Thе controversy before us centers around the following provision contained in a contract of sale for improved realty: “Heating plant to be functioning properly — Entire Unit.” The contract was signed in March 1964 and the deed delivered in June of that year. In November appellees (purchasers) first noticed that the boiler leaked. They subsequently sued appellants for breach of wаrranty and recovered $780, the cost of purchasing and installing a gas heating system on the premises.
In order to render any judgment for ap-pellees, the trial court had to find that there was a warranty; thаt it survived delivery of the deed; that there was a breach which was not waived; and that notice of the breach was given within a reasonable time. It then had to determine the proper measure оf damages. For convenience, we shall deal with the elements of the case in the same order.
Appellants do not argue that the contractual language did not create a warranty. They do contend, however, that all warranties merged into the deed and that a suit on the contract was therefore improper. Their argument is untenable for two reasons. The face of thе contract contained the following:
“(16) The principals to this contract mutually agree * * * that the provisions hereof shall survive the execution and delivery of the deed aforesaid and shall nоt be merged therein; * * * »
In addition, it is settled in this jurisdiction that covenants which are independent of the conveyance of title survive delivery of a deed. Libby v. Trako Builders,
*58 Turning to the questions of breach and waiver, there is no dispute that when ap-pellees first turned on the heating system in November 1964 they discovered the boiler was leaking. Appellаnts argue that ap-pellees had both the duty and the opportunity to inspect the premises long before that date, and that by failing to do so they waived any possible breach.
The testimony adduсed at trial shows that no inspection of the heating system was made until November although appellees had been given keys to the premises in March. The record also indicates, however, thаt appellants, who are in the real estate business, had purchased the property two months prior to its sale to appellees; that there was freeze damage to certain рipes and radiators; that they never ascertained whether the heating system was functioning properly; and that the premises were vacant when sold.
The warranty in question stated that the heating plаnt was to be functioning properly. Appellants argue, however, that the risk of loss or damage to the system was on the purchasers after the contract was signed, and that the trial court had to find that a breach had occurred prior to March 1964. Assuming, arguendo, that this is a correct statement of the law, we hold that there was sufficient evidence from which the trial court could have found that the system was nоt in good working order when the contract was signed.
On the issue of waiver, the law is clear that a buyer may lose his cause of action for breach of warranty if he fails to notify the seller of the breаch within a reasonable time. Campbell Music Co. v. Singer, D.C.Mun.App.,
Appellants’ final argument is that the trial court erred because it applied the wrong measure of damages. We agree.
The record shows that the heating plant in question was of the coal-converted-to-oil type, and consisted of a boiler, a motor unit and a thermostat. Thе boiler was estimated to be between twenty-five and forty years old. Subsequent to the breach, ap-pellees installed a new gas heating plant (including thermostat) which had a greater heating cаpacity than the oil system. The total cost was $780, the amount of the judgment herein.
The general rule of damages for a breach of warranty has been variously stated. In Fries, Beall & Sharp Co. v. Livingstone,
In the case at bar, the only testimony concerning the boiler was that it had no monetary valuе. The contract of sale was not apportioned; consequently there was no way to determine what part of the purchase price was applicable to the heating system. There was no showing that anything other than the boiler was faulty. Testimony further showed that used boilers could be obtained from junk yards or plumbers, and that certain of these sources sold them only after they had beеn tested. Under all the circumstances of this case, we hold that the proper measure of damages was that amount required to make the goods conform to the warranty,
i. e.,
the cost of purсhasing and installing a properly functioning used boiler. Whether or not anyone would recommend the installation of such a boiler is immaterial. Appellees were free to substitute a gas system (which they did), change over to forced air heating, or even experiment with a solar heating plant. They could not, however, recover the cost of such systems. They contracted for a used oil system thаt would function properly, and can neither receive more than they bargained for nor be put in a better position than they would have been had the contract been fully performed. Thornе v. White, D.C.Mun.App.,
In Clarke v. Cleckley, D.C.Mun.App.,
In Thorne v. White, supra, we held that where a contract for a four-ply roof had been breachеd, the innocent party could not then make a contract for a five-ply roof and collect the difference in cost as damages. In Fries, Beall & Sharp, supra, damages were disallowed where plaintiff, in rеplacing a leaky roof, did not use material of substantially the same style, grade and character as that for which he had originally contracted. In Morfessis v. Sterling Metalware Co., supra, it was shown thаt certain dented stainless steel parts of a display unit could have been replaced. Plaintiff was not allowed to collect for the cost of remodeling the unit with formica paneling. In the instant case, appellees bargained for a used oil heating system. Although they could replace it with a new and larger gas system, they could not collect the full purchase price and installation cost.
To reiterate, since the boiler was the only defective part of the system and could be replaced, appellees’ damages are limited to the cost of purchаsing and installing a used boiler. Appellants’ evidence showed that used boilers cost between ten and $100, and that the cost of installation was between $200 and $250. We therefore find that the maximum appellees could have recovered was $350.
*60
As discussed above, the decision of the trial court requires affirmance on all issues other than damages. It will therefore be affirmed provided appеllees, within ten days hereof, file with the trial court a remittitur in the sum of $430; otherwise the said judgment shall be reversed and remanded for further proceedings not inconsistent with the opinion of this court. Such reductions may be made when the computation is reasonably clear from the record. Lalley v. Escoett,
Affirmed on condition.
