Millennium Pipeline Co., LP v. GutierrezMillennium Pipeline Co., LP v. Gutierrez
MEMORANDUM OPINION
This matter comes before the Court on the plaintiffs motion [30] for summary judgment, intervenor-defendant New York
BACKGROUND
Millennium, a partnership of several North American energy companies, proposes to construct and operate a natural gas pipeline that would stretch approximately 420 miles (the “Project”), from a point along the United States-Canada border in Lake Erie to a terminus outside New York City. The Project will transport U.S. and Canadian natural gas to markets in the eastern United States, including New York. Millennium states that the pipeline’s capacity would be 700,000 decat-herms per day. (Pl.’s Mot. 2.)
The construction and operation of the Millennium Project must be approved by the Federal Energy Regulatory Commission (“FERC”) under the Natural Gas Act,
In preparation of an Environmental Impact Statement (“EIS”) for the Millennium Project under the National Environmental Policy Act (“NEPA”),
Villages of Croton-on-Hudson, Briarcliff and Cortlandt, and other intervenors thereafter requested a rehearing of the FERC’s order approving the Millennium Project. On September 19, 2002, the FERC denied those requests for rehearing. Croton-on-Hudson, Briarcliff, Cort-landt, and others subsequently sought review of the FERC’s orders regarding the Millennium Project by the United States Court of Appeals for the District of Columbia Circuit. On March 16, 2004, the Court of Appeals issued an order holding those proceedings in abeyance pending the outcome of this Court’s review. (Pl.’s Mot. at 5.)
In addition to the FERC proceedings, proceedings regarding the Project were also held before the NYSDOS under the Coastal Zone Management Act (“CZMA”),
Section 307(c)(3)(A) of the CZMA also states that if a state fails to act within six
On or about November 27, 2001, New York became aware, from information received from the U.S. Army Corps of Engineers, that Millennium might conduct blasting in a portion of the Hudson River. (Id.) On December 14, 2001, New York wrote to Millennium advising that the State “ha[d] not completed its review” because of project changes involving underwater blasting in the Hudson River, and accordingly had not, and would not, complete its CZMA review in the 30 to 60 days following New York’s receipt of the final FEIS it had previously estimated. (Secy.’s Opp’n 13.) On March 14, 2002, Millennium wrote to New York providing information concerning the blasting issues. (Id. at 14.) On April 23, 2002, Millennium provided New York a site specific blasting plan and impact assessment for the pipeline’s proposed Hudson River crossing and requested that New York complete its review and conclude that the project is consistent with New York’s coastal management program. (Id.)
On May 9, 2002, New York objected to the Millennium Project, finding that the Project was not consistent with New York’s coastal management program. New York asserted that alternative pipeline routes across the Hudson River and across the Catskill Aqueduct were reasonable and available.
Millennium filed a timely consistency appeal with the Secretary of Commerce (“Secretary”) seeking an override of the State’s objection pursuant to
LEGAL STANDARD
As
Millennium notes, this Court has jurisdiction under the Administrative Procedure Act (“APA”), and the parties agree that review of the Secretary’s decision must be conducted on the administrative record and reviewed under the standards for judicial review.
The Court must review the agency’s action based on the administrative record before the court.
See Camp v. Pitts,
DISCUSSION
Millennium argues that the Secretary exceeded his statutory authority in extending the CZMA’s six-month period for state action. Millennium also alleges that the Secretary acted arbitrarily and capriciously and abused his discretion by failing to accord preclusive effect to the FERC findings. In response, defendants argue that the Secretary correctly determined that New York objected to the project on a timely basis. Defendants also state that the Secretary had a reasonable basis for his conclusion that reasonable alternative routes are available and that Millennium did not establish otherwise. And finally, defendants argue that the Secretary did not act arbitrarily or capriciously in deciding the pipeline was not necessary in the interest of national security. The Court agrees with defendants and will address plaintiffs arguments in turn.
I. Timeliness of New York’s Objection
A. Coastal Zone Management Act
The CZMA states that “[i]f the state or its designated agency fails to furnish the
The review for consistency does not automatically begin with the mere submission of an application for certification. According to the CZMA, “commencement” of review occurs when the applicant “furnish[es] to the state or its designated agency a copy of the certification, with all necessary information and data.”
