W. O. MILES, Respondent, v. W. H. RYAN, City Clerk of the City of Fresno, Appellant.
S. F. No. 6765
Department One. Supreme Court of California
February 28, 1916
Rehearing Denied March 27, 1916
172 Cal. 205
Department One.
The judgment is affirmed.
Sloss, J., and Lawlor, J., concurred.
MECHANICS’ LIENS—CONTRACT WITH CITY FOR PUBLIC BUILDING—GARNISHMENT BY CREDITOR OF CONTRACTOR—NOTICE TO WITHHOLD—PRIORITY.—The claim of one who has garnished, under
ID.—NO MATERIALMEN‘S OR LABORERS’ LIEN ON PUBLIC BUILDING.—Neither the constitution nor the statute gives laborers or materialmen any lien against public buildings.
ID.—NOTICE TO WITHHOLD—ASSIGNMENT BY CONTRACTOR—ATTACHMENT OF RIGHTS OF CONTRACTOR.—If, before the service of the notice under
ID.—TIME WHEN NOTICE MAY BE GIVEN.—
APPEAL from a judgment of the Superior Court of Fresno County. H. Z. Austin, Judge.
The facts are stated in the opinion of the court.
L. L. Cory, for Appellant.
Milton M. Dearing, for Respondent.
SHAW, J.—The defendant appeals from a judgment in favor of the plaintiff.
The object of the action was to obtain a writ of mandate directing the defendant as city clerk to draw his warrant in favor of the plaintiff for the sum of $750.50, being the amount due and remaining unpaid by the city of Fresno to one J. G. Simpson. The clerk refused to issue the warrant, basing his refusal on the ground that the plaintiff‘s claim was founded solely on a garnishee process under
We are of the opinion that upon the facts above stated, and under the provisions of the law relating to claims of such materialmen and laborers, the giving of a notice by the judgment creditor, prior to their notice and after the maturity of the claim, gives the judgment creditor precedence over said laborers and materialmen in the payment of money due the contractor.
Neither the constitution nor the statute gives laborers or materialmen any lien against public buildings. This was expressly decided in Mayrhofer v. Board of Education, 89 Cal. 110, [23 Am. St. Rep. 451, 26 Pac. 646]. The doctrine on which it rests, namely, that the state is not bound by general words in a statute, which would operate to trench upon its sovereign rights, injuriously affect its capacity to perform its functions, or establish a right of action against it, and that such general expressions will not be applied to public property, has been repeatedly affirmed since that decision. As there could be no lien in this case, we are not concerned with the priorities that may exist in favor of lien claimants. The respective rights of laborers and materialmen on the one hand and of judgment creditors on the other must, therefore, be determined by the statutory provisions relating thereto.
These principles control the decision in the present case. Before the claimants under
The judgment is affirmed.
Sloss, J., and Lawlor, J., concurred.
Hearing in Bank denied.
In denying a hearing in Bank, the following opinion was rendered on March 27, 1916:
SHAW, J.—In a petition for rehearing the defendant contends that of the $750.50 which the city of Fresno, on May 2, 1913, ordered paid to Simpson on his building contract, only $363 was due, and that the remainder, $387.50, did not become due until thirty-five days after May 1, 1913, the date
The record does not establish the facts as claimed. The complaint alleges that the city allowed the Simpson claim for $750.50 on May 2, 1913, and ordered that a warrant be drawn for its immediate payment. The answer does not aver that this allowance anticipated the final payment on the building contract and included the installment of $387.50 that was not due until June 4, 1913. It cannot be presumed that the city would pay a debt before its maturity, and the only inference remaining is that the $750.50 was made up of the installments which fell due at and before completion. The answer alleges that the $750.50 is the full amount due under the building contract, but as the action was begun on May 16, 1913, which was before the final payment became due, this would be true only if the allowance covered the installments which were then due. The demurrer to the answer included a specification that the answer was uncertain in this respect, and defendant was therefore duly advised that if the facts were as now claimed, the pleading was defective.
Sloss, J., and Lawlor, J., concurred.
