Lead Opinion
OPINION OF THE COURT
This case requires us to decide the pre-clusive effect of a state utility agency’s ruling, which has been affirmed by Pennsylvania’s Commonwealth Court and denied review by the Pennsylvania Supreme Court and the United States Supreme Court. Although the Appellants, electric utility companies Metropolitan Edison Co. (“Mei>-Ed”) and Pennsylvania Electric Co. (“Penelec”) (collectively, the “Companies”), also, in effect, invite us to review the agency’s ruling on the merits, we need not and do not take that step.
The Companies’ end-game appears to be to recoup from their customers more than $250 million in costs associated with “line losses”—ie., energy that is lost when electricity travels over power lines—and interest related to those costs. For reasons we will explain, the Companies’ line loss costs had increased pursuant to a mandate by the Federal Energy Regulatory Commission (“FERC”), and the Companies’ ability to recover those costs depended on whether line-loss costs were classified as a cost of electricity generation or as a cost of electricity transmission on their customers’ utility bills. In a prior proceeding, the Pennsylvania Public Utility Commission (“PUC”) rejected the Companies’ proposal to classify line-loss costs as a cost of transmission, thereby preventing the Companies from passing those costs through to their customers. The Companies then pressed their arguments and lost in the Pennsylvania state courts and were denied review by the United States Supreme Court.
The Companies now seek declaratory judgment and injunctive relief in federal court against the PUC and its Commis
I. BACKGROUND
To understand the issues raised in this appeal, it is helpful to first look at the legislative and administrative framework of electricity regulation and how that framework affects the parties before us.
A. The Federal Power Act and the Filed Rate Doctrine
In 1935, Congress enacted the Federal Power Act (“FPA”), 16 U.S.C. § 791a et seq., which authorized “federal regulation of the expanding business of transmitting and selling electric power in interstate commerce.” New York v. FERC,
The so-called “filed rate doctrine” is an application of the FPA’s statutory grant of authority to FERC. See Borough of Ellwood City v. FERC,
Before the passage of the FPA, electricity was usually sold by vertically integrated electric utilities that controlled their own generators, transmission lines, and local distribution networks.
Advances in technology since the enactment of the FPA have resulted in “[transmission grids [that] are now largely interconnected, which means that ‘any electricity that enters the grid immediately becomes a part of a vast pool of energy that is constantly moving in interstate commerce.’ ” N.J. Bd. of Pub. Utils. v. FERC,
In 1996, FERC issued Order No. 888, a landmark ruling aimed at encouraging competition and lowering electricity rates. See Promoting Wholesale Competition Through Open Access Non-Diseriminatory Transmission Services by Public Utilities, 61 Fed.Reg. 21,540, 21,541 (May 10, 1996) [hereinafter Order No. 888], ajfd in relevant part, Transmission Access Policy Study Grp. v. FERC,
That same year, Pennsylvania enacted the Electricity Generation Customer Choice and Competition Act (the “Electric
As a result of introducing competition into the market for electricity generation services, the Electric Competition Act left electric utilities with “transition,” or “stranded,” costs, which are defined as “known and measurable” generation-related costs that “traditionally would be recoverable under a regulated environment but which may not be recoverable in a competitive electric generation market and which the [PUC] determines will remain following mitigation by the electric utility.”
To ease transition to a competitive market, the Electric Competition Act required electric utilities in the Commonwealth to submit “restructuring plans,” including proposed rate schedules and plans for the recovery of stranded costs, for approval by the PUC. 66 Pa. Cons.Stat. § 2806(d)-®. The Act outlined some restructuring standards, such as “caps” on service rates for certain periods of time in exchange for electric utilities being able to recover their stranded costs. Id. § 2804(4). The rate caps allowed customers to obtain electricity at the capped rates, which put downward pressure on any market rate above that level. Cf. ARIPPA,
C. The Companies’ Settlement Agreement
The Companies provide electricity and associated services to customers in their prescribed territories within Pennsylvania. Pursuant to passage of the Electric Competition Act, they filed restructuring plans with the PUC in 1997. In 1998, they jointly and voluntarily entered into an omnibus settlement agreement (the “Settlement Agreement”) that resolved disputes related to their restructuring plans and to pending litigation in the United States District Court for the Eastern District of Pennsylvania. Of importance in the present matter, the Companies agreed to caps on “Transmission and Distribution (T & D) Charges” through December 31, 2004, as well as caps on “Generation rates” through December 31, 2010. (J.A. at 115.) Compared to the standard time-frames for rate caps under the Electric Competition Act, the periods for those agreed-upon rate caps represented extensions of three-and-a-half years on the transmission rate cap and five years on the generation rate cap. 66 Pa. Cons.Stat. Ann. § 2804(4)(i), (ii). In exchange for accepting those extensions, the Companies were given additional time to recover certain stranded costs from their customers. The PUC entered a final order approving the Settlement Agreement in October 1998.
D. The Companies’ Line-Loss Costs
The Companies’ distribution facilities are connected to an interstate transmission grid that is overseen by PJM Interconnection, LLC (“PJM”). PJM is a regional transmission organization, a voluntary association “to which transmission providers ... transfer operational control of their facilities for the purpose of efficient coordination” of the wholesale electricity market. Morgan Stanley Capital Grp. Inc. v. Pub. Util. Dist. No. 1.,
Until June 30, 2007, PJM calculated and billed for line losses using what is called the “average loss” methodology. See Atl. City Elec. Co. v. PJM Interconnection, LLC (Atlantic City I),
On March 2, 2006, several electric utilities (but not the Companies) filed a complaint with FERC alleging that, under an agreement appended to PJM’s Tariff, PJM was required to switch from the average loss methodology to a “marginal loss” methodology to calculate the cost of line losses. Id. at 61,473. “Under the marginal loss method, the effect of losses on the marginal cost of delivering energy is factored into the energy price ... at each location.” Id. at 61,474. Thus, “[o]ther things being equal, customers near generation centers pay prices that reflect smaller marginal loss costs while customers far from generation centers pay prices that reflect higher marginal loss costs.” Id.; see also Sacramento Mun. Util. Dist. v. FERC,
In an order issued in 2006, FERC held that the agreement appended to PJM’s Tariff required PJM to use the marginal loss methodology once it was technologically feasible to do so and that PJM had conceded that it possessed the necessary technology. Id. at 61,477. FERC also noted that using marginal loss pricing would result in cost savings to PJM and efficiencies in resource allocation. Id. at 61,474, 61,477-78. Accordingly, FERC required PJM to switch from using the average loss methodology to the marginal loss methodology of calculating line losses. Id. at 61,478. The Companies did not participate in the comments process before
A few months later, FERC denied rehearing requests but granted a request to delay implementation of the marginal loss methodology to June 2007. Atl. City Elec. Co. v. PJM Interconnection, LLC (Atlantic City II),
II. PROCEDURAL HISTORY
Not surprisingly, the Companies eventually sought to recover their increased line-loss costs by asking the PUC to allow them to pass the expense through to their customers. A “transmission rider,” which was approved by the PUC in 2006 after the Companies’ transmission rate cap had lapsed, allowed the Companies to pass through various proposed transmission costs to their customers and to engage in an annual updating and reconciliation process in order to recover projected transmission costs and adjust for the over-or under-collection of past transmission costs. Pa. Pub. Util. Comm’n v. Metro. Edison Co., Nos. R-00061366C0001 et al.,
A. The PUC Order
Pennsylvania’s Office of Consumer Advocate and Office of Small Business Advocate
The ALJ recommended dismissing the Customer Groups’ complaints and approving the Companies’ requests to recover line-loss costs as a transmission cost. In re Pa. Elec. Co. Transmission Serv. Charge, Nos. M-2008-2036188 et al., 2009 Pa. PUC LEXIS 2328 (July 24, 2009).
