Mike Moore's 24-Hour Towing v. City of San DiegoMike Moore's 24-Hour Towing v. City of San Diego
Opinion
The City of San Diego (the City) awarded five-year contracts for vehicle towing in nine separate districts. The losing bidders in three of these districts, Mike Moore’s 24-Hour Towing (Moore), Tom Moynahan, and H. M. Sevel, Inc. (sometimes collectively the Moore group), filed protests with the San Diego City Council (City Council), which heard them at a council meeting. (San Diego Mun. Code (SDMC), § 22.0513.) The Moore group protested that the bids of the prevailing bidder in those three districts, San Diego Police Tow Operators, Inc. (SDPTO), should have been disqualified for ten specified omissions in its bid. Moore also contended that its own bid should not have been disqualified as incomplete. The City rejected the protests and the Moore group filed this petition for writ of mandate. (Code Civ. Proc., 1 § 1085.) The trial court rejected Moore’s claim that its bid should have been found complete, but accepted the argument of the Moore group that a fair hearing had not been held before the City Council because the evidence presented at the hearing included a misrepresentation by City staff that there were no material omissions in the SDPTO bid. The trial court remanded the matter to the City Council to reconsider the bids submitted in the three districts, with directions to consider a particular document presented at the protest hearing supporting the Moore group’s allegations of material omissions by SDPTO.
The City, joined by SDPTO, appeals from the order, contending that the trial court erred in finding the City’s approval of the SDPTO bid was irrational, arbitrary, оr capricious. The Moore group has cross-appealed the order, contending the trial court erroneously rejected its arguments that its bid was adequate. We reverse the portion of the order requiring remand to the City Council for reconsideration, finding that application of the proper standard of review does not permit such a resolution of the matter. We affirm the balance of the order after hearing, which is construed as an appealable judgment. (§ 1064.)
Factual and Procedural Background
The City contracts with private companies to have vehicles towed from public streets and other places for reasons ranging from illegal parking to
The proposals received were evaluated by a screening committee, which made a recommendation to the City Council. This action concerns only three of the nine City districts, as no citywide contract was awarded. SDPTO bid on each of those districts, and Moore bid on district 3, offering a higher referral fee than did SDPTO. Moynahan and Sevel submitted bids for districts 8 and 9, offering referral fees which were lower than those offered by SDPTO. The city manager’s recommendations were based on the evaluation committee’s findings, and found Moore’s bid was nonresponsive to the RFP, and that for district 3, SDPTO should be awarded the contract. SDPTO also received the contracts for districts 8 and 9, although the Moynahan and Sevel bids were found responsive, because SDPTO offered the City a higher referral fee.
The Moore grоup filed formal protests as allowed by the RFP’s, each arguing that the SDPTO bid was inadequate because it contained nine or ten material omissions of information required by the RFP. In addition, Moore individually protested that it was unfair to find his bid was nonresponsive for failure to provide a biographical summary for the key personnel in his management team, and a list of his current business accounts, since that information had been inadvertently omitted and was available in earlier versions of his bids. 2 Moore argued that if his bid were going to be disqualified for such omissions, the SDPTO bid should likewise be disqualified.
At the hearing on the protests, City Council member Judy McCarty inquired of City staff about the reasons for disqualifying Moore’s bid while
The Moore group then sought reconsideration of the denial of their protest, and submitted papers entitled “Documentation Supporting Allegations of Material Omission by SDPTO” to the City Council. The City did not act upon the request for reconsideration.
