138 Minn. 215 | Minn. | 1917
Oscar Dahlvik contracted to erect a dwelling house for plaintiff and to furnish all the labor and material therefor, and gave a bond, executed by defendants as sureties, to secure the performance of the contract and the payment of all obligations incurred for labor and material and to hold plaintiff harmless from any claim on account thereof. He erected
Defendants contend that they have been released from liability on the bond, and in support of that contention they assert: (1) That plaintiff made changes in the building not agreed upon in writing; (2) that plaintiff made payments to Dahlvik at different times, in different amounts, and in a different manner than the contract provides; (3) that plaintiff increased the cost of the work by wrongfully interfering with and hindering the performance thereof by Dahlvik and his employees.
1. The contract gave plaintiff the right to deviate from the plans and specifications and make any changes in the building that he should deem proper, and provided that the increase or decrease in cost resulting from such changes should be added to or deducted from the contract price. The bond made the contract a part thereof, and then provided that'the bond should not be invalidated by any changes agreed upon in writing by plaintiff and Dahlvik. It contained no expressly prohibitive provisions. During the construction of the building, the plans and specifications were departed from in certain particulars at plaintiff’s instance. Plaintiff testified that a writing specifying all the changes of any consequence, and the amounts agreed upon therefor was signed and given to Dahlvik; and that the full cost of such changes, amounting to the sum of $319, had been paid in addition to the contract price. Defendants asserted that this writing had not been signed, and that changes not specified therein had been made. The court charged the jury to the effect that, if plaintiff made changes in the building, this fact released defendants from liability, unless the changes were agreed upon and the agreement was reduced to -writing and signed by plaintiff and Dahlvik, or
Defendants contend that, if changes were made in the building which were not agreed upon in writing, they are released from liability under the bond, even if such changes were not prejudicial but beneficial to them; that as sureties who received no compensation for becoming such, any deviation from the strict letter of the bond, even if it enured to their benefit, discharged them from liability. In support of this contention they cite: Board of Co. Commrs. of Fillmore County v. Greenleaf, 80 Minn. 242, 83 N W. 157; Board of County Commrs. of Renville County v. Gray, 61 Minn. 242, 63 N W. 635; Flanigan v. Phelps, 42 Minn. 186, 43 N W. 1113; Simonson v. Grant, 36 Minn. 439, 31 N. W. 861; Erickson v. Brandt, 53 Minn. 10, 55 N. W. 62; Tomlinson v. Simpson, 33 Minn. 443, 23 N W. 864. In the first three cases cited, the instrument itself upon which suit was brought had been materially altered after its execution without the knowledge or consent of the sureties, and they were held not liable oh the ground that the instrument sued upon was not the instrument they had executed. None of these cases involved building contracts. In Erickson v. Brandt, 53 Minn. 10, 55 N. W. 62, which involved a building contract, the owner had made changes which increased the cost of the work, and it was held that the sureties were discharged thereby; but the contract contained no provision authorizing the owner to make changes. In Simonson v. Grant, 36 Minn. 439, 31 N. W. 861, which also involved a building contract, the sureties were held not liable because the owner had failed and refused to make payments to the contractor as stipulated in the contract. The effect of changes in the work made at the instance of the owner was not involved or considered. In Tomlinson v. Simpson, 33 Minn. 443, 23 N. W. 864, no claim was made that the surety had been released from liability upon the bond, and the court merely determined the extent of such liability.
The instant case is distinguished from all the cases above cited by the fact that the plaintiff was authorized by the contract to make the changes in controversy. The question here is not whether the sureties were re
The mere omission to put the agreement for the changes in writing did not affect the contract'of the sureties in’matter of substance, and, being without substantial prejudice to them, did not operate to release them from liability in the absence of an express stipulation that such omission should invalidate the bond.
Dahlvik began work about the first of October and at his request pay
Plaintiff was under the necessity of determining for himself the value of the work done in each month as the contract made no provision for determining such value. He claims to have determined such value according to his best judgment, and to have paid Dahlvik the proportional part thereof due under the contract. At the time the payments were made, they were accepted without any question being raised as to the correctness of the amounts. Defendants now insist, however, that the payments for each month were in fact much less than the amount due for the work performed in such month. The evidence leaves both the amount and the value of the work performed in the different months uncertain and indefinite. Defendants base their contention upon estimates'made by Dahlvik while on the witness stand. These estimates for the different months, when added together, make a total which exceeds the contract price by more than 50 per cent. The jury could well find that they were inaccurate and excessive. They were by no means conclusive, and we are unable to say that the conclusion reached by the jury is not justified by the evidence.
Dahlvik applied for and obtained $1,000 from plaintiff' to pay de-, fendant Lofbaeka for material purchased from him. Defendants now assert that plaintiff violated the contract by making this payment, for the reason that only a part of this material had then been furnished and none of it had then been incorporated into the building. As defendants also claim that' more than this amount had been earned and remained unpaid at the time of this payment, they are not in position to claim that the payment was prematurely made; and so far as appears Dahlvik had the right to pay this money to Lofbaeka if he so desired.
Defendants insist that plaintiff gave Dahlvik a promissory note of $400 due in 90 days and thereby obtained an extension of time which
Defendants, although strenuously insisting that plaintiff ought to have made larger monthly payments than he in fact made, complain because he did not retain one-fourth of the contract price and have it on hand at the completion of the work. The contract required plaintiff to make monthly payments, “to the amount of seventy-five per cent (75 %) of the actual value of the work done during the preceding month.” The actual value of the work performed was made the basis for measuring and determining the amounts to be paid as the work progressed, and defendants do not claim that the payments made exceeded three-fourths of such value. On, the contrary, they claim that the payments were less than that amount. The jury having found that the payments were made substantially in accordance with the rule prescribed therefor, the fact that, in consequence of making such payments, plaintiff had less than one-fourth of the contract price on hand at the .completion of the work did not discharge the sureties. Graves v. Merrill, 67 Minn. 463, 70 N. W. 562; George A. Hormel & Co. v. American Bonding Co. 112 Minn. 288, 128 N. W. 12, 33 L.R.A.(N.S.) 513.
So far as important, the assignments of error are directed to one or more of the above questions, and the orders appealed from are affirmed.