In a letter dated January 28, 1999, New York notified Millennium, the FERC, and the New York and Buffalo Districts of the Army Corps of Engineers, that “if [the specified] necessary data and information is not provided, the Department of State may object to your consistency certification on the grounds of insufficient information” and that “without the specified information the consistency of the proposal with the NYS Coastal Management Program cannot be addressed.” (Secy.’s Reply 5.) This letter from New York satisfies the minimal requirements of
Accordingly, as found by the Secretary, the mere submission by Millennium of a consistency certification was insufficient to commence review, until it furnished all necessary information and data.
B. Chevron
Plaintiff also contends that the Court’s determination of the validity of the Secretary’s interpretation of the CZMA is governed by
Chevron. Chevron U.S.A., Inc. v. NRDC, Inc.,
The precise question at issue is the content of the notice a state is required to provide in order to forestall a federal agency from conclusively presuming the state’s concurrence.
Additionally, a state cannot review the merits of a project’s consistency with a state coastal management program (“CMP”) until the applicant has tendered the statutorily required necessary data and information. The statute clearly anticipates that the certification will be submitted as a package, including all necessary data and. information.
Conversely, Millennium suggests that both the statute and the legislative history indicate that the time period for state review begins when the certification is filed, and does not require the submission of necessary data and ' information. The Court disagrees. The statute requires that “the applicant shall furnish to the state or its designated agency a copy of the certification, with all necessary information and data.”
C. Six-Month Extension
Millennium argues that even if the Secretary’s interpretation of the statute were upheld by the Court, the Secretary erred by concluding that the agreement extended the state’s consistency review period for an indefinite period. Millennium also contends that they lacked the authority to waive strict compliance with the six-month period for state consistency review and, accordingly, that both its agreement and the National Oceanic and Atmospheric Administration of the Department of Commerce (“NOAA”) regulation which permitted such agreements are unlawful and void. The Court disagrees with all of Millennium’s arguments.
The agreement between Millennium and NYSDOS was not indefinite. The agreement as interpreted by the Secretary did not contain a specific date certain by which the review period must end. However, the Secretary did construe the agreement to require NYSDOS to complete its review after issuance of the FEIS and Millennium’s submission of information the State deemed necessary for its review. (Secy.’s Decision 19 n. 58.) More critically, the Secretary found that, though not fixed in length, the agreement to continue the consistency review period was terminable .at will by either party.
Millennium also argues that the extension agreement was void because the six-month statutory time limit precludes any modification by agreement of the parties. Defendants argue that the six-month
The Secretary’s rule at issue in this case permits mutual agreements between a state and applicant to stay the consistency time period. The regulation merely sanctions an applicant’s own exercise of its prerogative to waive the statutory deadline. The administrative record supports a finding that Millennium agreed to stay the consistency time period based on their own self-interest and failure to provide the required information. This agreement waived Millennium’s right to a timely decision. Accordingly, the Secretary did not abuse his discretion by finding that the agreement between Millennium and New York was lawful.
II. The Secretary’s Decision
A. State Review under CZMA: Catskill Aqueduct
Under Section 307(c)(3)(A) of the CZMA, a state may only review a project requiring a federal license or permit to the extent that the project “affect[s] any land or water use or natural resource of the coastal zone of that state....”
[A]ny reasonably foreseeable effect on any coastal use or resource resulting from a federal action.... Effects are not just environmental effects, but include effects on coastal uses. Effects include both direct effects which result from the activity and occur at the same time and place as the activity, and indirect (cumulative and secondary) effects which result from the activity and are later in time or farther removed in distance, but are still reasonably foreseeable.
Millennium contends that the pipeline segment proposed by Millennium across the Catskill Aqueduct would not “affect[ ] any land or water use or natural resource of the coastal zone of the state” and thus is not subject to New York’s review under the CZMA. (Pl.’s Mot. 26.) However, the Secretary concluded otherwise. The Secretary reasoned that a rupture of the pipeline could conceivably cause a release of water from the aqueduct, that such a loss of water supply “would directly affect New York City, a part of which is located within the coastal zone,” and that, as a consequence, “a failure of the [aqueduct] would have direct impacts on the resources and uses of the coastal zone.” (Pl.’s Mot. 26.) This Court agrees.
