248 F. 807 | E.D. Pa. | 1918
A discussion of the questions which are presented by this record to be answered may well precede a statement of the facts to be found, as the number of the latter, which arc of importance, is determined by the former. The respondent raises substantially four objections to the allowance of the claim made by the libelant.
We feel, however, relieved of any call to decide or to consider this branch of the defense, because the respondents themselves interpreted the charter party as one imposing the duty of discharge upon them, by assuming it and undertaking the work of discharge. After thus waiving their right (if they had one) to require the libelant to deliver the cargo upon the wharf, it is too late now to make their stand upon it. The issue thus presented is one not raised by the pleadings and one no notice of which was given before trial, nor was it sought to be brought in by amendment. The position is clearly an afterthought, no suggestion of which is disclosed by the answer, but the thought of which was first revealed at the trial of the case.
The answer states that the respondent assumed the task of unloading the vessel, in the course of which difficulties were encountered which caused interruption of the work and consequent delays which the respondent claimed excused performance; hut there was no hint of the thought of a denial of the duty to discharge with such dispatch as that the vessel would not be unduly delayed.
A point was made of this by the libelant at the trial in the assertion of the position that the respondent cannot avail itself of a defense not set up in the answer, and objection was promptly interposed to its consideration. Everything which the respondent asked to have the record show in support of this position was permitted to go upon the record, subject to the objection, for such appellate use as the respondent has the right to make of it. We adhere, however, to the ruling indicated. Brooks v. Hilton (D. C.) 221 Fed. 265; Barber v. Lockwood (D. C.) 134 Fed. 985.
Respecting the first subdivision of these claimed excusing facts, it is to be stated that the strike was not declared until after the vessel should have been discharged, and therefore has no bearing upon the detention of the vessel, beyond increasing the duration of the detention.
The cargo consisted of 19,400 bags of sugar. The time of discharge in days was measured by an output of 5,000 bags per “working day.” This, although a minimum measure of discharging dispatch, is under the conditions of this case a definition of “customary quick steamer dispatch at the port of discharge.” It follows that the time allowance for discharge was four working days, and as soon as we translate working days into calendar days we are enabled to fix the time when the demurrage allowance begins to run.
Disregarding the earlier' movements of the vessel, which do not enter this discussion, she was at the wharf ready to discharge her cargo, and the discharge was in fact commenced, on the morning of February 3, 1917. This was Saturday, which, in this port, was a holiday, or at least a half holiday, in the sense that it is a holiday from the noon hour on. The next day being Sunday, if we exclude holidays and Sundays as not work 'days, and as not “working days,” within the meaning of this contract, the consignees were entitled to the four days from the 5th to the 8th, both inclusive, before the demurrage began to run. The vessel was discharged at the close of the working day on the 16th, and on this basis demurrage would.be chargeable from the 9th to the 16th, both inclusive, or a tptal of eight days.
It is not unusal, particularly of recent years, to find incorporated in many contracts a provision to the effect that performance is excused'by or during the duration of strikes. There is, however, no such provision in this charter party. There is also in somewhat common use a phrase, frequently employed in charter parties, such as “weather working days,” or an equivalent expression. It is to be observed that the phrase employed in this charter party is simply “working days.” These words have an established meaning in construing charter party contracts.
This found meaning is that “working days” are calendar days, exclusive of Sundays and holidays, without reference to weather or other excusing conditions. It is not necessary to be held, and in consequence it is not now held, ihat the words of a contract, which is, to. be construed as of the place of performance, will not yield their otherwise accepted meaning to the local usage meaning of that locality, because of the finding, hereinafter made, that there is no meaning of, the phrase local to the port of Philadelphia at variance with its. accepted legal meaning.
Demurrage charges partake of the nature of penalties, and although they are more strictly speaking liquidated damages agreed to by the parties, the claim of demurrage none the less is based upon a default which cannot be declared unless in strictness it has taken P'lace. The first working day which the consignees had, which could be called a 5,000-bag day, was Monday, February 5th, and hence the count of such working days against them begins with that day.
It adds nothing of value to the discussion, but an observation or two may be made respecting- the position of the libelant. It is that the consignees were bound to discharge with the quick dispatch called for by the charter party, without regard to any time oilier than that called for by this degree of promptness and energy in the act of discharging. This we think is the correct view, but the parties have defined not only “days,” but also “quick dispatch,” in terms of bags, so that the discharge of 5,000 bags becomes the most definite, and because of this the accepted, measure of what is a “day,” and also what is “quick dispatch.”
The contract says “24 hours,” not “a day.” We see, as before intimated, no more warrant for reading it “clear working day” than for reading it “clear working hours” — indeed, a less warrant. We think the charter party means what it says. Of course, it would necessarily mean that “lay days” would not begin until there was a lay day to begin after the expiration of the dme limit, and if'the time expired on a day which was not a lay day, the running of the lay days would begin with the then next lay day. There would be some plausibility in the argument which is implied in this that it allowed 24 hours of working time in which to prepare for the work of discharging. This would give for preparation the time up to practically Wednesday morning, February 7th, and relieve the respondents of the demurrage charge until noon Tuesday, February 13th (Monday being a holiday), or possibly to the 14th, thus' reducing the claim to $5,250, or to $4,500, The Assyria, 98 Fed. 316, 39 C. C A. 97.
