Miami Mds Company v. Federal Communications CommissionMiami Mds Company v. Federal Communications Commission
Opinion for the Court filed by Circuit Judge STEPHEN F. WILLIAMS.
Petitioners held permits issued by the Federal Communications Commission to con *659 struct stations for “multipoint distribution service” or “MDS”, a type of fixed radio facility for common carrier service. 1 Each permit specified its expiration date. After the petitioners secured various extensions (one in the ease of petitioner Miami MDS, three in the ease of petitioner Boston MDS), the Commission’s Common Carrier Bureau ultimately denied extension requests for each petitioner (in March 1988 as to Miami, in April 1988 as to Boston), for want of due diligence. In each case the denial decision ordered the petitioner to return its permit for cancellation. Each petitioner immediately ordered the necessary equipment. On its receipt each filed an application for reconsideration, at the same time undertaking construction in earnest. Each petitioner managed to complete construction within two months of the Bureau’s denial, and filed suitable forms certifying completion. On May 24, 1989, nearly a year after the stations were completed, the Bureau denied the petitioners’ applications for reconsideration; more than three years later, the Commission itself denied their applications for review and imposed monetary forfeitures. 7 F.C.C.R. 4347 (1992).
Petitioners’ principal claim is that their construction permits were extended as a matter of law even after the Bureau’s formal denial of the last extension requests, so that their post-denial construction surges fulfilled the requirements of their permits. Such fulfillment would normally lead to receipt of operating permits. 2 The supposed source of this automatic extension is the third sentence of § 9(b) of the Administrative Procedure Act, 5 U.S.C. § 558(c), which reads as follows:
When the licensee has made timely and sufficient application for a renewal or a new license in accordance with agency rules, a license with reference to an activity of a continuing nature does not expire until the application has been finally determined by the agency.
5 U.S.C. § 558(c). Because the construction permits do not qualify as “license[s] with reference to an activity of a continuing nature”, this sentence of § 558(c) does not apply-
First, we reject a view of § 558(c)’s third sentence, offered by the Commission, that is plainly wrong. Citing language from our decisions in
Atlantic Richfield Co. v. United States,
Section 558(c)’s third sentence limits its application to licenses “with reference to an activity of a continuing nature”. This precondition was expressed slightly differently by Justice Burton, in a dissent, but in a passage with which, as Judge Friendly later noted, the majority did not quarrel:
The policy behind the third sentence of [§ 558(e) ] is that of protecting those per *660 sons who already have regularly issued licenses from the serious hardships occasioned both to them and to the public by expiration of a license before the agency finds time to pass upon its renewal.
Pan-Atlantic Steamship Corp. v. Atlantic Coast Line,
Apart from § 558(c), petitioners invoke this court’s statement in
MG-TV Broadcasting Co. v. F.C.C.,
Petitioners allege that in considering applications for extensions or for reinstatements of expired permits, the Commission routinely takes account of progress in construction made after expiration of the initial permit (or of its extension). Of the five eases cited in support, four do not pan out at all. In two cases the Commission
denied
the requested extension, but referred to an earlier one that had been granted. In
Mt. Baker Broadcasting Co., Inc.,
3 F.C.C.R. 4777 (1988), the
staff
had granted the prior extension in clear reliance on post-expiration work, but the Commission said nothing to endorse that decision. In
GOS Broadcasting Corporation,
1 F.C.C.R. 314 (MMB 1986),
rev. denied,
2 F.C.C.R. 1757 (1987), the Bureau observed of the prior extension that it had been “[bjased on [the permittee’s] representation that [it was]
in the process
of rebuilding [an access] road”,
id.
at 314 (emphasis added). So far as appears the representation referred to operations being conducted at the time the permittee
filed
its application for an extension, within the previously allowed time. In
Hubbard Broadcasting, Inc.,
In the fifth case,
In re John J. Tibiletti,
In fact, more recently the Bureau has refused to allow a permittee to rely on actions taken after a construction permit expired, and indeed asserted that its policy was to disregard progress made after denial of a request for more time. See
Metrovision,
*661
Inc.,
3 F.C.C.R. 598, 602 (MMB 1988), citing
In re Sunrise Broadcasting, Inc.,
We note also that
Tibiletti
and two of the other eases cited by petitioners involved permits under Part 73 before the Commission. stiffened extension criteria under those rules in 1985.
In re Amendment of Section 73.3598 and Associated Rules Concerning the Construction of Broadcast Stations,
Petitioners also challenge the Bureau’s imposition of forfeitures of $2000 on each of the petitioners for engaging in unauthorized construction after expiration of their permits. In this context, they assert that the Commission staff was bn notice of their intention to complete construction, and that the Commission’s failure to object bars any liability for monetary forfeitures.
We do not have jurisdiction to address this argument. Section 504(a) of the Communications Act authorizes the collection of such forfeitures by a civil suit in district court. Monetary forfeitures “shall be recoverable ... in a civil suit in the name of the United States brought in the district where the person or carrier has its principal operating office ... ”, and such a suit “shall be a trial de novo”. 47 U.S.C. § 504(a). We have construed § 504 to confine initial review of forfeiture orders to the district courts.
Pleasant Broadcasting Co. v. FCC,
Accordingly, the petitions are Denied.
Notes
. Commission regulations define MDS specifically as a "one-way domestic public radio service rendered on microwave frequencies from a fixed station transmitting (usually in an omnidirectional pattern) to multiple receiving facilities located at fixed points”. See 47 CFR § 21.2.
. After issuance of the original construction permits, the Commission changed to a system of a single conditional permit that covers both construction and operation, but which lapses if construction is not completed within the specified deadline. Revision of Part 21 of the Commission’s Rules, Report and Order, 2 F.C.C.R. 5713, 5717-18 (1987). This structural change is not claimed by either party to affect the issues before us.