MIDWEST INDEPENDENT TRANSMISSION SYSTEM OPERATOR, INC., PETITIONER v. FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT NEW YORK INDEPENDENT SYSTEM OPERATOR, INC., ET AL., INTERVENORS
No. 03-1238
United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT
Decided November 12, 2004
Argued October 7, 2004; Consolidated with 03-1254
On Petitions for Review of Orders of the Federal Energy Regulatory Commission
Stephen L. Teichler argued the cause for petitioners and intervenors in support of petitioners. With him on the briefs
Lona T. Perry, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With her on the brief were Cynthia A. Marlette, General Counsel, and Dennis Lane, Solicitor.
Before: ROGERS, TATEL, and GARLAND, Circuit Judges.
Opinion for the Court filed by Circuit Judge TATEL.
TATEL, Circuit Judge: Obligated by statute to recoup its costs from industries it regulates, the Federal Energy Regulatory Commission funds its electricity-related programs through annual charges to public utilities based on the volume of electricity they transmit. In this case, two transmission providers, having unsuccessfully petitioned FERC to base those charges on sales as well as transmissions—an approach the Commission once followed but has now abandoned—ask this court to order FERC to reconsider its position. They argue that changed circumstances warrant a new rule because in the wake of severe disruptions in California and other western electricity markets, FERC has shifted its focus from transmission to sales—an allegation FERC vehemently disputes. Because we order rulemaking “only in the rarest and most compelling of circumstances,” WWHT, Inc. v. FCC, 656 F.2d 807, 818 (D.C. Cir. 1981), and because we defer to an agency‘s view of its own regulatory priorities, we deny the petition for review.
I.
The Omnibus Budget Reconciliation Act of 1986 (the “Budget Act”) requires that “the Federal Energy Regulatory Commission shall, using the provisions of this section and authority provided by other laws, assess and collect fees and annual charges in any fiscal year in amounts equal to all of the costs incurred by the Commission in that fiscal year.”
FERC first implemented
Because FERC‘s new initiatives meant increased focus on “assuring open and equal access to public utilities’ transmission systems,” as opposed to monitoring wholesale electricity rates, FERC proposed to “assess our electric regulatory
Meanwhile, the electricity industry had entered a crisis. Beginning in June 2000, wholesale prices in California and other western states, driven by a combination of high gas costs, unusual weather, and slack supply, climbed to what FERC later called “unprecedented” levels. See FERC, Annual Performance Report for Fiscal Year 2001, at 1, 5 (Mar. 2002), http://www.ferc.gov/about/strat-docs/FY01-PR.pdf (“FY2001 Report”). As a result, retail costs in some areas rose by 200 to 300 percent, while two major California utilities, barred by state law from raising retail prices yet forced to buy power at short-term market rates, incurred crippling debts. See In re Cal. Power Exch. Corp., 245 F.3d 1110, 1114-16 (9th Cir. 2001) (“CalPX”); FY2001 Report at 5. In response, FERC intervened and canceled a mandatory spot market, thus freeing utilities to enter long-term forward supply contracts. See CalPX, 245 F.3d at 1116-18; FY2001 Report at 5-6. At the same time, FERC launched an investigation of market problems and eventually ordered refunds for excessive wholesale prices. See CalPX, 245 F.3d at 1118-19; FY2001 Report at 5-6.
Caught off guard by the California debacle, FERC was contrite, stating in its FY2001 Annual Performance Report, “we have a duty to change the way we do business in light of the Western energy crisis.” FY2001 Report at 7. Accord-
FERC nonetheless stuck with Order No. 641 and assessed the first charges under the new system in July 2002. Though FERC had denied a rehearing request shortly after issuing Order No. 641, see Revision of Annual Charges Assessed to Public Utilities, Order No. 641-A, 94 F.E.R.C. ¶ 61,290, 66 Fed. Reg. 15,793 (2001), the New York Independent System Operator, Inc. (“NYISO”) and other transmission providers filed fresh challenges based on their first bills. Among other things, they argued that the SMD proposal evidenced an attention to wholesale markets inconsistent with FERC‘S
MISO now petitions for review of these two orders. NYISO has intervened in support.
II.