The Moore group filed this petition for writ of mandate to require the City to find that the Moore bid was responsive, and the SDPTO bids were not. 3 At the hearing on the petition, the Moore group submitted as an exhibit their “Documentation Supporting Allegations of Material Omission by SDPTO” (referred to here as exhibit 20), which had been submitted to the City in the reconsideration request. The trial court issued a tentative ruling denying the petition in all respects, and heard argument. The City’s contention was that the SDPTO bid was exemplary, and no additional response should be required concerning business records, business hours, fees, etc. (i.e., as covered in section 3 of the RFP, the “Statement of Work”), or as to other matters such as insurance and credit rating. The court then took the matter under submission and issued an order after hearing, first denying the petition to the extent it requested that Moore’s bid be deemed qualified or responsive. The court stated, “There is no evidence that the City Council acted arbitrarily or capriciously in rejecting Moore’s bid. Moore’s bid did not contain material information which was needed by the Evaluation Committee to determine that Moore was capable of performing under the contract. The Committee and the City Council were not required to search Moore’s other bids, submitted in a different context, in order to locate the missing material.”
As to the SDPTO bid, the trial court granted the petition on the basis that the City Council had abused its discretion when it dismissed without inquiry
Posttrial proceedings ensued, including the City’s motions for reconsideration and for new trial which were set for oral argument October 12, 1995. The time to rule on the motion for new trial had expired before the hearing, and the record does not show any ruling on the new trial or reconsideration motions. The motion for new trial was deemed denied. (§ 660.) The order after hearing constitutes a final order disposing of the entire matter and may be construed by this court as the judgment issuing the writ. (§ 1064.) The City, allied with SDPTO, appealed, and the Moore group cross-appealed.
Discussion
On appeal, the Moore group does not challenge the standard of review utilized by the trial court, which was general mandamus under § 1085, for review of legislative action by the City in awarding the contracts and denying the protests. We therefore set forth the standard of review fоr legislative action, with attention to the Moore group’s argument that, even applying this standard of review, procedural unfairness occurred due to the nature of the evidence before the City Council, such that the trial court was correct in remanding the matter for further action and further evidentiary hearing. Once we have resolved the standard of review issues, we may turn to a review of the record to determine whether the City had a reasonable basis for the actions taken, both as to the SDPTO bid and the Moore bid.
Standard of Review
A
General Principles
A public entity’s “award of a contract, and all of the acts leading up to the award, are legislative in character.”
(Santa Ana Tustin Community Hospital
v.
Board of Supervisors
(1982)
Review of a local entity’s legislative determination is through ordinary mandamus under section 1085. “Such review is limited to an inquiry into whether the action was arbitrary, capricious or entirely lacking in evidentiary support. [Citation.]”
(Corona-Norco Unified School Dist.
v.
City of Corona
(1993)
Scope of Review
Before outlining in more detail the process this court should follow in reviewing this record, we first focus upon which decisions are under review. The appeal and cross-appeal are from the trial court’s decision finding the Moore bid inadequate and granting the petition to remand for consideration of allegedly omitted material as to the SDPTO bid. The underlying City Council legislative decision was to find the SDPTO bid adequate and reject the protests, and to find the Moore bid inadequate. The City argues de novo review on appeal is necessary of the underlying legislative City decision, with no deference paid to the trial court’s decision. The Moore group argues that this court should defer to a foundational factual finding by the trial court that there was a misrepresentation by City staff to the effect that there were no significant omissions in the SDPTO bid. To choose between these two positions, we must outline the nature of legislative decisionmaking to determine if the trial court was correct that it had the power to find evidentiary error by the City Council and to prescribe a remedy to correct such error.
In general, due to separation of powers considerations, “[t]he judiciary confines evaluation of a statute to the terms of the legislation itself and will eschew inquiry into what motivated or influenced those who voted on the legislation. [Citation.]”
(Board of Supervisors
v.
Superior Court
(1995)
Here, the trial court was concerned that the statement by the City’s deputy police chief, Dave Worden, to the effect that he had nоt found any omissions in the SDPTO bid, was a misrepresentation to the City Council of the true state of that bid. However, in legislative mandamus proceedings, the decision of the legislative body is to be evaluated on its face, without an inquiry into the underlying motive or thought processes of the legislators.
(Board of Supervisors, supra,
C
Issues on Appeal
With these principles in mind, we return to describing the basic task this court undertakes in reviewing an appeal in a legislative mandamus action. The court’s function is to determine whether the exercise of legislative power has exceeded constitutional limitations. The inquiry is whether
Where a legislative decision is under review, the courts “will tend to defer to the presumed expertise of the agency acting within its scope of authority.”
