Respondent, Middleborough Horizontal Property Regime Council of Co-owners (the Regime), 1 instituted this action against appellants, Montedison S.p.A. and Montedison USA, Inc. (referred to collectively as Montedison) and others, for damages sustained as a result of defective roofing materials installed on the condominiums. The Regime alleged several causes of action including negligence, breach of implied warranty, breach of express warranty, strict liability in tort, breach of warranty accompanied by fraudulent conduct, and violation of the Unfair Trade Practices Act. Prior to trial, the court granted the Regime’s motion for partial summary judgment as to liability against Montedison on the ground of non-mutual offensive collateral estoppel. Montedison appeals. We affirm in part, reverse in part and remand.
Facts and Procedural History
Montedison S.p.A. is an Italian chemical corporation. Montedison USA, Inc. is a wholly owned subsidiary of Montedison S.p.A. and markets certain Montedison S.p.A. chemical products in the United States.
In 1981, Middleborough Apartments were converted into condominium units. As part of the conversion, the roof was replaced. Middleborough contracted with Love and Cobb Architects to provide architectural services related to the replacement of the roof, and with Southeastern Waterproofing Company, Inc. to install the roof.
After conferring with Love and Cobb, Southeastern decided to replace the roof using Flagon C materials. The new roof consisted of a lV2-inch layer of expanded polystyrene insulation placed over the existing roof, a layer of Flagon C roofing membrane, and a layer of washed river stones as ballast. 2
On October 14,1981, Flag issued two consecutive five-year written guarantees to Middleborough whereby it guaranteed “to maintain the Flagon roof ... in a watertight condition.” Within the warranty period, the roofing system failed, resulting in extensive water damage to the condominiums due to leakage. The Regime notified Southeastern, Watpro, and Flag of the leakage, but was unsuccessful in its attempts to have the roof repaired. Eventually, the Regime had the roof repaired at its own expense. The instant litigation ensued. .
Prior to trial, the Regime moved for partial summary judgment against Montedison as to liability. The motion was premised on the fact that “underlying issues regarding the role, responsibility, and liability for the development, production, and marketing of the roofing material which failed [had] been previously adjudicated against [Montedison]” who was collaterally estopped from relitigating those issues. In support of this argument, the Regime referred the trial court to the Minnesota Supreme Court’s holding and findings of fact in
Church of the Nativity of Our Lord v. WatPro, Inc., Montedison S.p.A. and Montedison U.S.A. Inc., et al.,
In opposition to the Regime’s motion, Montedison argues summary judgment on the basis of offensive collateral estoppel was improper because the instant litigation involves issues which were not litigated in Nativity. Montedison also argued the trial court should not give collateral estoppel effect to the holding in Nativity because it is inconsistent with the holding in Curtiss-Wright Corp. v. Rainbow Roofing, et al., No. L-35834-88, L-39567-88 (N.J. Super. Ct. Law Div. 1991), a subsequent action wherein Montedison was found not liable for a failed Flagon roof.
Discussion
I.
At the heart of Montedison’s appellate arguments is its contention the trial court erred in granting the Regime’s motion for partial summary judgment because issues relating to liability in this case have not been previously litigated. Specifically, Montedison contends, among other things, that the issue of whether or not the Flagon roof involved in this case was properly installed has never been litigated because the
Nativ
ity
case did not involve a claim of improper installation. Montedison claims there exists evidence the Regime’s roof failed because it
The doctrine of nonmutual offensive collateral estoppel was adopted in this State by this court in
Beall v. Doe,
While it is true improper installation was not an issue in Nativity, we agree with the trial court that Montedison’s agency relationship with Flag and Watpro and the question of the defectiveness of the Flagon material were litigated. In Nativity, Flag issued guarantees on a Flagon roof. 3 The Nativity court found an agency relationship existed between Montedison and Flag as well as between Montedison and Watpro. The Nativity court further found that all of Flag’s and Watpro’s activities relevant in Nativity, including the issuance of guarantees, fell within the scope of their agency relationship with Montedison. Montedison is precluded, therefore, from denying its agency relationship with Flag and Watpro for purposes of having issued the guarantees on the Regime’s roof.
We further hold Montedison is precluded from relitigating issues concerning defects in the Flagon material. The Nativity court held the Flagon materials 4 installed on the Church’s roof were defective due to an improper chemical formulation which causes plastercizer migration. Because Montedison does not claim the Flagon C material installed on the Middleborough roof is any different from the Flagon C material installed on the Nativity roof, Montedison is estopped from denying the product is defective.
II.