The Customer Groups argued to the PUC that line-loss costs should not be billed to them as transmission costs because (1) line losses have historically been recognized as part of the cost of electricity generation; (2) how PJM bills the Companies for line losses is irrelevant to whether those losses should be billed to the Companies’ customers as a generation or transmission cost; and (3) the Companies themselves have historically treated line-loss costs as generation costs. The Companies responded by (1) emphasizing how line losses are related to transmission, ie., as electricity is transmitted over longer distances, line losses increase; (2) pointing to the FERC-approved definition of “transmission losses” in PJM’s Tariff;
The PUC in a split decision entered March 3, 2010 (the “PUC Order”) ultimately rejected all of the Companies’ arguments and agreed with the Customer Groups. The PUC did not adopt the ALJ’s recommendation that line losses be considered a transmission cost, concluding instead that the Companies’ line losses were generation costs subject to the Settlement Agreement’s generation rate cap that was in effect through 2010. As the merits of the PUC Order are not before us, suffice it to say that the PUC thoroughly reviewed all of the Companies and the Customer Groups’ arguments. By a three-to-two vote of the Commissioners, the agency required the Companies to file tariff supplements consistent with the majority’s decision.
B. Review of the PUC Order
The Companies petitioned the Pennsylvania Commonwealth Court for review of the PUC Order to the extent it denied their request to classify line-loss costs as a transmission cost.
Important for purposes of this appeal, the Commonwealth Court addressed the Companies’ argument that classifying line-loss costs as a generation cost for purposes of retail billing “violates the Filed Rate Doctrine and is inconsistent with ... FERC’s characterization of line losses.” (J.A. at 183.) The Companies had cited FERC decisions that allegedly treated line losses as a cost of transmission, but the Commonwealth Court held that those decisions “do not unambiguously state that such costs are transmission-related.” (J.A. at 188.) As the court saw it, several of those FERC decisions included language tying line losses to the costs of generating electricity. The court thus concluded that FERC’s decisions did not create any “direct conflict” with the classification of the Companies’ line-loss costs as generation costs. (J.A. at 189.)
Furthermore, the Commonwealth Court held that, for two reasons, there was no impermissible “trapping” of the Companies’ costs. Cost trapping, in this context, refers to a state “bar[ring] regulated utilities from passing through to retail consumers FERC-mandated wholesale rates.” Miss. Power & Light,
The Pennsylvania Supreme Court subsequently denied the Companies’ petition for allowance of appeal, and the United States Supreme Court denied the Companies’ petition for a writ of certiorari. The Commonwealth Court’s decision (the “State Decision”) affirming the classification of line-loss costs for retail billing purposes thus became final.
C. The Federal Action
On July 13, 2011, while their petition for review before the Pennsylvania Supreme Court was pending, the Companies filed the present action in the District Court, naming as defendants the PUC and PUC Commissioners Robert F. Powelson, John F. Coleman, Jr., Pamela A. Witmer, Wayne E. Gardner,
The gravamen of the Companies’ amended complaint is that the outcome of the state proceeding resulted in unlawful trapping of the line-loss costs that PJM charged them pursuant to FERC-ap-proved tariffs. The Companies ultimately seek to recover the line-loss costs they incurred between 2007 and 2010.
Count I of the Companies’ amended complaint asserts that the alleged cost-trapping violates the FPA and the filed rate doctrine. Count II alleges that the PUC Order “imposes a confiscatory rate on the Companies” by depriving them of a property interest in recovering line-loss costs and, thus, violates the Due Process Clause of the Fourteenth Amendment and, by extension, the FPA’s requirement that rates be just and reasonable. (J.A. at 50.) Count III claims that the Electric Competition Act is unconstitutional as applied because it is pre-empted by federal law. In sum, the Companies allege that, by barring them from recovering the line-loss costs that PJM charged them under a FERC-mandated methodology, the PUC Order violates the filed rate doctrine, the Supremacy Clause of the Constitution, the Fourteenth Amendment, and the FPA, and, to the extent the PUC and the Commonwealth Court relied on the Electric Competition Act, that statute, as applied, is pre-empted by federal law.
The PUC Defendants moved to dismiss the amended complaint,
After hearing oral argument on the renewed motion to dismiss, the District Court dismissed all of the Companies’ claims on the basis of issue preclusion. The Companies then timely filed this appeal.
At the outset, it is worth emphasizing what is and is not at issue here. The question before us is whether the State Decision—ie., the Commonwealth Court’s decision that the PUC’s classification of line-loss costs did not violate the filed rate doctrine or impermissibly trap costs—bars litigation of the claims in this federal action. It is not whether the PUC correctly classified the Companies’ line-loss costs as generation costs in the first instance.
The Companies offer several arguments for denying the State Decision any preclu-sive effect, based on what they call exceptions to the application of the Full Faith and Credit Statute, 28 U.S.C. § 1738. (Appellants’ Opening Br. at 29-44.) They also argue that the District Court misinterpreted the reach of the State Decision to preclude all of their claims. The PUC Defendants respond that the principles of issue preclusion properly bar the present case and, in the alternative, that dismissal would be proper under claim preclusion, abstention principles, and judicial estoppel.
A. Issue Preclusion
The District Court viewed the State Decision as having preclusive effect because the Commonwealth Court addressed the Companies’ arguments that the PUC Order violated the filed rate doctrine and impermissibly trapped costs. Under the doctrine of issue preclusion, also referred to as collateral estoppel, “once a court has decided an issue of fact or law necessary to its judgment, that decision may preclude relitigation of the issue in a suit on a different cause of action involving a party to the first case.” Allen v. McCurry,
Here, there is no dispute that Pennsylvania’s preclusion law applies. The Pennsylvania Supreme Court has established a five-prong test providing that issue preclusion will apply when:
(1) the issue decided in the prior case is identical to the one presented in the later action;
(2) there was a final adjudication on the merits;
(3) the party against whom the plea is asserted was a party or in privity with a party in the prior case; (4) the party ... against whom the doctrine is asserted had a full and fair opportunity to litigate the issue in the prior proceeding; and (5) the determination in the prior proceeding was essential to the judgment! [20 ]
Office of Disciplinary Counsel v. Kiesewetter,
As noted before, Count I of the amended complaint alleges that the PUC Order trapped the Companies’ line losses in violation of the filed rate doctrine and, by extension, in violation of the FPA and the Supremacy Clause of the Constitution. The Companies do not appear to dispute that Count I meets all five of the requirements for issue preclusion under Pennsylvania law. That is wise, since (1) the Commonwealth Court squarely decided that the PUC Order did not violate the filed rate doctrine or impermissibly trap costs; (2) the court’s decision was on the merits and final after both the Pennsylvania Supreme Court and the United States Supreme Court denied petitions to review the State Decision;
According to the Companies, however, their claims in Counts II and III—which allege a confiscatory taking and federal pre-emption of the Electric Competition Act, respectively—do not meet the five-prong issue preclusion test under Pennsyl
1. Waiver
“[Fjailure to raise an issue in the district court constitutes a waiver of the argument.” Gass v. V.I. Tel. Gorp.,
The Companies claim that they did not waive their arguments because their “[b]rief ... explained] why Counts II and III were not commingled with Count I.” (Appellants’ Reply Br. at 25.) But that argument is unavailing because the brief that they cite to is the opening brief before us, not anything that they filed in the District Court.
