Miller Building Corporation (plaintiff) appeals from the trial court’s order allowing judgment on the pleadings for NBBJ North Carolina, Inc. and William C. Johnson (dеfendants) based on “estop-pel by record” and election of remedies. Defendants cross-assigned error from the failure of the triаl court to enter a judgment on the pleadings based on their statute of limitations defense.
The relevant facts are as follows: On 13 December 1991, the plaintiff entered into a contract with Raleigh Parking Decks Associates, Inc. (RPDAI) to construct a multi-level parking deck, maintenance and storage facility (Project) in Raleigh, North Carolina. The City of Raleigh (City) subsequently assumed some or all of RPDAI’s contractual duties with the plаintiff. On 1 August 1990, the defendants contracted with RPDAI to design the Project.
During the construction of the Project, disputes arose among the various parties involved. On 22 October 1991, a subcontractor of the plaintiff, Spencer White & Prentis Corporation, filed a lawsuit against the plaintiff, the City, RPDAI, and several other parties. The present defendants were not involved or included in that suit. The plaintiff *99 subsequently asserted cross-claims against RPDAI and thе City and asserted the following causes of action: (1) breach of contract; (2) breach of warranty; (3) request for additional time to complete work; and (4) unfair and deceptive trade practice. In support of these claims, the plaintiff alleged, inter alia, that the defendаnts were representatives of RPDAI and as such “failed to fulfill [their] contractual requirement...,” and further that they had “no prior experience with the design or construction of parking decks” and that as a result of this lack of experience, “numerous design errors occurred . . . .” It was furthеr alleged that the defendants “repeatedly failed to timely respond to [the plaintiff’s] requests for information... and refused to execute change orders which allowed [the plaintiff] to preserve its rights . . . .” Finally, it was alleged that the “plans and specifications and the Sub-Surface Report. . . were in error . . . .”
On 19 January 1996, the plaintiff filed a Stipulation of Dismissal with Prejudice as to all of its claims against RPDAI and the City. In May of 1996 the plaintiff filed this action against the defendants and alleged malpractice; negligent misrepresentation; breach of contract under a third-party beneficiary theory; tortious interference with contract; and breach of implied warranty. In support of these claims the plаintiff alleges that it relied on the defendants in the bidding and construction of the Project (the subject of the first law suit) and that the defendants committed “numerous design errors” because of their “lack of experience.” It is further alleged that the defendants “failed and refused to respond in а timely fashion” to the plaintiffs request for information and that the defendants “often required [the plaintiff] to execute change orders on fоrms drafted by [the defendants] which forced [the plaintiff] to waive certain rights.”
The dispositive issue is whether collateral estoppel bars the plaintiff from proceeding with this suit.
The trial court indicates in its order that the dismissal is based on “estoppel by record.” “Estoppel by record” is an antiquated phrase formerly broadly used to refer to the principles presently encompassed within the phrases res judicatа (claim preclusion) and collateral estoppel (issue preclusion).
1
See Price v. Edwards,
In North Carolina a defendant is permitted to “assert collateral estoppel as a defense against a party who has previously had a full and fair opportunity to litigate a matter [in а previous action which resulted in a final judgment on the merits] and now seeks to reopen the identical issues [actually litigated in the prior аction] with a new adversary.”
Thomas M. McInnis & Assoc., Inc. v. Hall,
In this case the defendants have met their burden of showing that the issues underlying the present claims were in fact identical with the issues raised in the plaintiff’s previous cross-claims. The issues in *101 both cases are (were) whether the defendants: failed to fulfill their contractual duties; failеd to supply correct plans and specifications; did not have the experience to design and construct the parking decks; did not timely respond to the plaintiffs requests for information; and failed to properly execute change orders. The plaintiff has failed to show that it was denied an opportunity to litigate these issues in the first case, and the dismissal “with prejudice” of those cross-claims thereforе constitutes an adjudication of those issues against the plaintiff. The trial court thus correctly determined that this second action, the present claims, are barred by collateral estoppel.
Having so decided, it is not necessary for this Court to determine whether dismissal is alsо supported by res judicata and election of remedies. Furthermore, having affirmed the order of the trial court we need not reaсh the defendants’ cross-assignment of error based on the statute of limitations.
Affirmed.
Notes
. The continued use of the phrase “estoppel by recоrd” is discouraged. The party seeking dismissal should specify whether he seeks dismissal on the basis of res judi-cata or collateral estoppel. This permits the party resisting dismissal to know how to defend the motion and allows the trial court to properly analyze the evidence. Furthermore, appellate review is better served as the parties can direct their arguments to the relevant evidence and law.