(Shapell Industries, Inc., supra,
With these standards in mind, we turn to the record to determine if the City Council had a reasonable basis (1) to find the SDPTO bid adequate under the RFP and (2) to find the Moore bid inadequate as a response to that document.
II
Sufficiency of the Bids
Under SDMC section 22.0512, subdivision (a), contracts for procurement under a request for proposals “will be awarded on the basis of the proposal
On appeal, the inquiry is whether the legislative body adequately considered all relevant factors and demonstrated a rational connection between those factors, the choice made, and the purposes of the statute or regulations under which it was acting.
(Shapell Industries, Inc., supra,
A
SDPTO Bid
The parties disagree on the interpretation of the RFP provisions as to the amount of information required to be supplied by bidders. The position of the City and SDPTO is that under section 7.1.1 of the RFP, proposals must meet the minimum requirements listed in the RFP sections 4 (information requirements), 5 (proposal fоrmat), and 6 (minimum administrative requirements), and this was done here.
The Moore group relies chiefly upon RFP section 2.8, “Selection of Contractor,” which provides that the bids will be evaluated “based upon a line item comparison with the [RFP] requirements. Simply stating compliance with a requirement or the absence of a complete descriptive statement by the Offerer
relevant to any action or service item of the
[RFP’s] will be construed as a negative response to that item and will have a negative impact upon the evaluation of the proposal.” (Italics added.) The Moore group has two major arguments: First, this provision should be broadly interpreted to require detailed responses to all portions of the RFP, not just sections 4, 5, and 6, as section 7.1.1 might suggest. Thus, although SDPTO claims it was enоugh under the RFP, section 3, to agree to comply with the requirements
To analyze these arguments, we set forth the four categories of omissions which the Moore group contends on appeal should have resulted in the SDPTO bid being found nonresponsive. 7
1. RFP Section 7.4, Bidding Documents
Section 7.4 of the RFP provides that by submitting the bid, each bidder “hereby proposes to furnish to the City” the services involved at the stated prices. This section states that the bidder “further warrants” that the bid is not made in the interest of or on behalf of undisclosed persons or entities. Pursuant to RFP section 2.6, the SDPTO bids included a statement acknowledging its acсeptance of all the terms and conditions of the request for proposal. SDPTO also signed required acceptance certificates agreeing to the provisions of this section.
Moore contends that a more specific, verbatim response to this section was required. The City responds, first, that RFP section 7.4 does not constitute an “action or service item” (RFP § 2.8) such that a more detailed response was required; second, that the required warranties are implied by the submission of a bid and the acceptance certificates; and third, that section 7.4 is not one of the “minimum requirements listed in sections 4, 5, and 6” of the RFP, as stated in section 7.1.1, such that any further detail was
2. RFP Section 2.14, Insurance
RFP section 2.14 requires a winning bidder to procure and submit copies of certain proofs of insurance “before commencement of work,” not before submitting the bid. Proof of insurance is thus a condition of award of a contract, not a part of a bid. When SDPTO accepted the terms and provisions of the RFP, it agreed to comply with this insurance requirement. The bid also includes existing certificates of insurance for each of its subcontractors that would do the work.
The Moore group argues the insurance documentation provided wаs not sufficient because it pertained to SDPTO’s members, not to the separate corporate entity of SDPTO itself. 8 Even assuming this to be true, section 2.14 of the RFP did not require proof of insurance of SDPTO individually at the bidding stage, but rather at the stage of approval of the contract. Moreover, section 2.14 is not an “action or service item” under section 2.8, and thus no further detail was required in the bid. Thus, the Moore group’s objection on this ground is not well founded.
3. RFP Section 4.1.3, Credit Rating
The RFP requires that the bidder respond to the question of the bidder’s credit rating, by providing a “bank or other letter of reference.” SDPTO submitted a bank’s letter of reference for each of its five member entities, and showed that one of its members had sufficient financial strength to perform without help from the others. SDPTO also submitted a letter showing it had a performance bond in its own name. The Moore group claims that this showing in the bid was inadequate because no credit information for SDPTO, a separate corporate entity, was provided, as distinct from its constituents.