The only colorable argument that the Companies make to rebut waiver is that the PUC and its Commissioners, in their motion to dismiss, “did not argue [in the first place] that Count II was barred by issue preclusion.” (Appellants’ Reply Br. at 25.) In that regard, the Companies are correct. As a consequence, we are not prepared to say that they were required, at the risk of waiver, to argue that issue preclusion does not apply to Count II. We will not consider the Companies’ issue preclusion arguments with respect to Count II waived. The PUC and its Commissioners did, however, argue in the District Court that issue preclusion bars Counts I and III. As the Companies did not attempt to distinguish Count III in the District Court in response to the issue preclusion arguments, they waived at least their arguments as to that count.
In any event, as the PUC Defendants argue, Counts II and III of the Companies’ amended complaint are both barred by issue preclusion, absent any exceptions that would preserve them. Count II alleges that the PUC Order “imposes a confiscatory rate on the Companies in violation of the Constitution because it deprives the Companies of their property right to recover their federally-approved costs of providing electric service, which includes marginal transmission line loss charges, to their Pennsylvania customers.” (J.A. at 50.) Count II further alleges that the PUC Order is confiscatory because it violates the FPA’s requirement for rates to be just and reasonable. In other words, Count II is premised on the success of the argument that the PUC Order violated the filed rate doctrine and, thus, impermissibly “trapped” the Companies’ line-loss costs— the same argument that the Companies raise in Count I and that is precluded by the State Decision, absent an applicable exception. Without a legal determination that their costs were impermissibly “trapped,” the Companies have no basis for asserting an unconstitutional deprivation of any property interest. Because Count II depends entirely on the same issues that were already litigated to finality in the state proceeding, it is foreclosed by issue preclusion.
A similar fate would befall Count III, even if the Companies’ arguments regarding that count were not waived. Count III relates to the constitutionality of the Electric Competition Act as applied to the Companies, to the extent the PUC Order “disregarded] FERC orders or ... interpreted] FERC tariffs” in violation of the filed rate doctrine. (J.A. at 51.) Although the constitutional challenge to the Electric Competition Act was not raised until the PUC made its decision, it depends, like Count II, on the Companies being able to establish that the PUC Order violated the filed rate doctrine. Again, the State Decision expressly held that there was no violation of the filed rate doctrine, so Count III would also be precluded, absent any exception.
B. Exceptions to the Full Faith and Credit Statute
Although issue preclusion would typically foreclose their claims, the Companies argue that three exceptions to the Full Faith and Credit Statute apply to render the State Decision devoid of any preclusive effect: (1) the state proceeding was legislative rather than judicial in nature; (2) the Companies had a substantially higher burden of persuasion in the Commonwealth Court than they do in this federal action; and (3), under the filed rate doctrine, the PUC and the Commonwealth Court infringed on FERC’s exclusive jurisdiction. [Appellants’ Opening Br. at 24-26.] We are not persuaded that any of those exceptions apply to foreclose the application of issue preclusion in this ease.
1. Whether the state proceeding was legislative or judicial in nature
The Full Faith and Credit Statute, by its terms, applies only to “judicial proceedings.” 28 U.S.C. § 1738. The Companies
The parties do not dispute that the Supreme Court has counseled federal courts to defer to each state’s characterization of its own proceedings. See Okla. Packing Co. v. Okla. Gas & Elec. Co.,
[a] judicial inquiry investigates, declares and enforces liabilities as they stand on present or past facts and under laws supposed already to exist. That is its purpose and end. Legislation on the other hand looks to the future and changes existing conditions by making a new rule to be applied thereafter to all or some part of those subject to its power.
Id. at 370-71,
The Companies argue that Pennsylvania has not clearly decided whether the Commonwealth Court’s review of a PUC order is legislative or judicial, while the PUC Defendants counter that the Pennsylvania Administrative Law and Procedure Act and the Pennsylvania Judicial Code unequivocally call appellate review of PUC proceedings “judicial.” (PUC Defendants’ Br. at 44.) The District Court concluded that the Commonwealth Court’s review of the PUC Order was judicial in nature because the Commonwealth Court’s authority to review PUC orders under 2 Pa. Cons.Stat. § 704 “is limited to determining whether a constitutional violation, an error of law, or a violation of PUC procedure has occurred and whether necessary findings of fact are supported by substantial evidence.”
The Companies contend that the District Court’s reasoning was erroneous because “[i]t cannot be true that [the] commonplace standard of agency review—one that applies to both ratemaking and non-ratemak-ing agencies alike—makes the Commonwealth Court’s decision here judicial.” (Appellants’ Opening Br. at 51.) In other words, they argue that the scope of the Commonwealth Court’s review, alone, cannot determine whether such review is judicial or legislative in nature. That argument fails, however, because the scope of agency review is not the sole basis for concluding that the State Decision was judicial rather than legislative. Other aspects of the state proceeding also indicate that it was judicial in nature.
The Companies rely on two Pennsylvania cases from the 1950s to argue that Pennsylvania courts consider their review of a state agency’s rate-making to be legislative in nature. The two are a 1954 Pennsylvania Superior Court case, Duquesne Light Co. v. Pennsylvania Public Utility Commission, which includes the comment that “[r]ate making is an exercise of the legislative power, delegated to the Commission,”
We recognized in Kentucky West Virginia Gas Co. v. Pennsylvania Public Utility Commission,
A straightforward application of the distinction between judicial and legislative inquiry outlined in NOPSI confirms that the Commonwealth Court decision at issue here is judicial in nature. As the District Court held, “the Commonwealth Court of Pennsylvania did not conduct an independent, forward-looking ... investigation.” (J.A. at 30.) Instead, the Commonwealth Court, like the PUC, referred to and endeavored to enforce (whether correctly or not is immaterial at this juncture) the preexisting Settlement Agreement. The Commonwealth Court further made a determination specific to the Companies. It determined that there was no violation of the filed rate doctrine with respect to how the PUC required the Companies to classify their line losses, which involved a review of the record regarding how the Companies, specifically, had treated line losses in the past. At bottom, both the PUC and the Commonwealth Court adjudicated the adversarial dispute between the Customer Groups and the Companies after considering those parties’ respective legal arguments. We have no difficulty holding that the state proceeding was judicial, not legislative. The nature of the state proceeding therefore does not bar the application of issue preclusion in this case.