The expression construed in che cited case was “one clear day,” and the construction put upon it was moreover in accord with the proven custom of the port. We find no mandate in that case, nor in any proven port custom here, to construe “24 hours” to have any other meaning than chat which the words, as ordinarily understood, carry.
There is this further observation to be made. Claims of demurrage may be made by way of damages for detention. In such cases (as we are figuring the actual damage), fractions of days may well be taken into account. Claims of demurrage may not be made on the basis of actual damages, but of a stipulated sum. The latter suggests, not a penalty, but something which partakes of the nature of a penalty. The sum to be paid for a day may be $1,500, but there is neither an agreement to pay $750, nor any such penalty incurred, for a half day.
There was first the charter party (known as the Anderson-Atkins) dated October 26, 1916. This chartered the whole ship for the voyage afterwards made to carry the cargo which afterwards was carried. It provides for demurrage as now claimed. It provided for the signing of bills of lading “without prejudice to this charter.” There was a cesser clause, relieving charterers of liability after vessel was loaded and bills of lading signed, reserving, however, “absolute lien on cargo for freight, dead freight, and demurrage.” The cargo was loaded and bills of lading signed.
One was dated January 21, 1917, for 4,400 of the bags of sugar which formed the cargo, and names Czarnikow, Blonda Company, or assigns, as consignees. It provides that:
“This bill of lading is subject to ail provisions of the charter party or freight contract dated [blank] under which this shipment is made, and is without prejudice thereto.”
Clause 8 provides that the carrier shall have a lien on the goods for “all freights, primages, demurrage, and other charges * * * and also for all other sums for which shipper, owner, or consignee may be liable to carrier under this bill of lading and/or under any charter party or freight contract under which this shipment is made.” The final provision is that the shipper, owner, consignee, or holder shall be bound by every provision in the bill of lading which was signed by the master. The other bill of lading covers 15,000 bags of the same cargo (the two thus covering the full cargo). It is also dated January 21, 1917, and is the same as the other, and also signed by the master. The respondents are the indorsees of both of these bills of lading. There was also another charter party, entered into between Atkins & Co. and the Munson Steamship Line, dated January 4, 1917, for the whole ship. It provides for the same $1,500 per diem demurrage. Clause 5 calls for bills of lading “to be signed without prejudice to this' charter and subject to this contract as to * * * demurrage.” Clause 12 gives to ship “an absolute lien on cargo for * * * de-murrage.”
We are unable, however, to subscribe to the soundness of the proposition. This action is by the owners of the ship upon the contract made with them. If it were founded upon the Munson contract, the right of action would he in the charterer. We see no difference in respect to contractual liability between a contract affecting a ship and one affecting other property. The owner of a house may lease it without restrictions. The tenant may sublet it (as if he were the owner) to another tenant. If the owner asserts his right of action, it must be based upon the agreement made with him. If he asserts it against his lessee, the contract measures the liability of the defendant, if he asserts it against the subtenant, who is not a party to this contract, the liability of the defendant may or may not be so measured. This fact may introduce oilier questions.
Respecting the point before us, however, the rights of the plaintiff would he properly based on his contract, although it might be true that his rights as against his lessee had been modified as against the subtenant. This objection to the right of the libelants to maintain their libel is not sustained.
The other point sought to he made is more readily grasped. The right to recharter a chartered vessel must be conceded, because the charterer is pro hac vice the owner. It must be clear, however, that nothing the charterer does can affect ipso facto the rights of the owners. Whatever change is wrought must be because of something done by them, or arise out of the relations between them and the consignees. After a cargo has been taken aboard and a bill of lading is signed, the consignee may assign it, and the indorsee acquires certain rights which, of course, he can assert. Along with these rights he assumes certain obligations, or at least his rights are qualified by those of the carrier. As between the carrier and an indorsee of the bill of lading, the measure of their respective rights may differ from that which is applied in controversies between the carrier and charterer. A carrier, who signed a bill of lading by which he agreed to deliver to any indorsee of the hill without, for instance, the payment of freight or demurrage, could not assert a right to either against such indorsee or the cargo, although his claim against the charterer would remain good. Moreover, the agreement in such bill that the cargo should remain liable to the carrier for demurrage would not be construed as an admission of
We see no occasion to pursue this subject further, or to determine questions which might have been raised. Here again the respondents are 'too late in raising some of the questions which are discussed in the brief. They might have raised the one of their liability for the de-murrage stipulated by the conventions of the charter party. They, however, admitted it, and sought to show that the agreement had been met, or that they were excused from performance by the facts they sought to prove. To permit them now to introduce this new defense would do an injustice to the libelants, which cannot be permitted.
A decree in favor of the libelants and against the respondents for the payment of the sum of $12,000, with interest thereon from February 16, 1917, together with costs, may be submitted.