MFA, Inс. appeals from a summary judgment entered in the Circuit Court of Callaway County in favor of HLW Builders, Inc. in an action filed by MFA to compel arbitration or, in the alternative, for breach of contract. For the following reasons, the judgment is affirmed.
On Dеcember 9, 1998, MFA entered into a contact with HLW for the construction of an agriculture chemical/fertilizer facility in Callaway County. HLW was chosen as the contractor by MFA’s project coordinator, John Seiler. In order to solicit bids for the project, Seiler had created and provided contractors with drawings of the proposed facility along with certain specifications. Those drawings and specifications were incorporated by reference in thе construction contract. HLW completed the construction in March 2000.
On October 25, 2002, Bradley Hamilton went to the facility to repair an elevated conveyor system on behalf of a repair contractor hired by MFA. The repairs rеquired Hamilton to utilize the catwalk located next to the conveyor. While working on the conveyor, Hamilton had a seizure, fell to the ground, and died as a result of the injuries he sustained. OSHA investigated the incident and cited MFA with exposing employеes to a twenty-four foot fall hazard because the catwalk did not have a guardrail or other fall protection system on the side closest to the conveyor belt.
On May 10, 2004, Hamilton’s widow filed a wrongful death action against MFA in *623 the Circuit Court of Jackson County. On November 10, 2004, MFA filed a third-party petition against HLW. In its answer to MFA’s third-party petition, HLW asserted that the dispute should be resolved through arbitration as provided by the arbitration clause contained in the construction contract. On Jаnuary 7, 2005, HLW wrote MFA and requested that the claims be submitted to binding arbitration as provided in the construction contract.
On August 24, 2005, Hamilton’s widow filed her First Amended Petition, adding HLW as a defendant. On May 10, 2006, the circuit court granted HLW’s motion for summary judgment on the claims brought by Hamilton’s widow based upon the acceptance doctrine. On June 6, 2006, MFA dismissed its third-party petition and demanded for the first time that the dispute between the two companies be arbitrated. HLW refused to arbitrate at that point, contending that the findings аnd conclusions of the summary judgment resolved the dispute between the two companies. On January 23, 2007, following mediation, MFA entered into a settlement agreement with Hamilton’s widow for $1.2 million.
On February 28, 2007, MFA filed the current action in the Circuit Court of Cal-laway Cоunty asserting that HLW had breached the construction contract by refusing to arbitrate its claim that HLW should indemnify it for the $1.2 million paid to Hamilton’s widow. In the alternative, MFA brought a breach of contract claim against HLW for failing to construct the facility in сompliance with OSHA standards and claimed that breach resulted in Hamilton’s death and the subsequent settlement of the wrongful death action.
HLW filed a motion for summary judgment on July 26, 2007. On September 4, 2007, MFA filed a motion for partial summary judgment and motion to compel arbitration.
Following a hearing, the trial court denied the motion to compel arbitration, finding that the arbitration clause in the contract was not mandatory. In addition, the court found that MFA had waived any right it had to arbitrate. The trial court аlso granted HLW’s motion for summary judgment and denied MFA’s motion for partial summary judgment. MFA brings three points on appeal.
In its first point, MFA claims the trial court erred in denying its motion to compel arbitration because the arbitration clause was mandatоry rather than permissive. MFA also argues that the trial court erred in finding that it waived its right to arbitration.
“In determining whether parties are bound by an agreement to arbitrate, the court must determine whether a valid arbitration agreement exists and, if so, whether the specific dispute falls within the scope of the arbitration agreement.”
Kritzer v. Curators of Univ. of Mo.,
Article 15 of the General Conditions of the contract, adopted by reference in the Construction Agreement, providеs:
To prevent suits and litigations, it is agreed by the parties hereto that should any disputes arise under this Contract that cannot be otherwise peacefully agreed upon, the same may be submitted to arbitration upon the written request of either party hereto. If arbitration is chosen, the Owner and the Contractor shall each choose one *624 arbitrator, and they in turn shall choose a third member. Their decision shall be final, and either the Owner or Contractor shall comply.