2. Whether the Companies’ burdens before the Commonwealth Court and in the instant case are different
The Companies also argue that the so-called “difference-in-burden exception” bars giving the State Decision any preclusive effect. (Appellants’ Opening Br. at 44.) They rely on Section 28(4) of the Restatement (Second) of Judgments, which states that preclusion does not apply when
[t]he party against whom preclusion is sought had a significantly heavier burden of persuasion with respect to the issue in the initial action than in the subsequent action; the burden has shifted to his adversary; or the adversary has a significantly heavier burden than he had in the first action.
Restatement (Second) of Judgments § 28(4) (1982). The Companies do not argue that the burden of proof ever shifted to their adversaries. (See Oral Argument Transcript (“Tr.”) at 29:11-12 (“We have the burden—either way we have the burden.”).) Rather, they argue that, in reviewing the PUC Order, the Commonwealth Court applied the wrong standard of review and placed a substantially more onerous burden of persuasion on them than the Companies would face in this action. The PUC Defendants respond by arguing that “the use of the [difference-in-burden] exception is not ‘well-established’ in relevant ease law,” and that, in any event, the Companies confuse the concept of a party’s burden of proof with a court’s standard of review. (PUC Defendants’ Br. at 42.)
According to the Companies, Section 28(4) of the Restatement is well-established because it provides the basis for the axiomatic rule that, “ ‘even when the parties are the same, an acquittal in a criminal proceeding is not conclusive in a subsequent civil action arising out of the same event.’ ” (Appellants’ Opening Br. at 44 (quoting Restatement (Second) of Judgments § 28 cmt. f).) A comment to Sec
However, we need not decide whether Pennsylvania recognizes the difference-in-burden exception, wherein a party that lost on an issue in a first proceeding is nevertheless permitted to relitigate the issue in a second proceeding if its burden of proof is lower in the second proceeding.
3. Whether the PUC and the Commonwealth Court were without jurisdiction
That brings us to the Companies’ only remaining argument that the State Decision lacks any preclusive effect: that “[t]he PUC and [the] Commonwealth Court lacked subject matter jurisdiction to construe the nature of new charges imposed by a FERC transmission tariff.” (Appellants’ Opening Br. at 24.) We have recognized that Pennsylvania’s preclusion law appears to require subject matter jurisdiction in the first proceeding for a decision made in that proceeding to have preclusive effect, McCarter v. Mitcham, 883
To be clear, the Companies’ position is that the State Decision is “void ab initio for want of subject matter jurisdiction and not merely voidable as wrongly decided on the merits.” (Appellants’ Supp. Br. at 10.) They argue that the PUC and the Commonwealth Court “invaded th[e] exclusive federal scheme [of power regulation] by purporting to reclassify FERC-mandated interstate transmission rates as generation charges.” (Appellants’ Opening Br. at 32.) In other words, the Companies’ jurisdictional argument is premised on the outcome of the merits in the state proceeding being adverse to them. Notably, they do not dispute that the Commonwealth Court had jurisdiction to consider the import of the filed rate doctrine to the classification of line losses. (Id. at 33-34 (“The Companies did not contend that the Commonwealth Court lacked subject matter jurisdiction to address the Companies’ filed rate doctrine claim.”).) They only dispute that the PUC and the Commonwealth Court had jurisdiction to say they lose.
We begin by emphasizing “the limited scope of review one court may conduct to determine whether a foreign court had jurisdiction to render a challenged judgment.” Underwriters Nat’l Assurance Co. v. N.C. Life & Accident & Health Ins. Guar. Ass’n,
With respect to its jurisdiction, the PUC held:
[I]t is within the [PUC’s] discretion whether and how to allocate costs via [the Transmission Rider] or otherwise. And, we believe it is unreasonable to suggest that the [PUC] is required to rubber stamp recovery of such costs simply because they are imposed by PJM, even when the Companies voluntarily (and properly) sought approval of their recovery from [the PUC] acting within its jurisdiction to set just and reasonable retail rates for jurisdictional transmission and distribution facilities.
(J.A. at 154.) In short, the PUC concluded that it had jurisdiction not only to consider how to classify line losses for the Companies’ retail rate structure but also to resolve the classification of costs under the Settlement Agreement as it did. As the Companies have conceded, they challenged the PUC’s exercise of jurisdiction on direct appeal to the Commonwealth Court and lost. (See Appellants’ Supp. Br. at 10 (“The basis for the Companies’ appeal— forum and field preemption under the FPA and filed rate doctrine—was jurisdictional, not factual.”).)
Under Pennsylvania law, the Commonwealth Court has “jurisdiction of appeals from final orders of ... the [PUC].” 42 Pa. Cons.Stat. Ann. § 763(a). The Commonwealth Court affirmed the PUC, holding that the PUC Order “was not inconsistent with FERC precedent, did not violate the Filed Rate Doctrine, and did not improperly prevent [the] Companies from recovering trapped costs.” (J.A. at 191.) On application for discretionary review to both the Pennsylvania Supreme Court and the
The Companies, however, submit that their argument raises a question that we reserved in Crossroads Cogeneration v. Orange & Rockland: whether “an exception to the rule [of according preclusive effect to a tribunal’s determination of jurisdiction] applies in a case ... where a federal statute ... preempts [a] state agency from acting altogether.”
a. Whether the state tribunals have been divested of jurisdiction
The Companies maintain that the result of the state proceeding is void for lack of jurisdiction, and it is true that “[a] void judgment is a legal nullity.” United Student Aid Funds, Inc. v. Espinosa,
Showing that a state tribunal lacked even an arguable basis for jurisdiction over a federal question is difficult because, under the principles of federalism, there is a “deeply rooted presumption in favor of concurrent state court jurisdiction.” Tafflin v. Levitt,
In the standard fields of exclusive federal jurisdiction, the governing statutes specifically recite that suit may be brought “only” in federal court, Investment Company Act of 1940, as amended, 84 Stat. 1429, 15 U.S.C. § 80a-35(b)(5); that the jurisdiction of the federal courts shall be “exclusive,” Securities Exchange Act of 1934, as amended, 48 Stat. 902, 15 U.S.C. § 78aa; Natural Gas Act of 1938, 52 Stat. 833, 15 U.S.C. § 717u; Employee Retirement Income Security Act of 1974, 88 Stat. 892, 29 U.S.C. § 1132(e)(1); or indeed even that the jurisdiction of the federal courts shall be “exclusive of the courts of the States,” 18 U.S.C. § 3231 (criminal cases); 28 U.S.C. §§ 1333 (admiralty, maritime, and prize eases), 1334 (bankruptcy cases), 1338, (patent, plant variety protection, and copyright cases), 1351 (actions against consuls or vice consuls of foreign states), 1355 (actions for recovery or enforcement of fine, penalty, or forfeiture incurred under Act of Congress), 1356 (seizures on land or water not within admiralty and maritime jurisdiction).
Tafflin,
The Companies are correct that the FPA grants FERC exclusive jurisdiction over certain matters, but the relevant question here is whether Congress divested state utility agencies or state courts of jurisdiction to hear cases requiring an adjudication of the filed rate doctrine’s scope, and the answer to that is no. The FPA plainly leaves a role for states in electricity regulation.