Montedison also maintains the trial court erred in giving preclusive effect to the
Nativity
decision because that decision is inconsistent with the
Curtiss-Wright
decision. Montedison argues that under the doctrine of
res judicata,
when two inconsistent final judgments are rendered, the latter judgment is accorded conclusive effect in a third action. Restatement (Second) of
Judgments
§ 15 (1982). While these are correct statements of law, we cannot under the facts of this case determine the applicability of
Curtiss-Wright.
The text of the
Curtiss-Wright
decision was neither introduced into the trial record, nor included in the record on
III.
The trial court granted the Regime’s motion for partial summary judgment based in part on its finding that even if the roof’s failure was caused by defective installation of the Flagon material, the guarantee covered such installation. The guarantee provides, in pertinent part:
Flag S.A.S. guarantees to maintain the Flagon roof of Middleborough ... in a watertight condition at its own expense for a period of [ten years] provided that the owner gives WATPRO, INC., our exclusive agent, written notice of any leaks within 30 days from discovery of such leaks.
. . . This guarantee is solely intended to cover any condition caused by defective Flagon brand material produced with compounds made by and under the supervision and control of Montedison, the installation or ordinary wear and tear thereof.
While conceding the guarantee warrants installation, Montedison, nevertheless, claims the guarantee is limited to the installation of defective Flagon material. Montedison postulates “the guarantee does not cover non-defective Flagon material. Therefore, if non-defective Flagon material failed because of improper installation there would be no coverage.”
The construction and enforcement of an unambiguous contract is a question of law for the court, and thus can be properly disposed of at summary judgment.
Lyles v. BMI, Inc.,
The trial court apparently found the guarantee unambiguous and warranted the installation of the Flagon brand material without regard to whether the material was defective or not. Because the installation of the Flagon material was not an issue in
Nativity,
that court necessarily did not construe the guarantee from the standpoint of whether the guarantee excluded the installation of non-defective Flagon material as contended by Montedison.
6
We fail to see how construction of the guarantee avails Montedison anything in view of the
Nativity
court’s finding that Flagon is defective when considered in conjunction with Montedison’s concession that the guarantee covers installation of defective materials. Nevertheless, Montedison argues defective material did not fail in this instance, but rather non-defective Flagon material failed because it was improperly
IV.
Nevertheless, we hold summary judgment was premature as to the cause of action in negligence. Summary judgment should be granted only when there is no genuine issue as to any material fact and the moving party is entitled to judgment as a matter of law. Rule 56, SCRCR The evidence and all inferences which can be reasonably drawn from the evidence must be viewed in the light most favorable to the nonmoving party.
Calvert v. House Beautiful Paint and Decorating Center, Inc.,
V.
Montedison finally argues the trial court’s grant of summary judgment was inappropriate inasmuch as it did not have a full and fair opportunity to conduct discovery, citing
Baughman v. American Tele, and Tele. Co.,
Affirmed in part, reversed in part and remanded.
Notes
The Regime brought this action in its capacity as representative of the individual owners of Middleborough condominium units.
Ballast is a layer of coarse gravel, crushed rock, or smooth stones laid to form a bed for the purpose, in this case, of “restraining” the roofing membrane.
Aside from the names of the parties, square footage and dates identified in the guarantees, the guarantees issued to the Regime are identical to those issued to the Church in the Nativity case.
As we read the trial court’s order and the appellate court’s opinion in Nativity, both the Flagon C and Flagon SF materials were found to be defective.
As to the Curtiss-Wright decision, the record on appeal contains only-pleadings, special interrogatories to the jury, and the jury’s answers to those interrogatories.
Montedison states in its brief:
The Regime misinterprets the Flagon guarantee as blanket protection for improper installation. This interpretation ignores the term “defective” expressly stated in the guarantee. According to the Regime’s interpretation, even if nothing was inherently wrong with the Flagon material and the Flagon was damaged by improper installation, then Flag would have nonetheless guaranteed the product. Such an interpretation is absurd as no manufacturer guarantees a product when it is improperly used.
The trial court found a breach of implied warranty because the Flagon material “was not fit for its particular use on Middleborough’s roof as it existed when Montedison’s product was guaranteed on the Middleborough roof.” We observe, however, that the finding of an express warranty precludes Middle-borough from recovering also on an implied warranty touching on the same obligation of the parties.
Jones v. Winn-Dixie Greenville, Inc.,
— S.C. —,
As with the implied warranty cause of action, an election of remedies may at some point be required to avoid double recovery.
Montedison S.p.A. submitted to jurisdiction approximately one week prior to the hearing on the motion for summary judgment.
The trial court found Montedison failed to comply with Rule 56(f), SCRCP in that it did not present affidavits showing reasons why it could not obtain necessary affidavits. Montedison responds in its brief that because “of the early stage of discovery, Montedison was not in a position to present affidavits as to why certain items of discovery were not available.”