Michigan Gas Co. v. Federal Energy Regulatory CommissionMichigan Gas Co. v. Federal Energy Regulatory Commission
Lead Opinion
MOORE, J., delivered the opinion of the court, in which DAUGHTREY, J., joined. WELLFORD, J. (pp. 1272-73), delivered a separate concurring opinion.
OPINION
Petitioner Michigan Gas Company (“Mi-Gas”) petitions for review of two orders of the Federal Energy Regulatory Commission (“FERC” or “the Commission”) authorizing construction by ANR Pipeline Company (“ANR”) of a new delivery point for natural gas. The Commission gave its approval over the protest of MiGas, which intervened at the agency proceeding. MiGas contends that the Commission failed to state its reasons for the authorization and failed to hold an evidentia-ry hearing. The Board of Public Works of the City of Holland, Michigan (“BPW’), as an intervenor, challenges MiGas’s standing to bring this appeal. For the reasons stated below, we deny the petition for review.
I. BACKGROUND
MiGas is a local distribution company (LDC) that has a nonexclusive franchise to supply natural gas to consumers in Holland, Michigan. Among its customers is one of three electricity-generating plants operated by BPW, which is the exclusive provider of electricity to consumers in Holland. BPWs James DeYoung Plant is a coal-fired stаtion that uses natural gas for ignition purposes. BPWs other two generating stations currently burn oil; one of them, the 48th Street Peaking Station, can use natural gas. MiGas has never supplied gas to the 48th Street Station.
After negotiating with several gas suppliers (and rejecting a bid from MiGas), BPW contracted with ANR, an interstate pipeline company, and with another supplier, Con
ANR, an interstate gas company subject to the jurisdiction of the Natural Gas Act (“NGA”), applied for FERC authorization to construct the delivery tap. Under the NGA, an interstatе gas company must obtain a certificate of public convenience and necessity before constructing a transportation facility (i.e.pipeline) or a connection to a local facility. NGA § 7 (15 U.S.C. § 717f). Mi-Gas filed a protest pursuant to 18 C.F.R. § 157.205(f). BPW and Michigan Consolidated Gas Company also intervened. MiGas argued that granting authorization to ANR to сonstruct the delivery tap would not be in the public interest, which under the NGA is the governing concern. MiGas asserted that a comparative analysis demonstrated that the cost of the proposed connection to ANR would far exceed the cost of a connection to MiGas at MiGas’s proposed rate. MiGas contended that because the ANR connection would be so much more expensive, it would not serve the “public convenience and necessity.” See NGA § 7(e). MiGas further argued that the construction of the BPW pipeline and the ANR connection would create wastefully duplicative facilities, and that interconnection with MiGas would be more economical and would providе greater flexibility of supply. It also contended that BPWs plan to build a pipeline and connect to ANR was “likely to be the first step in a plan to serve other high load factor customers [e.g., utilities, as opposed to residences] now served by Michigan Gas.” J.A. at 36. MiGas requested that the Commission deny ANR’s application, or in the alternative, conduct an evidentiary hearing to determine whether the construction would be in the public interest.
The Commission rejected all of MiGas’s arguments and granted the authorization, citing its policy of allowing competition between LDCs and interstate pipelines absent evidence of “anticompetitive or unduly discriminatory behavior,” as well as a policy of honoring the choice of the end-user — here, BPW. 71 F.E.R.C. ¶ 61,289 (1995). The Commission stated that MiGas had proffered no evidence of anticompetitive or discriminatory behavior. MiGas requested a rehearing, which the Commission denied, again discussing its current policy. 78 F.E.R.C. ¶ 61,044 (1995). MiGas filed a Petition for Review of those two orders in this court. BPW was granted leave to intervene on behalf of the rеspondent.
II. STANDING
BPW challenges MiGas’s standing to pursue this appeal, arguing that MiGas has suffered no injury from the Commission’s orders, that any alleged injury is not redress-able, and that MiGas does not have an interest protected by the Natural Gas Act. MiGas responds that it is an “aggrieved” party pursuant to NGA § 19(b) (15 U.S.C. § 717r(b)) and that it has been injured as a competitor of BPW. BPW contended at oral argument that MiGas cannot rely on its alleged competitive injury because it did not allege such injury in its application for rehearing; any objection not raised in the rehearing application cannot be argued on appeal. NGA § 19(b). The limitation imposed by § 19(b) on a petitioner’s arguments on the merits, however, does not delimit this court’s standing inquiry. Standing “is a qualifying hurdle that plaintiffs must satisfy even if raised sua sponte by the court.” Community First Bank v. National Credit Union Admin.,
Section 19(b) states that “[a]ny party to a proceeding under this chapter aggrieved by an order issued by the Commis
The two standards are similar but not identical; “[cjommon to both these thresholds is the requirement that petitioners establish, at a minimum, ‘injury in fact’ to a protected interest.” Shell Oil,
At oral argument, MiGas conceded that it was not basing its сlaim of injury on the loss of the opportunity to supply the 48th Street Station, focusing instead on the alleged competitive threat posed by BPW to MiGas’s ability to retain its other customers. For standing purposes, MiGas contends that its injury is that the FERC orders will result in BPW having the ability to “run amok,” going beyond merely transporting gas for use at the 48th Street Station to establish itself as a cоmpetitor in supplying gas to other customers in Holland.