Nevertheless, the Companies submit that the PUC and Commonwealth Court so exceeded the scope of their authority under the “preemptive force of the federal regulatory scheme” of the FPA and the filed rate doctrine that those tribunals utterly lacked jurisdiction. (Appellants’ Opening Br. at 29.) The Companies point out that a federal statute or regulation may pre-empt state regulation in three ways. First, under express preemption, Congress can preempt state law by explicit statutory language. Barnett Bank of Marion Cnty., N.A. v. Nelson,
As we have recently noted, preemption arguments do not ordinarily raise issues of subject matter jurisdiction. Harris v. Kellogg Brown & Root Servs., Inc.,
While the Supreme Court has said that “[d]octrines of federal pre-emption ... may in some contexts be controlling” over “the general rule of finality of jurisdictional determinations,” Durfee,
The Companies also try to rely on “complete pre-emption,” which is jurispruden-tially distinct from the three “ordinary” types of pre-emption—express, field, and conflict pre-emption—described above. Ry. Labor Exec. Ass’n v. Pittsburgh & Lake Erie R.R. Co.,
Complete pre-emption, however, stands as a limited exception to the well-pleaded complaint rule, i.e., the rule that “a case may not be removed to federal court on the basis of a federal defense, including the defense of pre-emption, even if the defense is anticipated in the plaintiffs complaint, and even if both parties concede that the federal defense is the only question truly at issue.” Id. Complete pre-emption, in other words, arises in the context of removal jurisdiction. It serves as a basis for federal jurisdiction over causes of action that may appear, on their face, to be based on state law but that are in truth only actionable under federal law due to Congress’s clear intent “to completely pre-empt a particular area of law.” U.S. Healthcare,
Furthermore, history matters here. The Supreme Court has recognized, without indicating that there were any jurisdictional defects, that “state courts have examined th[e] interplay [of the filed rate doctrine] in determining the effect of FERC-approved wholesale power rates on retail rates for electricity.” Nantahala,
b. Whether the state proceedings were an impermissible “collateral attack” on a FERC decision
The Companies also argue that the FPA explicitly proscribes the state agencies and courts, as improper forums, from resolving the dispute between the Companies and the Customer Groups such that the state proceedings were an impermissible “collateral attack” on a FERC decision. The United States Supreme Court in City of Tacoma v. Taxpayers of Tacoma,
necessarily preclude^] de novo litigation between the parties of all issues inhering in the controversy, and all other modes of judicial review. Hence, upon judicial review of the Commission’s order, all objections to the order, to the license it directs to be issued, and to the legal competence of the licensee to execute its terms, must be made in the Court of Appeals or not at all.
Id. (footnote omitted). Emphasizing that the rule bars tribunals—with the exception of federal circuit courts and the United States Supreme Court—from hearing di
When Congress intends a particular forum to have exclusive jurisdiction ..., that policy decision deprives other fora of subject matter jurisdiction. This doctrine of “forum preemption” implements Congressional determinations that development of the substantive law in a particular area should be left to a particular administrative agency created for that purpose.
Ry. Labor Execs. Ass’n v. Pittsburgh & L.E.R. Co.,
The Companies argue that, to the extent the Customer Groups had any grievances regarding the proposed fine losses, they could and should have brought their grievances in a federal court of appeals on direct appeal of a FERC order, rather than waiting to contest the Companies’ proposed rates before the PUC in a separate proceeding. However, the issue in the state proceeding—whether the Companies could classify line losses as transmission charges—was not an issue arising from any FERC order that the Companies have identified. To the extent the Companies complain that the Customer Groups should have directly appealed the Atlantic City decision, their argument is misplaced. The Customer Groups did not challenge how FERC has mandated PJM to ealcu-late its line losses. If anything, the classification of the Companies’ line-loss costs for retail billing was an issue made relevant by the voluntarily agreed-upon terms of the Settlement Agreement, which provided different end dates on transmission rate caps and generation rate caps.
c. Conclusion on state jurisdiction
Ultimately, for purposes of jurisdiction, we need not resolve whether the Companies are correct that their interpretation of line losses is required under FERC’s regulatory scheme or that the Commonwealth Court improperly deferred to certain aspects of the PUC Order. Cf. Decker v. Nw. Envtl. Defense Ctr., — U.S. -,
The Companies have not cited a single instance in which a party has been allowed to litigate a substantive issue all the way through the state courts and a petition for certiorari to the United States Supreme Court and then subsequently argue that the state courts lacked jurisdiction in the first place. The closest case is Southern Union Co. v. FERC,
The Companies also cite several Supreme Court decisions in which actions by state utility agencies were held to be preempted by FERC actions. See Entergy La., Inc. v. La. Pub. Serv. Comm’n,
Moreover, “[t]here is ... no reason to believe that Congress intended to provide a person claiming a federal right an unrestricted opportunity to relitigate an issue already decided in state court simply because the issue arose in a state proceeding in which he would rather not have been engaged at all.” San Remo Hotel, L.P. v. San Francisco,
*367 [pjublic policy [ ] ... dictates that there be an end of litigation; that those who have contested an issue shall be bound by the result of the contest; and that matters once tried shall be considered forever settled as between the parties. We see no reason why this doctrine should not apply in every case where one voluntarily appears, presents his case and is fully heard, and why he should not, in the absence of fraud, be thereafter concluded by the judgment of the tribunal to which he has submitted his cause.
Durfee,
The Companies could have withdrawn their federal issues from the state proceeding and brought them in federal court, as has been done before. See Ky. W. Va. Gas v. Pa. Pub. Util. Comm’n,
In the end, we are compelled to reject the Companies’ efforts to pose their merits-based pre-emption arguments—the same ones that were rejected in the State Decision—as jurisdictional arguments. They would like, as the saying goes, to have it both ways—if they had obtained approval to charge their customers line-loss costs as a transmission cost, the PUC and the Commonwealth Court would have had jurisdiction to approve their proposed rates; otherwise, as they perceive it, the PUC and the Commonwealth Court must lack jurisdiction, and the Companies get a “do-over” with a clean slate in federal court. It is the classic “heads I win, tails you lose” approach to dispute resolution.
IV. CONCLUSION
The Companies chose to challenge the PUC Order on direct appeal, and they must abide by the result.
We will therefore affirm the District Court’s dismissal of the Companies’ amended complaint.
Notes
. Consistent with our standard of review for dismissal under Federal Rule of Civil Procedure 12(b)(6), the facts from the Companies' amended complaint are taken as true. See Tellabs, Inc. v. Makor Issues & Rights, Ltd.,
. The FPA originally vested authority in the Federal Power Commission, but that commission was reorganized and renamed FERC in 1977. Department of Energy Organization Act, Pub.L. No. 95-91, § 204, 91 Stat. 565, 571 (codified at 42 U.S.C. § 7134).
. In contrast with a horizontally integrated monopoly, which relates to consolidation of market power “at the same level of market structure,” a vertically integrated monopoly consolidates "different levels of the market structure,” such as electricity generation, transmission, and distribution facilities and services. Oreck Corp. v. Whirlpool Corp.,
. The Electric Competition Act calls electric utilities "electric distribution companies” since they do not necessarily provide customers with direct generation services anymore. See 66 Pa. Cons.Stat. § 2803 (defining "[e]lec-tric distribution company”). For ease of reference, we will continue to refer to them as “local” or "electric” utilities.
