288 Mass. 243 | Mass. | 1934
The trial judge, in awarding damages to the petitioner, justifiably found that within the limits of a State highway in West Boylston, not “in the macadam surface of the highway, but . . . near that surface,” stood a maple tree. The evidence warranted a finding that the tree was about nine feet westerly of the westerly side of the macadam surface; that the branches overhung that surface so that one could drive thereon under them; and that,
The chief contention of the Commonwealth is that the evidence did not warrant the finding that the tree constituted a defect “within the limits of the constructed traveled roadway,” such as is a requisite of liability under G. L. c. 81, § 18. See Lemon v. Commonwealth, 236 Mass. 599. We assume in favor of the respondent that those words are more restricted than the word “way” in G. L. (Ter. Ed.) c. 84, § 15, or the words “travelled path” or “way” used in Weave v. Fitchburg, 110 Mass. 334, 337, Moran v. Palmer, 162 Mass. 196, Dupuis v. Billerica, 260 Mass. 210, 215, and similar cases. But a “constructed” roadway may include a gravel path as well as one built of macadam, and both may be “travelled” although one is used more than the other. The evidence warranted the finding that the tree stood in a place “which had been graded and surfaced for travel and which to some extent was used for travel,” and that finding warranted the conclusion that the tree constituted a defect “within the limits of the constructed traveled roadway.”
We need not consider whether the same conclusion could have been reached on the ground that, no matter where within the limits of the highway the trunk stood, there was evidence warranting a finding that the branches overhung the admittedly constructed and travelled macadam roadway. See Barber v. Roxbury, 11 Allen, 318; Wright v.
Exceptions overruled.