269 S.W. 838 | Tex. App. | 1924
On November 18, 1922, R. W. Bridgers et al., alleging themselves to be taxpaying citizens of the city of Lampasas, applied to the district judge of Lampasas county for a writ of injunction restraining the city of Lampasas, its mayor, board of aldermen, and secretary from carrying out an alleged illegal contract made by the city of Lampasas with the Miller Surfacing Company to pave certain streets in that city. The court in chambers on that date granted the writ as prayed for, enjoining the defendants from issuing or delivering any warrants to Miller Surfacing Company, in payment for paving the streets, and from levying, assessing, or collecting any tax for that purpose. Bond in the sum of $1,000, fixed by the court, was filed by plaintiffs on November 20th, and on November 29th writ was issued. On November 27th the defendants filed a motion to dissolve said injunction, which was granted on December 1, 1922. From this order of the court plaintiffs appealed and the trial court entered his order, continuing the temporary injunction in force pending said appeal. On this appeal the judgment of the trial court dissolving the injunction was affirmed by this court on January 31, 1923, motion for rehearing overruled on March 21, 1923, and writ of error refused *839
by the Supreme Court on May 2, 1923. See
The matter before us on this appeal is the action of the trial court on the cross-action for damages brought by the Miller Surfacing Company, a partnership composed of G. R. Miller, W. L. Pearson, and S. R. Merrill, against all the original plaintiffs in the injunction proceeding, the sureties on the injunction bond, and also against C. D. Stokes and M. Y. Stokes, impleaded by appellants under allegations that they had, for the purpose of preventing the performance of the paving contract, and to hinder, delay, damage, and injure appellants without cause, conspired with and induced the original plaintiffs to bring said injunction suit against them, though they were not parties of record to the suit themselves. This answer and cross-action of appellants is very long, and we will discuss only the portions of same necessary to the disposition of this appeal. The original plaintiffs and the Stokeses filed separate answers to the cross-action, but both answers were in substance the same. The trial court sustained several special exceptions lodged against the cross-action, and upon appellants' refusal to amend rendered judgment against them from which this appeal is prosecuted.
It is true that the injunction restrained only the city of Lampasas, and the Miller Surfacing Company might have fulfilled its part of the contract without violating any of the terms of the injunction. But the proceeding specifically sought to invalidate and destroy the contract under which the appellants were to work. They were necessary parties to such suit (Bonner v. Texarkana [Tex. Civ. App.]
Appellants' next proposition is based upon the action of the trial court in sustaining appellees' special exception to their cross-action, on the ground that appellants did not allege that such damages were the direct and proximate result of suing out said injunction, and such that were or could have been within the reasonable contemplation of the parties at the time. The damages claimed are itemized in the cross-action; the largest portion alleged being expenses incurred by appellants in reconditioning the streets for surfacing, and in placing them back in the condition in which appellants had them at the time their work on them was stopped by the injunction. Appellants alleged that such additional expenditure by them after the injunction was finally dissolved was necessary to restore the gravel base to its former condition so that the surfacing could be applied according to their contract; that same would not have been necessary had the appellants not been prevented by the injunction from completing the work when first begun; and *840
that all of this was well known to appellees at the time. We think these allegations sufficient. There may be some question raised as to some of the items being too remote to be recovered; but whether or not such items were or should have been in contemplation of the parties at the time is ordinarily a question of fact to be determined after hearing the testimony. Alexander v. Ry. Co.,
The next question presented on appeal by proper assignments is whether or not the liability of appellees for wrongfully suing out the injunction is limited to the amount fixed by the injunction bond. In this case the penalty of the bond was $1,000. Actual damages of $2,608.94 and exemplary damages of $715 were pleaded by appellants.
The only Texas case directly in point to which our attention has been called or which we have been able to find is that of Martin v. Sykes, 25 Tex.Supp. 197. In that case the court held that judgment against the sureties for an amount in excess of the bond was error, but not as to the principal, as she was liable for the original debt and damages thereon, regardless of the bond. As to limiting the liability of the principal on such bond to the penalty of the bond, there is considerable conflict of opinion in other jurisdictions. The rule as stated in 32 C.J. 465, is that, where suit is brought on the bond, the bond is controlling, and only such damages are recoverable as are clearly embraced within its terms. However, in 14 R.C.L. 481, we find that:
"What is said to be the better rule, however, is that, although a party may have his remedy on his bond, yet this is not exclusive, and he may, in a proper case, also have a right to maintain an action at law."
See, also, Shute v. Shute,
We think the better rule to be that appellants are not necessarily limited in their recovery to the amount fixed in the bond, but are entitled to recover the actual damages proximately resulting from the wrongful issuance of the injunction, whether maliciously sued out or not. Ry. Co. v. Miller (Tex.Civ.App.)
Appellants' fifth and sixth propositions assert error of the trial court in dismissing from appellants' cross-action C. D. Stokes and M. Y. Stokes on the grounds of misjoinder of parties and causes of action as to them. We think this was error. As above stated appellants are not confined entirely to the injunction bond in recovering actual damages. In the cross-action they allege specifically that a conspiracy was entered into between the Stokeses and plaintiffs to bring the injunction suit; that prompted by malice and without probable cause C. D. and M. Y. Stokes induced the plaintiffs to bring said suit, assisted in employing an attorney for that purpose, and prompted the wrongful action of plaintiffs, though not joined of record in the suit. If that were true, then, whether their names were signed to the application for injunction or not, they were in fact joint wrongdoers with the plaintiffs. Appellants could have sued them separately, but the suit would have involved the same transaction alleged, the same facts would have been involved, and the same measure of liability would have obtained as that charged against the actual plaintiffs Appellants' pleadings alleged all these matters. The law abhors a multiplicity of suits. They were therefore *841
proper parties to the suit on the cause of action pleaded, and the trial court erred in dismissing them. Article 1848, R.S.; National Surety Co. v. Atascosa Ice, Water Light Co. (Tex.Civ.App.)
The appellants' seventh proposition, addressed to their fifth and ninth assignments, asserts error of the trial court in striking out upon exception that portion of their cross-action claiming additional freight in the sum of $314, incurred because of the injunction in moving their outfits, equipment, and grader from Lampasas to Austin, where appellants alleged that they had other contracts, and in returning it to Lampasas after the injunction was dissolved. Appellants were charged with reasonable diligence in the use of their machinery to minimize their loss when the injunction was granted. Ordinarily that would have been the fair value of the use of their machinery while the injunction was in force, unless it could have been used by them with equal profit elsewhere. If it was reasonably necessary to remove it to some other city in order to use it, and the appellees knew or should have known that, then appellants would be entitled to recover the necessary expenses in so doing. Hermann v. Allen,
We have already discussed the question raised by appellants' eighth and last proposition, and deem further consideration of it unnecessary. For the reasons stated, the judgment of the trial court must be reversed and the cause remanded for trial in accordance with views expressed herein.
Reversed and remanded.