannot therefore affect the case as it stands.

And under this notice from the defendants that they should not occupy again, the plaintiff had a right to make the lease which he did of a portion of the premises to a third party. The defendants cannot complain if he did the best he could with the property. It was directly for their interest, as they would have the benefit of whatever he might receive as rent. All the analogies of the law sustain this view.

It is to be noticed, as confirming the plaintiff’s understanding of the defendants’ letter of October 20th, as a full and final refusal to occupy the premises again, that in their letter of February 16th, in reply to his of the day before, they say—“We herein give you notice, as we have done before, that we shall not occupy,” etc., making it clear that their final refusal to occupy again was not founded upon anything that had occurred since the fire, but was wholly a carrying out of the purpose first expressed and ever since held. It is found that the defendants did not know at this time of the written lease of a part of the premises on the 1st of January, 1885. We take this to mean that they had no knowledge that any lease had been made. If, however, it means that their ignorance was merely of the written *549lease, and that they knew that the rooms had been leased, the case becomes the stronger against them, because, with knowledge of the lease, they did not refer to it as a reason for their refusal to occupy.

We think the plaintiff therefore entitled to recover whatever rent had accrued, and would have become due if the defendants had gone into occupancy, between the 14th day of February, 1885, and the last rent day before the 18th day of February, 1886, the day when the suit was brought, allowing in favor of the defendants whatever rent he had received from the premises from other parties.

There is error in the judgment appealed from and it is reversed.

In this opinion Park, C. J., and Pardee, J., concurred.






Dissenting Opinion

Carpenter, J.,

(dissenting). I am not satisfied that the notice given to the plaintiff by the defendants, that they would not again occupy the premises, ought to be regarded as a waiver of reasonable diligence. Assuming that the court has rightly construed the statute, (on that point I say nothing,) I think the plaintiff ought to be held to a strict compliance with all its provisions. One requirement, by implication, is that he shall restore the building in a reasonable time. This, it is expressly found, he did not do. It is true that a man will not ordinarily be heard to complain of a delay that does him no harm. But that is not the question. The plaintiff is seeking to take advantage of a somewhat arbitrary statute, and one which has or may have a harsh operation. The question is—is he in a condition to do so ? In order to do so must he not place himself wholly within its provisions? Is an excuse for not complying with it sufficient? Again. The defendants immediately after the fire did all they could to surrender the premises, and the “plaintiff accepted the conduct and declarations of the defendants as a final breach of all the covenants in the lease on their part to be kept and performed, and accepted the premises, but did not intend thereby to in any way release the defendants from his claim against them *550for damages arising from said breach.” The plaintiff then waited two months before contracting for re-building; on the 1st of January, 1885, six weeks or more before the building was completed, he let one of the rooms, which was formerly occupied by the defendants, and which was not destroyed by the fire, to another party for sixteen months; and after the new building was substantially completed, he let the rooms from time to time as he saw fit. Now all this satisfies me that the plaintiff accepted the premises when surrendered to him and elected to treat the lease as at an end. If so I am unable to see how it could be kept in force for the purpose of recovering either rent under the statute or damages.

Moreover, he had put it out of his power to allow the defendants to occupy the premises as before. Suppose they had desired and proposed to resume possession on the 14th of February, 1885, and the plaintiff had refused, as he must have done under his contract with others; how would the parties have stood then? Will it be contended that the plaintiff could then have recovered rent under the statute? If it be said that they did not offer to re-oecupy, my answer is that they were not bound to. A room which “ was a material part of the premises occupied by the defendants,” had been leased to others; the office had not been partitioned off; and the elevator was in no condition for use. So that the premises were not then in fact restored, and we cannot know that there has ever been a time when the defendants could have resumed the possession of the premises. An offer to resume would have been nugatory—not through the defendants’ fault, but the plaintiff’s. Must not the defendants then stand as they would have done if they had actually proposed to occupy the premises?