Although both parties assure us that we have jurisdiction over this case, we have an independent obligation to be certain. See Steel Co. v. Citizens for a Better Env‘t, 523 U.S. 83, 94-95 (1998). We may consider petitions filed directly in this court—as was MISO‘s—only if Congress has provided for initial review in the courts of appeals. Otherwise, parties challenging agency action must first seek relief in the district court, proceeding to this court only on appeal—a procedure confusingly termed “nonstatutory review.” See Five Flags Pipe Line Co. v. Dep‘t of Transp., 854 F.2d 1438, 1439-40 (D.C. Cir. 1988). In this case, the jurisdictional basis advanced by the parties,
The Commission shall have power to perform any and all acts, and to prescribe, issue, make, amend, and rescind such orders, rules, and regulations as it may find necessary or appropriate to carry out the provisions of this chapter [i.e., the FPA].
To be sure, without
The statutory context here—broad rulemaking power plus a substantive statute calling for implementation via other authorities—distinguishes this case from Five Flags. In that case, we held that a direct review provision limited to orders “issued under this Act” excluded challenges to user fees imposed by the Secretary of Transportation pursuant to a different statute. See Five Flags, 854 F.2d at 1440-41 (quoting Pub. L. No. 90-481, § 6, 82 Stat. 724 (1968)). The statute containing the review provision at issue, however, conferred much narrower rulemaking power than does the FPA: far from allowing all “necessary or appropriate” actions, as the FPA does, the Natural Gas Pipeline Safety Act (the “Gas Act”), Pub. L. No. 90-481, 82 Stat. 720 (1968) (codified as amended at
Our decisions in General Electric Uranium Management Corp. v. United States Department of Energy, 764 F.2d 896 (D.C. Cir. 1985), and City of Rochester v. Bond, 603 F.2d 927 (D.C. Cir. 1979), support our jurisdiction in this case. In the first case, we exercised jurisdiction under the direct review
In City of Rochester, we held that a petition alleging that the Federal Aviation Administration had violated the National Environmental Policy Act of 1969 (“NEPA”),
Given that FERC‘s fee regulations not only implement the Budget Act, but also help “carry out” the FPA, bringing them within the scope of section 825h, the placement of section 7178 in the Budget Act affords no “firm indication” that Congress intended to depart from this “sound policy” embodied in the FPA‘s direct review provision.
III.
Turning to the merits, we review FERC‘s denial of MISO‘S petitions under familiar APA standards, reversing only if FERC‘s action was “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.”
Apart from their argument regarding changed circumstances, MISO‘s and NYISO‘s briefs assert various statutory and policy-based reasons for overturning FERC‘s system of charges: that cost causation principles bar the Commission from assessing charges only on transmission providers when FERC‘s regulatory activity is also directed at sellers; that assessing charges on bundled load transmitted by ISOs and RTOS, as Order No. 641 requires, exceeds FERC‘s jurisdiction because the load does not travel in interstate commerce; that assessing such charges deters local utilities from joining ISOs and RTOs; and that Order No. 641 contradicts the Commission‘s method of calculating gas pipeline user fees. At oral argument, however, counsel for MISO and NYISO withdrew these contentions.
Claiming that divestiture of transmission and generation assets has stalled, the ISOs argue that Order No. 641‘s methodology causes a greater disincentive to RTO/ISO formation than FERC expected. But although MISO and NYISO argued before the Commission that the order “works as a penalty to RTO participation”—one of the policy arguments they have now withdrawn—neither the rulemaking petition nor the petition for rehearing pointed to changed circumstances in the electricity industry as a factor bearing on the alleged disincentive. Because the ISOs have presented no “reasonable ground” for this default, we lack jurisdiction to consider their argument. See
This leaves only one argument for us to consider: that in response to the California crisis, FERC changed its regulatory focus and thereby undermined Order No. 641‘s factual basis. On this issue, we owe considerable deference to FERC‘s views, not only because of the “extremely limited,
Arguing that FERC‘s “situation [is] analogous to The Honeymooners when Ralph Kramden‘s caught red-handed ... [and] turns to Alice and demands whether she‘s going to believe him or her own eyes” (Tr. of Oral Argument at 12), MISO and NYISO cite three examples of FERC‘s purported focus on sales. First, they identify significant sales-related efforts in FERC‘s response to the California crisis, including investigations of allegedly excessive prices. Second, they point to FERC‘s efforts, evidenced by its annual reports and the creation of OMOI, to strengthen oversight of wholesale electricity markets. Finally, they cite the SMD proposal as evidence that FERC‘s future work will tilt toward structuring efficient markets rather than assuring transmission access.