. Under the Electric Competition Act, electric utilities have a "duty to mitigate generation-related transition or stranded costs to the extent practicable,” which may include efforts such as accelerating the depreciation and amortization of existing generation assets, minimizing new capital spending on generation assets, and maximizing market revenues from existing generation assets. 66 Pa. Cons. Stat. Ann. § 2808(c)(4).
. Upon a challenge filed by a Pennsylvania state representative, the Pennsylvania Commonwealth Court upheld the PUC’s final order approving the terms of the Settlement Agreement. George v. Pa. Pub. Util. Comm’n,
. The parties refer to lines losses interchangeably as "line losses,” "marginal transmission line losses,” “marginal transmission losses,” and "generation line losses.” (See, e.g., Appellants' Opening Br. at 32, 35; Br. of PUC and PUC Commissioners at 9.) Because the dispute underlying this case relates to whether the cost of those losses should be billed to the Companies’ customers as a cost of transmission or, instead, a cost of generation, we will use the neutral term "line losses” to refer to such loss of energy.
. The briefing refers to the "Office of Small Business Advocate.” {See, e.g., Br. of PUC and PUC Commissioners at 9.) We understand that to be an agency of the Commonwealth of Pennsylvania.
. Before consolidation, the PUC had instituted an investigation of Met-Ed’s proposed transmission charges and conditionally approved Penelec's proposed charges, pending resolution of the complaints.
. As defined in PJM’s Tariff, "[transmission losses refer to the loss of energy in the transmission of electricity from generation resources to load, which is dissipated as heat through transformers, transmission lines and other transmission facilities.” (J.A. at 481.)
. Commissioner Powelson filed a dissenting statement, saying that the Companies' line-loss costs were a cost of transmission because, inter alia, they were not expressly included as a generation cost in the Settlement Agreement, and including them in transmission costs would be consistent with FERC’s view of line losses. However, he was careful to note that “[t]his is not to say that ... line losses cannot be included within generation rates,” and he agreed with the PUC majority that FERC’s treatment of line losses "certainly is not controlling on whether the [PUC] should allow for the recovery of such losses in retail rates.” (J.A. at 165.)
.The Commonwealth Court consolidated the Companies’ petition with a cross-petition for review filed by Pennsylvania's Office of Small Business Advocate that sought review of the PUC Order to the extent it allowed the Companies to recover certain interest charges. The Commonwealth Court vacated the PUC Order with respect to that issue, which is immaterial to this appeal.
. Gardner has since been replaced as a defendant, pursuant to Rule 43(c)(2) of the Federal Rules of Appellate Procedure, with PUC Commissioner Gladys M. Brown. See Fed. R.App. P. 43(c)(2) (providing that, if an officeholder who is sued in his or her official capacity ceases to hold office, the officeholder's successor is automatically substituted as a party).
. There is no dispute that the State Decision leaves them free to recover line-loss costs after the Settlement Agreement's generation rate cap lapsed at the end of 2010.
. According to the Companies’ amended complaint in this action, the amount that they seek to recover exceeds their combined net income in 2009 and 2010.
. The District Court initially denied the motion to dismiss the amended complaint without prejudice to renew, pending resolution of the certiorari petition in the United States Supreme Court from the state proceeding. The PUC Defendants renewed their motion to dismiss after the Supreme Court denied cer-tiorari.
. The PUC Defendants also raised the Full Faith and Credit Statute, 28 U.S.C. § 1738, as a separate ground for dismissal in the District Court. However, as we will explain, that statute directs us to Pennsylvania’s law on preclusion. So, like the District Court, we will not examine the Full Faith and Credit Statute as a separate basis for dismissal.
. The Met-Ed Industrial Users Group and Penelec Industrial Users Alliance filed a brief before us as Intervenors-Appellees. In it, they adopt and join all of the PUC Defendants’ arguments and emphasize that “the [] PUC appropriately enforced the Companies' obligation under the ... Settlement Agreement.” (Intervenors-Appellees’ Br. at 14-15.) For simplicity, we only cite to the PUC
. The District Court had jurisdiction under 28 U.S.C. §§ 1331 and 1343(a)(3). The Companies argue that the Court also had jurisdiction under 16 U.S.C. § 825p, which provides federal district courts with jurisdiction to "enforce any liability or duty created by, or to enjoin any violation of [the FPA] or any rule, regulation, or order thereunder.” We have jurisdiction pursuant to 28 U.S.C. § 1291. We exercise plenary review of a district court's order of dismissal under Federal Rule of Civil Procedure 12(b)(6), Atkinson v. La-Fayette Coll.,
. Some earlier Pennsylvania cases apply the same issue preclusion test but without the fifth prong regarding whether the prior determination was essential to the judgment. E.g., Shaffer v. Smith,
. The Companies argue that the State Decision was a legislative action rather than an adjudication. We will address that argument when discussing the exceptions that they raise to the application of issue preclusion.
. "A party has been denied a full and fair opportunity to litigate only when state procedures fall below the minimum requirements of due process as defined by federal law.” Bradley v. Pittsburgh Bd. of Educ.,
. The opening brief before us is the first time the Companies raised arguments regarding how issue preclusion might apply differently to Counts II and III. As the PUC Defendants point out, the Companies did not even identify those arguments in their Concise Summary of the Case filed before us.
. For the reasons already discussed, issue preclusion does apply to Count I, absent any applicable exception,
. To the extent the Companies claim that they have not had a full and fair opportunity to litigate Counts II and III, that argument is unavailing. While the Companies may not have litigated the claims set forth in Counts II and III in the state proceeding, they had a full and fair opportunity to litigate the underlying issues of whether classifying their line-loss costs as a generation cost for retail billing purposes violated the filed rate doctrine or impermissibly trapped costs.
. Under 2 Pa. Cons.Stat. Ann. § 704, which relates to "Judicial Review of Commonwealth Agency Action”:
The [reviewing] court shall hear the appeal without a jury on the record certified by the Commonwealth agency. After hearing, the court shall affirm the adjudication unless it shall find that the adjudication is in violation of the constitutional rights of the appellant, or is not in accordance with law, or that the provisions of Subchapter A of Chapter 5 (relating to practice and procedure of Commonwealth agencies) have been violated in the proceedings before the agency, or that any finding of fact made by the agency and necessary to support its adjudication is not supported by substantial evidence. If the adjudication is not affirmed, the court may enter any order au*355 thorized by 42 Pa.C.S. § 706 (relating to disposition of appeals).
2 Pa. Cons.Stat. Ann. § 704.
. We note, without holding, that Pennsylvania would appear to recognize the difference-in-burden exception under Restatement (Second) of Judgments § 28(4). The Pennsylvania Supreme Court has cited other provisions of Section 28 favorably. See, e.g., Cohen v. Workers’ Comp. Appeal Bd..,
. At oral argument, the Companies also raised the concern that Pennsylvania “ha[s] [its] own version of Chevron deference” that would not apply in federal court. (Tr. at 29:20-24, 30:17-31:8.) The Companies, however, conceded that that argument also relates to a "standard of review,” not a burden of proof on the merits. (Tr. at 31:9—14.)
