Mickelsen v. Craigco, Inc.Mickelsen v. Craigco, Inc.
Lead Opinion
Plaintiff Garry W. Mickelsen brought this action to foreclose a mechanic’s lien which he had recorded against the River Oaks subdivision owned by defendant Cra-igco, Inc. Defendant Sherwood & Roberts, Inc., which was the beneficiary of a trust deed on the subdivision, moved for summary judgment on three grounds: (1) that plaintiffs foreclosure action had not been timely commenced; (2) that plaintiffs recorded notice of lien was invalid because it had not been properly verified; and (3) that no work had been done in the subdivision and no materials had been furnished as required by
In July 1978, Craigco began development of the subdivision. In October 1978, a boundary survey was made by a surveyor, who set more than twenty stakes in the ground. Later, there was additional surveying and setting of over two hundred stakes to mark the center line of proposed roads as well as water, sewer, and storm sewer lines. In April 1979, plaintiff dug six test holes for soil and water studies. Plaintiff claims that before the end of 1979, the proposed roads were rough cut, the land was “cleared and grubbed,” and an old dairy barn and corrals were demolished and removed from the property. On December 28, 1979, Sherwood & Roberts made a loan to Craigco which was secured by a trust deed on the property which was recorded on that date.
During 1980 and up to about August 28, 1981, plaintiff furnished labor and materials to install the water lines, sewer lines, and storm sewer lines. Three times during the course of his work, plaintiff, at the request of Craigco, suspended work for thirty days or more. The periods of suspension of work were August 22 through October 2, 1980; November 1, 1980, through January 2, 1981; and March 13 through July 26, 1981. On September 30, 1981, plaintiff recorded a notice of mechanic’s lien on the property to secure the payment of over $62,000 which was then past due. On April 29, 1982, he commenced the instant action to foreclose that lien.
On motion for summary judgment by Sherwood & Roberts, it contended and the trial court agreed that plaintiff was required to bring any foreclosure action within twelve months after the suspension of any work and therefore plaintiff had no valid lien for work done by him prior to March 13,1981, and any lien for work done after that date was junior to the trust deed.
*563 Actions to enforce the liens herein provided for must be begun within twelve months after the completion of the original contract, or the suspension of work thereunder for a period of thirty days.
We do not subscribe to the trial court’s interpretation of
The rationale for our decision in Totorica is that the mechanic’s lien law was enacted for the benefit of those who perform the labor and supply the materials and that the lien claimant’s remedy should not be limited without a clear mandate from the legislature requiring such an effect. We therefore conclude that plaintiff commenced his action to foreclose his lien within the time afforded by
Defendant next contends that the notice of lien filed by plaintiff was invalid since he admittedly did not make an oral averment as to the truthfulness of its contents to the notary public before whom he appeared.
Our decided cases do not appear to be entirely harmonious as to what is required for a proper verification. In one of the earliest cases on the subject, Spangler v. District Court of Salt Lake County,
Between our decisions in Spangler and Colman, we decided two cases in which the strict requirements of Spangler were not adhered to. In State v. Mathews,
A survey of cases from other jurisdictions reveals that many of them do not require that the affiant raise his hand or
(1) there must be a correct written oath or affirmation, and (2) it must be signed by the affiant in the presence of a notary or other person authorized to take oaths, and (3) the latter must affix a proper jurat.
There is no minimum requirement that an oath must be administered to the affiant or that the affiant must speak an oral oath or affirmation or raise his or her hand. We overrule Colman v. Schwendiman and Spangler v. District Court of Salt Lake County to the extent that they conflict with this new rule. However, our decision today in no way disturbs First Security Mortgage Corp. v. Hansen,
In the instant case, the form of verification on the notice of mechanic’s lien recorded by plaintiff was properly worded so that by signing it, plaintiff swore to the truthfulness of the contents of the notice of lien.
We note that in early 1988 after the instant case had been argued and submitted to this Court, the legislature amended our statutes governing notaries public and enacted the “Notaries Public Reform Act.”
Defendant’s third ground for its motion for summary judgment was that the work which was done in the subdivision by plaintiff and other mechanics prior to the rec-ordation of defendant’s trust deed, the work relied on by plaintiff in bringing his claims of priority over the trust deed, was insufficient to satisfy the requirements of
Notes
. The legislature amended this statute in 1985 to delete the requirement of verification. See
. The verification on the notice of lien form states: "[ ] being first duly sworn, says that he is claimant in the foregoing Notice of Lien; that he has heard/read said notice and knows the contents thereof, and that the same is true of his own knowledge. [Signed,] subscribed and sworn to before me this_day of-, 19_[notary’s signature and seal].”
Concurrence Opinion
(concurring):
I join the majority in departing from our decisions in Colman v. Schwendiman,
The question of the formalities required in the execution of documents is one upon which the legislature has spoken repeatedly, albeit with no apparently coherent overarching principles in mind.
I agree with the policy judgment that underlies the majority opinion: there is little reason to require these technicalities in this day of simplified practice and procedure. However, a complete remedy for the problems created by these statutes would be the legislature’s enactment of a law repealing technical swearing requirements in all statutes and substituting the simple requirement that the documents or statements in question be signed or made under penalty of perjury.
It is to be hoped that by adopting the position taken today and obviating some of the most unsettling consequences of the Colman and Spangler approach, we have not induced the Bar and the legislature to believe that the problem has been finally laid to rest. It would be most unfortunate
. See, e.g.,
. The legislature has repealed the technical swearing requirements construed in Colman, Spangler, and this case. See
The legislature has adopted the approach that I am advocating in the limited context of the Utah Uniform Probate Code. See
Concurrence Opinion
(concurring and dissenting):
I join the Court in following precedent which interpreted
The underlying policy considerations for the requirement of verification are as stated in First Security Mortgage Co. v. Hansen:
A lien creates an encumbrance on property that deprives the owner of his ability to convey clear title and impairs his credit. The filing of a lien for an excessive amount could be used to force a settlement unfairly weighed in favor of the claimant. Such abuse is made a misdemeanor by § 38-1-25. These serious consequences justify the statutory imposition of a requirement that one who makes the claim must furnish a sworn statement to the truthfulness of the facts giving rise to it. Frivolous, unfounded, and inflated claims can thereby be minimized, and the prejudgment property rights of the individuals receive their due protection.4
Thereupon, we concluded that verification is a mandatory condition precedent to the very creation and existence of a lien.
In Graff v. Boise Cascade Corp.
In the instant case, plaintiff’s own testimony was that he executed the notice of lien without being placed under oath and did not recite under oath any of the matters stated in the notice before the notary who placed her signature and notarial seal on the instrument. Without such verification, no lien was created.
I would affirm the judgment of the trial court, albeit on these different grounds.
. Totorica v. Thomas,
.
.
. Id.
.
.
.
. Id. at 31 (citing and relying upon Spangler v. District Court of Salt Lake County,