The evidence in the record does not support Millennium’s argument. The FEIS discusses the Catskill Aqueduct crossing as an environmental consequence of the project. The FEIS also notes that the New York City Department of Environmental Protection has expressed continuing concern about the pipeline crossing in this area since any failure of the pipeline would result in the interruption of water supplies to New York City. Accordingly, the Court affirms the Secretary’s decision that the Catskill Aqueduct crossing was subject to CZMA review because it had a “reasonably foreseeable effect on any
B. Route Alternatives
The Secretary also concluded that the Millennium Project was not consistent with the objectives of the CZMA because Millennium failed to demonstrate that “[t]here is no reasonable alternative available which would permit the activity to be conducted in a manner consistent with the enforceable policies of the state coastal management program.” (Pl.’s Mot. 28.) Millennium argues that “even if the Secretary may lawfully require an appellant to show that there are no reasonable and available alternatives to override a state’s objection to a project, the Secretary’s imposition of an onerous burden of proof on Millennium was arbitrary and capricious.” (PL’s Mot 29.) Millennium further contends that there were no reasonable and available alternative pipeline routes across the Hudson River and the Catskill Aqueduct, and that there was not substantial evidence to support the Secretary’s decision. (Id.) The Court is not persuaded by Millennium’s arguments.
The Secretary did not hold Millennium to an “impossible” burden of proof. Under
The Secretary also found that an alternative route could be constructed because, while New York had introduced sufficient evidence to demonstrate the availability of those routes, Millennium’s claims lacked credible evidence and convincing arguments. The Secretary acknowledged the conflicting evidence in the record but nonetheless accepted New York’s decision that the route could be constructed. The Secretary pointed out that 1) Millennium failed to provide actual information on specific conditions at a key site along the route; 2) Millennium failed to substantiate any concerns regarding the feasibility of constructing one of the route’s segments; and 3) Millennium had no response to the argument that pipelines can be constructed in close proximity to existing utilities. (Secy.’s Decision 30-32.)
The Secretary’s decision contains a reasoned and well-supported finding that this route alternative is reasonable and available. Furthermore, the Secretary’s decision that alternative routes are available is supported by substantial evidence and based on a permissible interpretation of the CZMA.
III. National Security
Under Section 307(c)(3)(A), the CZMA provides that the Secretary must override a state’s objection to a proposed project that requires a federal license or permit if the project is “necessary in the interest of national security.”
In spite of these recommendations, the Secretary decided that the record did not support a finding that the Project was
Plaintiff claims that the Secretary had no authority to alter the statutory standard — “necessary in the interest of national security” — by requiring “a specific and significant impairment” of national security interests “if the pipeline were not permitted to go forward as proposed.” (PL’s Mot. 34.) The Court finds that the “specific and significant impairment” requirement imposed in the Decision of the Secretary was a permissible reading of the “national security” standard in the statute, and that the Secretary did not abuse his discretion in finding that the standard was not satisfied.
Congress authorized the Secretary to override a state’s consistency objection when “necessary in the interest of national security,” but failed to define what it meant in terms of the national security interest. The NOAA permissibly resolved this ambiguity by promulgating a regulation further defining a national security interest as “a national defense or other national security interest that would be significantly impaired were the activity not permitted to go forward as proposed.”
Millennium also argues that even if the NOAA regulations are valid, the Secretary’s failure to heed the advice of the DOE and the FERC was arbitrary and capricious. (PL’s Mot. 34.) Plaintiffs argument is not persuasive. Here, the Secretary considered the recommendations of the federal agencies and reasonably decided that, under NOAA regulations, “general statements that the project furthers or is important to the national interest fail to satisfy the requirements [of a] specific and significant impairment.” (Secy.’s Opp’n 44.) Moreover, the regulations name the Department of Defense (“DOD”) as the one agency having a special interest in the national security issue. In this case, the DOD reiterated the views of the Army Corps of Engineers, objecting to the project due to its adverse impacts and the availability of alternative routes. (Id.)
The regulations leave it to the Secretary’s discretion to disagree with other government agencies if he determines that their national security concerns are not important enough to override the valid local concerns of the affected state.
CONCLUSION
For the reasons stated herein, the Court will deny plaintiffs motion for summary judgment and grant all defendants’ cross-motions for summary judgment.
A separate Order will issue this date.
ORDER
This matter comes before the Court on the plaintiffs motion [30] for summary judgment, intervenor-defendant New York State Department’s cross-motion [39] for summary judgment, intervenor-defendant Village of Croton-On-Hudson, Briarcliff Manor, and Town of Cortlandt’s cross motion [40, 44] for summary judgment and defendant the Secretary of Commerce’s cross-motion [45] for summary judgment. Upon consideration of these motions, it is hereby
ORDERED that defendants’ and inter-venor-defendants’ cross-motions for summary judgment are GRANTED.
Judgment is hereby entered for defendants, and this case shall stand DISMISSED WITH PREJUDICE.
SO ORDERED.