To evaluate the City’s approval of the SDPTO bid, we must determine whether there was a rational connection between the factors considered, the choice made, and the purpose of the regulations acted upon. Here, RFP section 4.1.3 required submission of a “bank or other letter of reference”
4. RFP Section 3, Statement of Work
Section 5.2.3 of the RFP requires the proposal format to include a narrative description of the technical approach to be used to accomplish the “Statement of Work” under the proposed contract. The RFP section 3 describes and sets criteria for such aspects of the towing business as business hours, employees, stоrage yards, trucks, etc., and is thus designed to describe the work to be bid upon. In its response to section 3, SDPTO described its methodology for performing the proposed contract and explained the operations involved in a typical tow call from start to finish. The SDPTO bid continues, “We have also included an Administration section and a Special Features section in order to address items that do not fall within the parameters of the ‘typical’ tow call (e.g. compliance requirements, fee payments, etc.). [¶] Our approach is designed to meet or exceed all of the specifications and requirements of the Request for Proposal. We hereby acknowledge and accept all terms and conditions of thе RFP, . . . including all requirements contained in the [City’s] General Provisions.” Thus, SDPTO agreed to comply with the requirements of the RFP, including these sections.
The Moore group’s argument is that the various requirements in the RFP section 3 “Statement of Work” have not been adequately described in the SDPTO bid, because there is no narrative description of the technical approach as to these particular subjects. Specifically, the bid is said to be inadequate as to sections 3.6 (response time), 3.7 (business records), 3.10 (negligent impound payment), 3.13.1 (tow dispatch center or system payments and fees), and 3.16 (compliance requirements).
9
While it is true that the format requirements of section 5 must be met in order for the bid to pass the minimum qualifications standard of section 7.1.1, that minimum requirement rule still does not specifically incorporate all the items listed in section
In any case, the City could reasonably have concluded that SDPTO provided sufficient information on the RFP section 3 provisions governing the above described topics. A “narrative description” is not a point-by-point response. The bid includes specific references to and descriptions of the challenged items, including SDPTO’s position on response time (§ 3.6), business records (§ 3.7), negligent impound payments (§ 3.10), tow dispatch payments and fees (§ 3.13.1), and complianсe reports (§ 3.16). SDPTO agreed to meet the required standards.
In conclusion, it is incorrect to characterize Deputy Chief Worden’s statements as misrepresentations which are a factual matter not to be reached on appeal. Rather, his statements were only part of the evidence before the Council, and did not prevent it from evaluating all the evidence. On the entire record, we conclude that the City could reasonably have found that the RFP requirements were satisfied by the SDPTO bid, and there were no material omissions interfering with the City’s ability to understand and approve that bid.
B
Sufficiency of the Moore Bid
The trial court upheld the City Council’s determination that the Moore bid was not responsive to the RFP. Examining the record, we find a transcript of the meeting of the evaluation committee, in which the members of the committee discuss the Moore bid, concluding that it was not responsive to the RFP in the areas of references, biographical sketches of key personnel, and business accounts and contracts However, Moore’s declaration states that the biographical data was not missing from his own copy when submitted, although the City contends it was missing from its copy. Moore also states that the missing documents were contained in a separate bid submitted for a citywide proposal by SDACT, as. well as an earlier Moore proposal, in 1993 and 1994. After the evaluation committee had completed discussion of the Moore bid, the members acknowledged there was background information about Moore in the overall bid by SDACT, but went on to find the SDACT bid nonresponsive.