But aside from any offer to resume possession: the last clause of the statute is, “ he shall then pay the rent, and may again occupy it.” Before the plaintiff can avail himself of the statute he must put the property in such condition as that the defendants can occupy it. This seems too *551clear to require argument; and this, it must he conceded, he has not done.

In this opinion, Stoddard, J., concurred.

Hote. Occasional expressions in law treatises and opinions have left the question of the effect of the rescission of a contract in some doubt. The law dictionaries concur in defining a rescission as the “destruction, annulling, abrogating or making void of a contract.” It would seem clear that a contract thus annulled and made void cannot be made the basis of a suit for its breach. The books all agree that where one party would otherwise have a right to rescind the contract, he cannot do so where the parties would not by the rescission be left in statu quo. But this is no objection to a rescission by both parties. There is no limitation to their joint power to deal with their own contract. But where a contract is thus rescinded, and the parties are not left in statu quo, the necessary right of action to recover that condition accrues to one or both the parties ; and it is believed that the demands of the status quo are the precise measure of the rights of action that accrue upon the rescission of a contract.

Thus, one party contracts to buy and the other to sell a piece of land; the land is conveyed to the purchase!-, but before he has paid for it the parties rescind the contract. Here the purchaser has the title to a piece of land to which he has no right; the other party can sue for and recover it. A man is paid in advance for a horse that he is to deliver; before the deli vei'y the parties rescind the contract; here the proposed vendor has the price of the horse in his hands, bxit has no right to keep it. The other party can sue for money held to his use. There may be a right of action on both sides. The party who was to buy the land in the ease supposed may have paid in part for it. Here, on the l'escinding of the contract, the original owner of the land can recover it ixx a proper action, and the other party can x'eeover the money he has paid.

The reseindixxg of the contx'act does xxot, however, leave the case as if it never existed. It explains, gives character to, and sanctions whatever was done under it while the contract was in foi'ce. Thus the possession of land under a contract of purchase afterwards rescinded, retains the character that it had under the contract, and does not become a tenancy, though the original light of the owner revives and he can x'eeover the possession in an action at law. This point is involved in the reasoning of the court in Vandenheuvel v. Storrs, 3 Conn., 208, although that was not a case of a rescinded contract.

It is laid down in the books without qualification that a contract cannot be rescinded in part, but must be rescinded if at all in whole. Bouvier’s Law Diet., Rescission. One reason may be that the annulling of a part of the contract would be rather an altei’ation than a rescinding of it. But there would seem to be no good reason why a contract may-not be rescinded as to everything executory under it, and left good so far as it has been executed on both sides. Thus a policy of life insurance for a term of years may have run for a part of the term, the premiums have been regularly paid and the assui'ed have had full insurance for the time, and at last, under a claimed *552act of forfeiture, the insurance company may refuse to keep it in force, and the assured may join with them in rescinding the contract. Here there would seem to be no good reason why the assured should recover the premiums he has paid, having had their equivalent in a valid insurance. The case would of course be different if the insurance .were for the entire term of life, as here the premiums would be greater, and the excess would have gone to pay for the final payment of the policy, certain in this case and contingent in the other. The latter is essentially the case of Day v. Conn. General Life Ins. Co., 45 Conn., 480. Under the charge of the court below the jury returned a verdict for the assured for the full amount of the premiums he had paid. The Supreme Court reversed the judgment, holding that the action, based on an implied agreement of the insurance company to accept the premiums and keep alive the policy, could not be sustained, and it was not necessary for it to decide whether all the premiums could have been recovered back if the contract had been rescinded. It would seem as if, upon a mutual rescission of such a policy, the insurance company would have had as good a right to recover for the valid insurance they had furnished the plaintiff, as he would have to recover the money he had paid the company for the insurance. As the two sums would not balance, a part of the premium being for the future payment of the policy, there was no part fully executed by the parties which could be separated from the executory part, making a whole rescission necessary, if any; but this would have left the insurance company a right to recover for the insurance it had furnished, what it was fairly worth, either by a direct action or by a set-off against the suit of the insured to recover back the premiums paid. The correct principle would seem to be that the mutually executed part of a contract might stand, while the executory part could be rescinded, if they could be separated.