. There seems to be some tension in the Supreme Court’s jurisprudence as to how Congress may remove jurisdiction from state courts. In an earlier case, the Supreme Court said, more broadly, that Congress may divest states of jurisdiction in three ways: explicit statutory directive, unmistakable implication of the statute’s legislative history, or
. Our dissenting colleague asserts that Congress, through the FPA, "divest[ed] states of jurisdiction to interpret FERC orders that define the elements of the rates of transmission facilities, such as PJM.” (Dissenting Op. at 371.) The authorities she cites for that proposition, however, are two cases reviewing whether FERC had jurisdiction to make certain other determinations. See New Orleans Pub. Serv., Inc. v. Council of New Orleans,
. "Furthermore, § 205 of the FPA prohibited, among other things, unreasonable rates and undue discrimination ‘with respect to any transmission or sale subject to the jurisdiction
. Field pre-emption and conflict pre-emption can be characterized as falling under "implied,” as opposed to “express,” pre-emption. See Roth v. Norfalco LLC,
. At oral argument, we asked the parties to submit supplemental briefing on whether preemption may be waived. The PUC Defendants argue that the Companies waived their pre-emption arguments by entering into the Settlement Agreement. They point to a provision in the agreement that provides, in part, that the Companies "agree that they shall not initiate or join in any court challenge, arising out of the issues resolved by this Settlement, to the constitutionality or legality of the Electric Competition Act such that would prevent or preclude implementation of this Settlement.” (Supp.App. at 70.) There may be an argument that the Companies, pursuant to that provision, waived their ability to bring Count III to challenge the constitutionality of the Electric Competition Act as applied. We need not reach that conclusion, though, because, as we have already discussed, see supra Part III.A.l, the Companies waived any argument that Count III rises or falls separately from Count I for purposes of issue preclusion.
The PUC Defendants also submit that, by fully arguing pre-emption in the Commonwealth Court, the Companies have waived their ability to raise pre-emption in federal court. But that is not a waiver argument related to the Companies' failure to raise an argument when it should have. It simply restates the PUC Defendants’ view that the State Decision—having been fully litigated— should bar the Companies from relitigating the issue of pre-emption. We are satisfied from a review of the record that the Companies timely raised their pre-emption arguments in the District Court.
. We are not suggesting that FERC would endorse what the PUC and the Commonwealth Court decided. Our dissenting colleague has ably discussed why that can be doubted. We eschew any comments on the merits beyond our observation that there is no definitive FERC. ruling.
. We have some doubt that either the FPA or the filed rate doctrine effects a complete preemption of state law. "The Supreme Court has recognized the ‘complete preemption’ doctrine in only three instances: § 301 of the [Labor Management Relations Act]; § 502(a) of [the Employee Retirement Income Security Act of 1974]; and §§ 85 and 86 of the National Bank Act.” N.J. Carpenters v. Tishman Constr. Corp.,
. FPA § 313(b) provides, in relevant part:
Any party to a proceeding under this chapter aggrieved by an order issued by the Commission in such proceeding may obtain a review of such order in the United States court of appeals for any circuit wherein the licensee or public utility to which the order relates is located ... by filing in such court, within sixty days after the order of the Commission upon the application for rehearing, a written petition praying that the order of the Commission be modified or set aside in whole or in part.... Upon the filing of such petition such court shall have jurisdiction, which upon the filing of the record with it shall be exclusive, to affirm, modify, or set aside such order in whole or in part .... The judgment and decree of the court, affirming, modifying, or setting aside, in whole or in part, any such order of the Commission, shall be final, subject to review by the Supreme Court of the United States upon certiorari or certification....
16 U.S.C. § 8251(b) (emphasis added). The relevant language of that provision has not changed materially since the City of Tacoma decision, except that when that opinion issued, exclusive jurisdiction attained "[ujpon the filing of [the] transcript” from the challenged FERC proceeding. 16 U.S.C. § 8251(b) (1958).
. The Companies themselves, who were adversely affected by the Atlantic City decision, did not mount any challenge to that FERC order.
. To be clear, we agree with our dissenting colleague that "[t]he fact that the Supreme Court did not grant certiorari does not mean that [a] question may not be validly raised in federal district court.” (Dissenting Op. at 373-74 n. 3.) As Southern Union illustrates, there may be exceptions.
. Although we have no occasion to revisit the substance of the PUC Order, it is worth noting that FERC has gone to some lengths to reserve to state agencies various issues regarding the potential recovery of retail costs. See Exelon Corp. v. PPL Elec. Utils. Corp., EL05-49-000, EL05-49-001,
. Our dissenting colleague believes that the policy interests in pre-emption outweigh those in applying issue preclusion. Even if her view of those policy interests were correct, however—and that is something as to which we make no further comment—the premise of her argument about preemption is problematic, for reasons we have noted already. She asserts that FERC has spoken in a binding way as to the classification of line losses. We respectfully disagree. While FERC has ruled on the method that PJM must use to calculate line losses, no one has presented to FERC the issue presented here, i.e., how line losses should be categorized for billing purposes, especially in light of a settlement agreement of the sort involved in this case. (At least no one has directed our attention to such a FERC order.)
. In their supplemental briefing, the Companies argue that "[i]f the state court found the FERC tariff and precedent unclear, it should have certified the question to FERC itself.” (Appellants’ Supp. Br. at 3.) That, however, is immaterial because ”[t]he relevant question ... is not whether the [party] has been afforded access to a federal forum; rather, the question is whether the state court actually decided an issue of fact or law that was necessary to its judgment.” San Remo,
.At oral argument, the Companies conceded that they were taking such a position. (Tr. at 5:8-19 ("THE COURT: So your position is really a heads I win, tails you lose position? ... [COUNSEL FOR THE COMPANIES]: Well, that’s the ... characterization that the ... opposing side put in their briefs[,] ... but it's accurate.”).) They tried to distance themselves from that characterization on rebuttal but simply highlighted their position that,
. Because all of the Companies’ claims in this action are foreclosed by the doctrine of issue preclusion, we need not reach matters of claim preclusion, abstention, or judicial estoppel.
Dissenting Opinion
dissenting:
I do not dispute that the federal courts are precluded from reviewing a state court decision applying filed rates. However, I disagree with the majority that this is what is at issue. The issue here is whether the Commonwealth Court’s misinterpretation of FERC orders, defining a component of a rate, is subject to collateral attack in federal court. I would hold that it is.
Contrary to the Commonwealth Court’s assessment that the FERC orders in question are ambiguous, FERC has clearly classified the component “line loss” as a transmission related cost. Atl. City Elec. Co. v. PJM Interconnection, LLC (Atlantic City I),
I. Background
The dispute here starts in June 2007, when PJM, a facility that transmits wholesale electricity over an interstate grid, implemented a new pricing scheme. Atlantic City I,
To understand these issues, I will go back to the enactment of the Federal Power Act (FPA) and the ensuing FERC oversight of the interstate transmission of electric power. In 1927, the Supreme Court held that the sale of electricity in interstate commerce falls under the exclusive jurisdiction of Congress. Pub. Utils. Comm’n v. Attleboro Steam & Elec. Co.,
The Companies acquire electricity from PJM and deliver it to retail ratepayers. Id at 82. Pursuant to the FPA, the rate PJM charges the Companies for this transaction is regulated exclusively by FERC. Id. FERC has reviewed PJM’s rates on various occasions. Relevant here is FERC’s review of PJM rates calculated via the locational marginal pricing (LMP) methodology, which classifies line losses as a transmission related costs. See PJM Interconnection I,
In PJM Interconnection I, FERC approved a proposal by PJM to begin calculating rates based on the LMP methodology. Id.
