This action was brought by appellee Asbestos Insulating & Roofing Company, Inc., (hereinafter referred to as AIRCO) as plaintiff against appellant and the other named appellees to recover a personal judgment against appellee Warfel Plumbing & Heating Co., Inc., and to foreclose a mechanic’s lien on real estate owned by appellant and occupied by the appellee Charles S. Drake Company.
The trial court, upon timely request, made special findings of fact and stated conclusions of law thereon and entered judgment in favor of AIRCO. Appellant’s motion for a new trial was overruled and this appeal followed. The appellees other than AIRCO have not filed answer briefs or appeared in this court.
The special findings which are material to the decision of this appeal read as follows:
“2. Some time in the month of April or May, 1956 defendants Miller Monuments, Incorporated and Warfel Plumbing & Heating Co., Inc., through duly authorized agents entered into an oral agreement for the installation of plumbing, heating and related equipment in a certain building on the aforedescribed real estate, which building was to be occupied by the defendant Charles S. Drake Company as tenant.
“3. Plaintiff was asked by defendant Warfel to submit a bid on insulating certain duct work and doing related work on said building. Plaintiff submitted a written bid in letter form, said letter being introduced in evidence.
*50 “4. Plaintiff completed the work' it agreed to do and the work was performed according to conr tract and was done in a good and workmanlike manner, in December, 1956.
“5. Defendant Miller Monuments, Incorporated never accepted plaintiff’s work and refused to pay for it because of blisters ■ which appeared in the insulation.
“6. That in December, 1957, pursuant to the direction of Yost & Taylor, architects employed by the defendant Miller, the plaintiff proceeded in an attempt to_ correct said blistering condition and meet the objections of the defendant Miller; that _ in said attempt to correct said blistering condition plaintiff worked on same in December, 1957, January, February, March, and July, 1958, as said blisters developed. The defendant Miller still refused to accept said work as completed.
“Plaintiff filed a notice of mechanic’s lien on July 18, 1958, a copy of which was introduced in evidence and is incorporated herein by reference. A balance of $3000 was due plaintiff on its contract with Warfel at the time of the filing of said lien, and still remains-unpaid.
“8. Plaintiff through its agents and employees had done corrective work on the blisters on the insulation work within sixty days prior to the filing of said lien. Such work was done with defendant Miller’s knowledge and consent and pursuant to its refusal to accept and pay for the work done by plaintiff until such corrective work was completed to its satisfaction.
“9. At no time did any of the said parties claim that the work done by plaintiff was in itself defective, but defendant Miller continued to refuse to accept the work in question as .completed or corrected.
“10. Defendant Miller Monuments, Incorporated had not accepted plaintiff’s work and was still insisting on further corrective work in November, 1958.”
Appellant states that the sole' question to be determined on this appeal is whether the mechanic’s lien *51 dated July 17, 1958, and recorded July 18, 1958, was filed or recorded within sixty days after the last labor was performed or the last material was furnished by AIRCO pursuant to the subcontract it had with the general contractor.
Heavy reliance is placed upon Special Finding No. '4 to the effect that AIRCO had completed the work it agreed to do ,in a good and workmanlike manner in December, 1956. Appellant contends that the work AIRCO did after appellant refused to accept this work as completed, in an effort to correct the blistering condition which developed, did not extend the time for filing a mechanic’s lien; that it was performed either gratuitously or under a new contract made after the work originally contracted for had been fully completed.
Special Finding No. 6 is the only finding of which any criticism is made in appellant’s original brief. Appellant states in his reply brief that parts . of two other findings are not sustained by the evidence, but we are confined to the questions presented in the original brief. Questions not discussed in an appellant’s original brief may not be presented for the first time in a reply brief. Flanagan, Wiltrout & Hamilton, Indiana Trial and Appellate Practice, §2682, p. 328, and authorities there cited;
Murrin etc. et al.
v.
Cook Bros. Dairy, Inc.
(1956),
Appellant argues that there is no evidence to sustain that part of Special Finding No. 6 to the effect that AIRCO proceeded in an attempt to correct the blistering- condition “pursuant to the direction of” *52 Yost & Taylor, architects employed by appellant, because the words used in a letter from the architects were “we authorize you” to proceed with the methods AIRCO used in venting and not “we direct you.” Appellant’s architects had written to the principal contractor concerning the corrective work which was later done by AIRCO stating in part as follows:
“Since Asbestos Insulating & Roofing Company, Inc. had objections and reservations to both, of the alternate suggestions which Ave made to remedy the condition, we authorize you to proceed with the method of venting which you originally proposed, namely, by a series of 1/4" copper tubes placed in the sides of the ductwork insulation, near the top.” (Our emphasis.)
In the same letter the architects also said that certain action should be taken — action which had nothing to do with the work AIRCO had done or was to do. Appellant argues that the letter made it a condition to the authorization of the venting by AIRCO that the other action should also be taken. We do not so construe this letter.
We do not regard it as material in this case whether AIRCO’s additional work was done pursuant to the “direction” of the architects or merely pursuant to the “authority” granted by appellant’s architects. The finding that the additional work was done with appellant’s knowledge and consent and pursuant to its refusal to accept and pay for the work done until such corrective work was completed to appellant’s satisfaction was not challenged.
We have here a situation where a subcontractor completed the work it Avas to do in a good and workmanlike manner, but the owner of the real estate would not accept the work as completed and refused *53 to pay for it until corrective work was completed to its satisfaction. Thereafter the subcontractor, with the owner’s knowledge and consent and under the authority or direction of its architects and pursuant to such refusal to accept the work as completed, did additional work in order to meet the owner’s objections.
In the case of
Whitcomb
v.
Roll
(1907),
In
W. P. Nelson Co.
v.
Weyl, Rec.
(1919),
As stated in 57 C. J. S., Mechanics’ Liens, §149, p. 671:
“Thus, where the owner or his authorized agent claims that certain details of the work are not according to the contract or not satisfactory, and they are accordingly changed or set right by claimant, the lien is in time if filed within the statutory period after such changes are made or such additional work is done, since the owner is estopped, in such case, from subsequently claiming that the contract was completed before the doing of the additional work or the furnishing of the additional materials demanded by him under the contract.” See also 36 Am. Jur., Mechanic’s Liens, §141, O. 98.
The facts found by the court do not show that the later work was done gratuitously or by virtue of a new contract. Appellant is estopped by its conduct, as shown by the special findings, from claiming that the work under the subcontract was completed before the doing of the additional work, and the mechanic’s lien was therefore timely filed.
We have examined the cases relied upon by appellant but find nothing in them contrary to the conclusion which we have reached. In the case of
Ellis
v.
Auch et al.
(1954),
The decision of the court is sustained by sufficient evidence and is not contrary to law, and the court did not err in its conclusions of law.
*56 With the view we have taken as to the main question involved here, we do not find it necessary to pass upon certain technical questions raised by appellee.
Judgment affirmed.
Kelley, C. J., Bierly and Gonas, JJ., concur.
Note. — Reported in
