41 Mass. App. Ct. 30 | Mass. App. Ct. | 1996
We are asked again to explore the limits of indemnity obligations by subcontractors to general contractors and owners. On December 20, 1989, John Miley delivered
Miley brought a negligence action against Johnson and Carlson, later amending his complaint to include claims against S&F and North Shore. Carlson, in turn, brought third-party indemnification claims against North and S&F, based on § 9 of their respective subcontracts with Carlson. A judge of the Superior Court granted summary judgment to all four defendants as to Miley’s claims on the ground that the undisputed facts generated by the summary judgment materials disclosed nothing other than a natural accumulation of snow. See Sullivan v. Brookline, 416 Mass. 825, 827 (1994). Carlson pressed the third-party indemnity claims against North and S&F. The judge dismissed the cross complaint of Carlson as moot. As to Johnson, he denied a postjudgment motion to file a similar cross complaint. His rationale for both orders was that there was no underlying liability, i.e., nothing for which to indemnify Johnson and Carlson. Miley took an appeal but, before argument, settled for an aggregate $10,000 with Carlson, North, and S&F.
What owner, contractor, and the two subcontractors are still litigating is not so much the burden of the $10,000, but whether North and S&F, under their subcontracts, are bound to indemnify the contractor and the owner for their legal expenses.
Section 29C of c. 149 of the General Laws, the text of which appears in the margin,
In text, § 9 — the indemnity clause of the subcontract form that Carlson used with its subcontractors — undertook to meet the prohibition of § 29C. “Subcontractor shall,” it begins, and then, making a bow to § 29C, says “to the fullest extent permitted by law and to the extent any such claims, losses, liabilities or expenses are caused in whole or in part by any act or omission of Subcontractor. . . .” Toward the end of the section, which is cast as one sentence, the text presses the limits of § 29C by imposing indemnity obligations for “any and all claims, losses, liabilities and expenses, including attorney’s fees, arising out of or in any manner caused by,
As the case stands before us, with final judgment in favor of all defendants, neither subcontractor is in breach of any duty to the man who slipped and fell. The accident occurred because of something with which North and S&F had nothing to do, i.e., the natural accumulation of snow. Nothing is left for imposing liability upon the subcontractors except that they were there. On a “but for” analysis it is possible to say that, had North not been on the job site, Miley, the deliveryman, would not have walked onto the floor on which he fell. To make presence alone the basis for indemnity, however, steps over the limit that the Legislature set in G. L. c. 149, § 29C. From the proscription in the statute of indemnity for injury or damage “not caused by the subcontractor” (emphasis supplied), the obverse proposition follows that the subcontractor may be bound to indemnify “up the line” only if the subcontractor does or does not do something to bring about the injury or damage. In its statutory context, the word “cause” must be taken to mean some action (dropping a pipe on the deliveryman’s foot) or inaction (leaving an unnatural ice patch in the delivery path) that provokes the mishap. Otherwise, the statute is nullified, and the subcontractors, just by signing up for the subcontract and coming on the job site, are bound to indemnify “come what may,” a standard described as offensive to the statute in M. DeMatteo Constr. Co. v. A.C. Dellovade, Inc., 39 Mass. App. Ct. at 4.
The owner and general contractor argue that, even were it to be established, as we have decided, that there is no causal
For the reason that liability based on presence alone by the subcontractors on the job site would offend G. L. c. 149, § 29C, and for the reason that the subcontract contained no independent undertaking by the subcontractors to defend claims against the general contractor, Carlson’s cross action was properly dismissed. The judgment, therefore, is affirmed. For the same reasons, there was no error in denying Johnson’s postjudgment motion to file a cross complaint.
So ordered.
We asked at argument and are still perplexed why, in a modest slip and fall case, the lawyers (all, presumably, employed by the insurers) for the target defendants and the potential indemnitors could not, through cooperation, designate one of their number as lead counsel. Instead, counsel for the parties have consumed four times the legal and a lesser multiple of judicial resources than those for which the occasion seems to call, plus, in the bargain, having produced this appeal. To the extent this is typical, the question we ask is one that insurance company general counsel and executives might profitably ponder.
And as the motion judge had ruled.
As previously noted, the owner was not required to share in the $10,000 paid to the plaintiff as settlement, and the other parties have voluntarily shared in paying that amount, reserving their right to pursue the issue raised in this appeal. -
Section 29C, as appearing in St. 1986, c. 557, § 135, reads, so far as material,, as follows: “Any provision for or in connection with a contract for construction, reconstruction, installation, alteration, remodeling, repair, demolition or maintenance work . . . which requires a subcontractor to indemnify any party for injury to persons or damages to property not caused by the subcontractor or its employees, agents or subcontractors, shall be void.” Statutes 1986, c. 557, is entitled, “An Act Making Certain Corrective Changes In Certain General and Special Laws.” The text set forth in § 135 of the Act is identical with that enacted by St. 1985, c. 228, § 3, to which reference was made in some of our previous opinions interpreting G. L. c. 149, § 29C.
The full text of the indemnity provision in the contract is as follows: “9. Indemnification. Subcontractor shall, to the fullest extent permitted by law and to the extent that any such claims, losses, liabilities or expenses are caused in whole or in part by any act or omission of Subcontractor, anyone directly or indirectly employed by Subcontractor or anyone for whose acts Subcontractor may be liable, regardless of whether or not any such claims, losses, liabilities or expenses are caused in part by a party indemnified hereunder, indemnify and hold harmless Contractor, Architect, Engineer and Owner and the agents and employees of Contractor, Architect, Engineer and Owner from and against any and all claims, losses, liabilities and expenses, including attorney’s fees, arising out of or in any manner caused by, connected with or resulting from Subcontractor’s performance of this Subcontract or the presence of Subcontractor or Subcontractor’s employees and/or agents at the Project site.”