Opinion
In а so-called class action plaintiffs seek to have the court declare that the “pre-payment penаlties” required of persons seeking to pay loans in advance of the normal maturity dates in real estate loan сontracts used by defendants are void as being in contravention of Civil Code section 1670.
1
The claims against eight federally chartered defendants were removed to the United States District Court pursuant to 28 United States Code section 1441(b). The balanсe of those, chartered under state law, demurred upon the ground that no cause of action was stated.
*546
Certain of these defendants also raised the question of proper parties plaintiff and defendant but for reasons to be stаted herein we need not consider this ground or the effect of the lack of unanimity of defendants’ claims in this respect. On April 12, 1972, all demurrers were sustained and plaintiffs given 10 days to amend. Upon failure of plaintiffs to amend a motion to dismiss pursuant to Code of Civil Procedure section 581 subdivision 3 was granted and an order of dismissal filed. Plaintiffs appeal from the order of dismissal. The order constitutes a judgment and is appealable. (Code Civ. Proc., §§ 581d, 904.1, subd. (a);
Morales
v.
Camello,
It is contended on appeal the “prе-payment penalty” provisions contained in all real estate loan contracts employed by defendants constitute liquidated damages in violation of California Civil Code section 1670 and are therefore void and since the cоmplaint so alleged it was error to sustain the demurrers for failure to state a cause of action. We do not agrеe.
The typical “pre-payment penalty” clause is alleged to be as follows: “The holder of said promissory note agrees to accept additional payments provided, however, that in any calendar quarter in which payments made thereon exceed twenty (20%) percent of the original amount of said promissory note the holder will require the additional payment of an amount equal to 180'days interest on such original amount at the rate of interest set forth hereinabove.” The clear import of this provision is to give the borrower an option to either pay the note in thе manner contemplated by the contract or to prepay the balance due upon condition that a surcharge be added for the privilege of exercising the option. The clause does not penalize for the “breаch of an obligation” as contemplated by section 1670. No breach is involved in the prepayment transaction, оnly the exercise of the option given to the debtor for an alternative method of paying the debt. The bulk of plaintiff’s аrguments regarding the social and economic undesirable aspects of a loan transaction involving such a prеpayment clause is more appropriately addressed to the Legislature than the courts and is not persuasivе or controlling of our decision herein.
In
Lazzareschi Inv. Co.
v.
San Francisco Fed. Sav. & Loan Assn.,
“In the instant case, the only reasonable interрretation of the clause providing for imposition of an increased interest rate is that the parties agreed uрon the rate which should govern the contract and then, realizing that the borrowers might fail to make timely payment, they further agreed that such borrowers were to pay an additional sum as damages for their breach which sum was determined by apрlying the increased rate to the entire unpaid principal balance. Inasmuch as this increased interest chargе is assessed only upon default, it is invalid unless it meets the requirements of section 1671. (§§ 1670, 1671; see also
In re Tastyeast, Inc.
(3rd Cir. 1942)
In view of our decision on the quеstion presented by the general demurrers filed by each of the defendants, it becomes unnecessary for us to *548 consider the question of proper parties plaintiff or defendant presented by . only a portion of the demurrers.
The judgment (order of dismissal) is affirmed.
Ford, P. J., and Loring, J., * concurred.
Appеllants’ petition for a hearing by the Supreme Court was denied June 26, 1974. Mosk, J., was of the opinion that the petition should be grantеd.
Notes
Civil Code section. 1670 provides: “Every contract by which the amount of damage to be paid, or other compensation to be made, for a breach of an obligation, is determined in anticipation thereof, is to that extent void, except as expressly provided in the next section.”
Assigned by the Chairman of the Judicial Council.