In our view, none of this evidence reveals a dramatic change in FERC‘s priorities. To the extent the Commission‘s California intervention focused on sales, its actions reflected the imperatives of a singular event—a “perfect storm,” FERC calls it (Resp‘t‘s Br. 47)—not a sustained shift in regulatory priorities. As to the more permanent changes, some—particularly the creation of OMOI—may indeed reflect renewed commitment to market oversight. Yet FERC never suggested in Order No. 641 that it would focus exclusively on transmission; instead, it stated that “the time and effort of our electric regulatory program is now increasingly devoted
Indeed, the very documents cited by MISO and NYISO—the annual reports and the SMD proposal—demonstrate that transmission reform remains a top priority. The FY2002 report, for example, stresses that the goal of “complet[ing] the transition to competitive energy markets as quickly and comprehensively as possible,” id.—FERC‘s “primary emphasis,” id. at 5—“furthers work on initiatives begun in the last couple years,” presumably including the transmission-related orders. Id. at 6. Similarly, while the SMD initiative calls for a standardized market design, describing “[m]arket monitoring at all times, and market power mitigation when needed,” as “critical pieces of this initiative,” SMD NOPR, [Proposed Regs. 1999-2003] FERC Stats. & Regs. at 34,281, 67 Fed. Reg. at 55,455, it also proposes measures aimed at “remedy[ing] remaining undue discrimination” in transmission access—including “exercis[ing] jurisdiction over the transmission component of bundled retail transactions,” modifying tariffs to offer “consistent transmission rules for all transmission customers,” and mandating that transmission owners “contract with an independent entity to operate their transmission facilities.” Id. In addition, the proposal sets out plans for a “congestion management system” designed to
As a fallback, the ISOs argue that FERC inadequately explained its denial of their petitions. See Am. Horse Protection Ass‘n v. Lyng, 812 F.2d 1, 7 (D.C. Cir. 1987) (holding that agency action was arbitrary and capricious where “the Secretary ha[d] not presented a reasonable explanation of his failure to grant the rulemaking petition”). It is true that FERC‘s principal rationale for denying new rulemaking—that it had “already considered and rejected” the petitioners’ arguments, 103 F.E.R.C. at 61,179—makes little sense insofar as the ISOs were asserting a change in circumstances. Yet FERC went on to explain that “a primary focus of the Commission‘s efforts in reforming the western markets and a primary focus of the SMD NOPR [notice of proposed rulemaking] is transmission,” citing in particular FERC‘s plans, noted earlier, for “a revised open access transmission tariff that is intended to remedy remaining undue discrimination,” and a “transmission congestion management system to ensure that public utilities manage the Nation‘s interstate transmission grid efficiently.” Id. at 61,180. FERC also explained that “much of the Commission‘s efforts involving western markets go to whether public utilities have used transmission schedules and constraints to manipulate prices or exercise market power.” Id. FERC‘s denial of the rehearing petition, while pledging that “the issues may merit further consideration at a later time and we will reevaluate whether a new rulemaking is warranted at that later time,” stated that “[t]he thrust of the Commission‘s current work involves the regulation of transmission.” 104 F.E.R.C. at 61,209. Though brief, these explanations easily satisfy FERC‘s limited burden of justification under our “highly deferential” standard of review. Nat‘l Customs, 883 F.2d at 96.
IV.
For federal agencies, as with mice and men, the best-laid plans often go awry. See Robert Burns, To a Mouse, On Turning Her up in Her Nest with the Plough (1785). We trust that FERC—as it has promised—will reconsider its system of charges if the resource-allocation assumptions underlying Order No. 641 prove false. At this early juncture, however, on the heels of a highly unusual four-year period and in the face of the Commission‘s continued efforts to reform transmission, we decline to override FERC‘s view of its own priorities and compel new rulemaking. Accordingly, we deny the petition for review.
So ordered.