MiGas also cannоt meet the second and third requirements for Article III standing. Even if its alleged injury meets the standard, MiGas also must be able to establish that the injury was caused by the FERC orders and that this court could redress the injury by vacating the orders and remanding to the Commission. See North Carolina Utils. Comm’n v. FERC,
For the same reasons, MiGas must fail the third prong of the constitutional inquiry. Even, if this court vacated the FERC orders, it would not redress MiGas’s alleged injury. The inability of ANR to supply gas to BPW would not necessarily force BPW to turn to MiGas, and would not stop BPW from establishing itself as a gas supplier if it did decide to do so. BPWs ownership of its own pipeline, and its connection to another LDC, would allow it to pursue other options.
The last requirement for standing is prudential, rather than constitutional. In administrative law cases, including those under NGA § 19(b), federal courts require that the alleged injury be to an interest that is “ ‘arguably’ within the zone of interests sought to be protected” by the statute at issue. Panhandle Producers and Royalty Owners Ass’n v. Economic Regulatory Admin.,
MiGas’s interest is arguably within the zone of interests that the Natural Gas Act was meant tо protect.
[c]ompetitors have a seemingly unbroken record of success in securing standing to challenge decisions involving agency licensing. ... This success may seem perplexing in light of many judicial assertions of a broad national policy in favor of competition in virtüálly every area of regulation .... But a 'license system by its very nature restricts entry into a particular field or transaction. Firms already operating within the restrictеd area, or in competition with such firms, benefit from vigorous enforcement of the restriction.
Id. (citations omitted); accord Associated Gas Distributors v. FERC,
This court has held in a different context that competitors seeking to limit competition can further congressional objectives even when the legislative history shows that limiting competition was not Congress’s intent. See Community First Bank v. National Credit Union Admin.,
Even if MiGas meets the prudential “zone of interests” test for standing, however, its failure to satisfy the constitutional test is fatal. Because MiGas cannot satisfy the requirements of injury in fact, causation, and redressability, we hold that it does not have standing to seek review in this court. For that reason, we DENY the petition for review of the two Commission orders.
Notes
. An order may be reviewed either in the Court of Appeals for the District of Columbia or in the Court of Appeals “for any circuit wherein the natural-gas company to which the order relates is located or has its principal place of business....” This petition for review is properly before this court because ANR, the relevant company in this case, maintains its headquarters in Michigan. See ANR Pipeline Co. v. Conoco, Inc.,
. The Federal Power Commission (FPC) preceded FERC in administering the Natural Gas Act. See Department of Energy Organization Act, §§ 402(a)(l)(C)-(F), (2)(B), Pub.L. No. 95-91, 91 Stat. 583-84 (1977) (transferring functions of the FPC under the NGA to FERC).
. The Commission has no authority under the NGA to prevent BPW from setting itself up to compete with MiGas; its authority is limited to the approval or disapproval оf ANR's delivery tap. See NGA § 1(b) (15 U.S.C. § 717(b)) (stating that the Act covers transportation and sale of gas in interstate commerce, and natural gas companies engaged in such transportation or sale, and specifically excludes from its coverage intrastate transportation and sale, local distribution, and facilities used for local distribution or for productiоn). ANR is an interstate gas company transporting gas by pipeline into Michigan; the proposed delivery tap would be used to transport gas from an interstate pipeline to a consumer. BPW is within the Commission’s jurisdiction only as a customer seeking to purchase gas in interstate commerce from ANR’s pipeline.
Since MiGas apparently is most conсerned about the potential future actions of BPW, rather than about competition from ANR, the regulated entity, the jurisdictional basis for this entire challenge is dubious — particularly in light of MiGas’s statement at oral argument that it conceded the loss of the 48th Street Station’s business to ANR.
. Regardless of MiGas's obvious objection to the construction of BPW’s pipeline, that construction is necessarily outside the jurisdiction of FERC under the NGA, and therefore outside the jurisdiction of this court on appeal. BPW’s pipeline is owned and operated not by an interstate gas company for the purpose of transport in interstate commerce, but by an "end-user” (ultimate consumer of gas) for the purpose of obtaining gas for its own local consumption. See, e.g., Kansas Power and Light Co. v. FERC,
. Though MiGas has emphasized the pоtential competition between itself and BPW — two nonjurisdictional entities — its standing to challenge the FERC orders must be based on its status as a competitor with ANR, the regulated entity. Mi-Gas can meet the "zone of interests” test only by showing a nexus of its interest with the subject matter of the NGA. Since ANR is covered by the NGA and MiGas and BPW are not, MiGas must hang its standing on competition with ANR.
Concurrence Opinion
concurring.
I agree with much of what my colleague has written on this difficult case. In sum, I believe we agree on the end result, although we would approach that terminal result, deni
Although it is a close call, I would hold that MiGas does have standing. I reach this conclusion in light of the expansive precedent cited by Judge Moore, particularly Associated Gas Distributors v. FERC,
Although MiGas was deemed to have standing to challenge the action of FERC, I am persuaded that FERC committed no error in its disposition of the controversy. Were I called upon to reaсh the merits in this case, I would concur in the result reached by FERC. In my view, however, FERC should have granted MiGas a hearing and an opportunity to present proof. I consider this failure, however, under all the circumstances, to have been harmless error, particularly in light of the factor of risk assessment and economic choice by a, public body ultimately subjеct to voter (and user) control and authority.
Accordingly, although I conclude that Mi-Gas has standing that should have had opportunity for an evidentiary hearing before FERC, I concur in the denial of the petition for review.
. Michigan Public Service commission also has authority to consider such issues involving Mi-Gas and BPW in light of the public interest, convenience, and necessity.