The rescission of a contract is spoken of in some of the books as a conclusion of law from acts of the party having the right to join in a rescission, even where he did not intend to rescind. But it is believed that the better, and most generally sustained rule is, that it is essentially a question of intention. There would seem to be no good reason why, when the intention of the parties is the great thing sought after in construing a contract, the real intention should not be the vital thing in construing acts that may be evidence of a rescission. Thus, an abandonment of a tenement by a lessee, with a declaration that he should never return,and possession taken by the lessor, has been given as an illustration of acts by the lessee which the law will construe as a rescinding of the contract by him. But such taking possession may have been an absolute necessity on the part of the lessor. His insurance policy would in most cases require the tenement, if a dwelling house, to be occupied. Such possession might be necessary for its care and protection. Its occupancy by a new tenant might be the lessor’s only practicable mode of protecting the property, and as all rent received would so far reduce the indebtedness of the original lessee, it would seem clear that such a reasonable and practically necessary course should not be construed as carrying with it an intention to rescind the lease. In the principal case the statute provides expressly that lessees, in case of an injured building, “ may quit possession,” and that after the building has been restored they “shall *553then pay the rent and may again occupy.” The defendants then did the plaintiff in that case no wrong in quitting possession, and after he had made the repairs their obligation under the statute was to pay rent. Their neglect to occupy could not affect this obligation. On their quitting possession, the possession necessarily reverted to the plaintiff, and remained in him necessarily until they returned and resumed occupation. It is difficult to see how this taking or holding possession on his part could be construed as a rescission of the contract independently of his intention. The correct principle must be that the intention of a party must be the principal factor in construing his acts in such a case.

The authorities seem to be ample that where a party refuses absolutely to perform a contract, the other party, without rescinding the contract, may take such a course as will preclude performance by the first party. Thus, a man contracts to render service as a servant for a year, and the master agrees to pay him a certain sum per month. The latter, before the year begins notifies the former that he shall not employ him, or after the year has begun dismisses him. Here the servant may hire himself to another person; indeed it is held in all the cases that he is bound to seek employment; and yet he is placing it out of his power to return to the first master’s service if the latter should change his mind and call for him. So I may contract with a builder to erect a house for me on my lot. He fails to begin the work and notifies me that he shall not do it. It may be a matter of the utmost importance to me that the house be built at once, and I am justified in making a contract with another builder to erect it. But by so doing I place it out of my power to allow the first builder to do the work if he should change his mind and offer to do it. The court applies that general rule to the case of premises leased and abandoned by the lessee. The lessor is not bound to rescind the lease, but may do the best he can with the property, both for its protection and to reduce the liability of the lessee.

There is a certain attitude in which a party may stand toward a contract and toward the other party that is entirely distinguishable from a rescission and yet so much like it as to have been sometimes mistaken for it. A builder who has contracted to erect a house for me, before the time for beginning on the work absolutely refuses to go on and perform the contract. I immediately contract with another builder to do the work. This I am justified in doing, not because the contract has been rescinded, for it has not been; but because I have a right to regard it as certain that the first builder will not perform his contract. This has sometimes been called an abandonment of the contract; but it is difficult to see the difference between an abandonment of a contract by both parties and a rescission by both. It is, and this is all that it is, an abandonment of all expectation on my part that the contract will be fulfilled. When the point is reached where, by reason of the refusal of the other party to perform, I have just ground for this abandonment of expectation, that is, for a certainty in my own mind that the contract will not he performed, I have a right to do the best I can for myself and my property, without in any degree relinquishing my rights under the contract. If this view be correct, as it seems clearly to be, it goes to show that the question whether a party has rescinded a contract is more a question of intent than of mere outward act.

*554The writer has undertaken merely to state what he believes to be certain general principles relating to the rescinding of contracts, and it does not fall within the purpose of this note to cite and comment on the very numerous and not entirely harmonious authorities on the subject.