At the City Council hearing on the protest, Moore’s attorney acknowledged that the Moore bid failed to include a few pages about background
On appeal, Moore cites to a copy of the Moore bid in the record which does cоntain the biographical data on key personnel and a listing of accounts and contracts. However, he appears to concede that the City Council was not given information in the operative Moore bid that was submitted (as opposed to earlier, related bids) about management background and experience, and business accounts and phone numbers of references. He thus argues that even if there were a clerical error due to missing pages in the City’s copy of the Moore bid, Moore should not have been disqualified since the same material was available in earlier versions of bids submitted by Moore or in which he participated. In his view, his bid was in substantial conformance with the RFP, so that the City erred in rеjecting it.
(Downtown Palo Alto Com. for Fair Assessment
v.
City Council
(1986)
In examining the act of a coordinate branch of government, the legislative branch, a court will not inquire into the wisdom of laws or regulations.
(Lockard
v.
City of Los Angeles, supra,
In
Monarch Cablevision, Inc.
v.
City Council
(1966)
In light of the admittedly incomplete nature of the Moore bid, and the uncertain availability and accuracy of the omitted material in related documents that had previously been submitted, the City Council had a reasonable basis to conclude that the Moore bid was not the most advantageous for the City. It was not compelled to find that the bid was in substantial conformity with the requirements, or to award the contract to Moore, in light of its right to negotiate in any manner necessary to serve the best interest of the City (RFP § 2.7), and in light of its obligation to seek the most advantageous contract for the City. On this record, the City’s decision was not “substantively irrational, arbitrary, capricious or wholly lacking in evidentiary support.”
(Lewin
v.
St. Joseph Hospital of Orange, supra,
Disposition
The order after hearing is construed as a judgment and is reversed to the extent that it determines the City Council abused its discretion in dismissing the protest concerning the sufficiency of the SDPTO bid, and to the extent that it remands the matter for reconsideration. The trial court is directed to enter a new judgment denying the petition on that basis. The balance of the judgment is affirmed to the extent that it denies thе petition to deem the Moore bid qualified. Each party to bear its own costs.
Nares, J., and Haller, J., concurred.
Respondents’ petition for review by the Supreme Court was denied August 14, 1996.
Notes
All statutory references are to the Code of Civil Procedure unless otherwise specified.
Moore had submitted a related bid in 1993, including background on his key management personnel and a listing of his accounts in 1993. Moore also participated with other contractors in submitting a city wide bid under the name San Diego Approved City Towers (SDACT) in 1994, which included biographical information about Moore.
In a related action not before this court, SDPTO sued the City, Moore, and the towing companies that received the other six district contracts, making claims of collusion and violations of various laws. Thаt action is still pending. (SDPTO v. City (Super. Ct. San Diego County, 1995, No. 681578).) The City brought a petition for writ of mandate and request for stay in both the related action and in this action, which were denied by order of December 1, 1995. (No. D024611.) However, it was ordered that this appeal be expedited. (Order of Dec. 1, 1995.)
On appeal, the City and SDPTO do not concede there were any material omissions in the bid, instead contending “SDPTO’s proposals responded to all required parts of the RFP.” (Italics added.) The difficulty lies in determining what parts of the RFP “required” responses. (See pt. II.A., post.)
Although the Moore group initially argued at trial that the matter should be considered to fall under administrative mandamus (§ 1094.5) as an adjudicative act, they have not pursued that claim on appeal.
In general, the trial court may not require consideration of material prepared after the agency has taken the action which is under review.
(Shapell Industries, Inc., supra,
The Moore group apparently is only pursuing arguments on appeal that eight of the cited ten omissions are material, as it has not presented any arguments here concerning RFP sectiоn 2.16, requiring disclosure of any felonies and financial interest in the subject of the contract, or RFP section 6.1, the cover letter requirement identifying offices, storage yards, qualifications to do business, and a corporate officer. We need not address these sections further. It should be noted that the Moore group submitted copies of both the 1993 and 1994 versions of SDPTO’s bids; it is the 1994 bid with which we are concerned. In this portion of the opinion, all “section” references are to the RFP.
SDPTO has five independent employees separate from the subcontractors.
RFP section 3.13.1 refers to a computer interface fee the City required to help run a dispatch center. Section 3.16 refers to an agreement to report tow information within 24 hours.