The triаl court concluded that the “may be submitted to arbitration” language rendered Article 15 permissive rather than mandatory.
Contrary to the trial court’s conclusion, “[t]he overwhelming authority from state and federal courts throughout the nation supports the conclusion that the use of operative language such as “may elect” does give rise to mandatory arbitration.”
Discover RE Managers, Inc. v. Preferred Employers Group, Inc.,
No. 3:05CV809,
Under the arbitration language contained in the construction contract at issue here, while not all disputes must be resolved through arbitration, once any of the parties to the contract invokes the right to arbitration by written request, arbitration is mandatory unless subsequently waived by that party. Thus, we must ascertain whether, as MFA claims, the trial court improperly found that MFA had waived its right to arbitration.
“A party may waive a valid arbitration agreement.”
Major Cadillac, Inc. v. General Motors Corp.,
MFA concedes that it had knowledge of its right tо arbitrate under the contract. However, it contends that it did not act in a manner inconsistent with that right and, furthermore, that HLW was not prejudiced by its actions.
The trial court found that, even if the language were mandatory, MFA had waived any right to arbitratiоn in the matter by filing its third-party petition against HLW without requesting arbitration and by not dismissing its claim against HLW even after HLW initially requested arbitration, thereby requiring HLW to defend the lawsuit for months. The court noted that MFA did not attempt to pursue arbitration until after HLW had prevаiled in its motion for summary judgment against the plaintiff in that lawsuit and findings adverse to MFA were made in that judgment.
MFA undoubtedly acted inconsistently with its right to arbitrate by filing its third party action against HLW in Cal-laway County Circuit Court, waiting nineteen months to dismiss its action, and not notifying HLW of its intent to рursue arbitration until after HLW had prevailed in its summary judgment motion against Hamilton’s widow.
See Getz Recycling, Inc. v. Watts,
Accordingly, we turn to whether prejudice was established. “Prejudice is determined on a case-by-case basis.”
Major Cadillac, Inc.,
MFA filed suit in the circuit court seeking judicial resolution of its claim against HLW on October 22, 2004. MFA first made its demand for arbitration on June 6, 2006. Thus, MFA waited nineteen months before asserting its contrаctual right to arbitrate, and during that time, MFA pursued a legal remedy in the circuit court. HLW was forced to incur litigation expenses defending against MFA’s third party action and to participate in discovery related thereto. Prejudice was sufficiently established.
See Reis v. Peabody Coal Co.,
The trial court did not err in concluding that MFA had waived its contractual right to pursue arbitration. Point denied.
In its sеcond point, MFA claims that the trial court erred in granting summary judgment to HLW with regard to
*626
MFA’s claim for specific performance of the arbitration clause because a genuine dispute existed as to the material facts related to whether MFA waived its right to arbitrate. Neither MFA’s point relied on nor its argument identify the facts it claims are in dispute. Indeed, MFA’s argument in Point I, which MFA incorporates by reference in its argument on Point II, asserts that the facts relevant to waiver are undisputed. This claim of error has not been sufficiently developed for appellate review and is, therefore, deemed to have been waived.
Chipperfield, v. Missouri Air Conservation Comm’n,
In its final point, MFA argues that the trial court erred in granting summary judgment in favor of HLW on MFA’s breach of contrаct claim because the trial court misapplied the law in concluding that the acceptance doctrine was applicable under the facts of this case. MFA further contends that genuine disputes existed as to the material facts relevant to the application of the acceptance doctrine.
The trial court’s judgment, however, expressed alternative grounds for granting summary judgment. In addition to concluding that summary judgment was appropriate bаsed upon the acceptance doctrine, the trial court found, based on the uncontroverted facts, “HLW did not breach the construction contract with MFA.” HLW has not challenged this alternative basis for summary judgment on appeal. Whеre the trial court’s ruling in entering summary judgment can be sustained under any theory, it must be affirmed.
Rocha v. Metropolitan Prop. & Cas. Ins. Co.,
The judgment is affirmed.
All concur.
Notes
. Citing
Allis-Chalmers Corp. v. Lueck,