The Commission accepted, with certain modifications, the Supporting Companies’ locational marginal pricing (LMP) model for calculating and recovering congestion costs. LMP is defined as the marginal cost of supplying the next increment of electric demand at a specific location on the electric power network, taking into account both generation and marginal cost and the physical aspects of the transmission system. When the PJM system is unconstrained, there is a single market clearing price for hourly energy equal to the marginal cost of meeting the last increment of demand. When transmission constraints occur on the PJM system, the marginal cost of energy varies by location because not all supply can be delivered to all demand. The differences between the LMPs at different locations represent congestion costs.
In Atlantic City I, FERC issued an order requiring PJM to account for a third component in the LMP, “transmission line losses.” Id.
Prior to Atlantic City, “transmission line losses” were recovered under an average loss method. Id. at 61,473. The average loss method calculated losses separately from the LMP via an uplift charge, distributing losses equally among all loads. Id. In other words, customers in nearby locations paid the same amount as customers in more distant locations—the cost of the lost power being distributed equally among all customers. In Atlantic City, FERC mandated that PJM implement the marginal loss method, in which “the effect of losses on the marginal cost of delivering energy is factored into the energy price (i.e., the Locational Marginal Price, or the LMP) at each location.” Id. at 61,474. Under this method, the cost of line losses increases as the distance between generator and user increased. Id. Akin to calculating congestion costs, calculating line losses is an incentive to PJM to use the transmission grid more efficiently. For example, in an effort to decrease the costs of line loss, PJM will consider distance in determining “which generators to dispatch to meet its loadsf’M
Pertinent here, PJM implemented the marginal loss method in June 2007, resulting in new charges to the Companies, reflecting the cost of transmitting power over long distances. The Commonwealth Court, in affirming the PUC, misinterpreted the above mentioned FERC orders, holding these orders to be ambiguous. On this basis, the court denied the Companies’ appeal to pass these costs on to retail ratepayers.
II. Preclusive Effects of the Commonwealth’s Determination
How we frame the question presented in this case matters a great deal. The Companies do not question that the Common
The FPA clearly divests states of jurisdiction to interpret FERC orders that define the elements of the rates of transmission facilities, such as PJM. See New Orleans Pub. Serv., Inc. v. Council of New Orleans,
As the majority indicates, we are not bound by preclusion when “Congress expressly ousts state courts of jurisdiction.” Haywood v. Drown,
Furthermore, the Supreme Court has cautioned that a state-court judgment is subject to collateral attack when “the policy underlying the doctrine of res judicata is outweighed by the policy against permitting the court to act beyond its jurisdiction.” Durfee v. Duke,
When Congress intends a particular forum to have exclusive jurisdiction to determine the rights of the parties in a particular situation, that policy decision deprives other fora of subject matter jurisdiction. This doctrine of “forum preemption” implements Congressional determinations that development of the substantive law in a particular area should be left to a particular administrative agency created for that purpose.
Ry. Labor Exec. Ass’n v. Pittsburgh & Lake Erie R.R. Co.,
III. Commonwealth’s Review of FERC Orders
The Commonwealth Court’s conclusion that the FERC orders “do not unambiguously state that [line losses] are transmission related” is flatly contradicted by FERC’s persistent use of the term “transmission line losses” throughout the orders of Atlantic City I and Atlantic City II. Metropolitan Edison Co.,
Furthermore, the language quoted by the court to illustrate ambiguity does nothing of the sort. According to the Commonwealth Court, FERC associated line losses with both transmission and generation. Metropolitan Edison Co.,
FERC stated “locational marginal prices [ (how line losses are calculated) ] are at the core of the PJM pricing methodology, because marginal prices send the proper price signals about the cost of obtaining generation.” FERC then explained how line loss costs impact a utility’s decision regarding from which generator to purchase energy. Similarly, in Atlantic City I, FERC noted that requiring PJM to charge for line loss on a locational marginal basis “ensures that each customer pays the proper marginal cost price for the power it is purchasing” and that, in using marginal pricing, “PJM would change the way that it dispatches generators by considering the effects of losses.”
Id. (quoting Atlantic City I,
In these statements, FERC simply illustrated the transmission related incentives that arise when line losses are calculated into the LMP. When line loss costs are calculated, PJM will attempt to shorten the route of delivering electricity by choosing the generators that are closest to the customers. Thus, this calculation encourages PJM to use the transmission system more efficiently. Atlantic City I,
Furthermore, FERC has indicated that similar incentives arise when congestion is calculated into the LMP, a cost that both the PUC and the Commonwealth Court have found to be related to transmission. PJM Interconnection I,
Finally, the Commonwealth Court referred to language in PJM Interconnection I and PJM Interconnection II that seemingly associated line loss with the cost of generation. Metropolitan Edison Co.,
At the time PJM Interconnection was decided, the LMP calculated two cost components, generation and the transmission constraints of congestion. PJM Interconnection II,
However, under LMP, the Commonwealth Court’s assessment of FERC orders as ambiguous is misplaced. It is clear that in conjunction with LMP, FERC has consistently classified line loss as a transmission related cost.
IV. Conclusion
In focusing on the Companies’ attempt to have us review the Commonwealth’s substantive determination under the filed rate doctrine, the majority misses the forest for the trees. The state may not improperly interpret a matter outside of its jurisdiction when the matter has been left to the exclusive jurisdiction of FERC.
. In a separate order, FERC noted that prior to the implementation of the marginal loss method, ‘‘[flosses were not included in the calculation of LMPs, and thus, were not recovered in the LMP energy prices collected from loads.” Black Oak Energy, LLC,
. It is FERC's prerogative to determine the elements that go into a filed rate. In Nant-ahala the element in question was the percentage of entitlement power to be allocated between two utilities. In the present case, the element is "line loss” and its classification by FERC as an element of transmission. Once FERC has spoken on the definition of any such element, the matter is preempted. The states may not then dispute that classification. The Commonwealth Court’s conclusion that there was no conflict here with FERC is invalid for the reasons set forth above.
. From the beginning the Companies have taken the position that this is a matter that can only be determined by FERC. And, in essence, this is the question asked by the Companies in their petition for certiorari to the Supreme Court:
The Federal Power Act, 16 U.S.C. §§ 824 et seq., grants the Federal Energy Regulatory Commission ("FERC”) “exclusive authority to regulate the transmission and sale at wholesale of electric energy in interstate commerce.” New England Power Co. v. New Hampshire,455 U.S. 331 , 340,102 S.Ct. 1096 ,71 L.Ed.2d 188 (1982). A regional transmission organization ("RTO”) implementing its federal tariff charged petitioners for "transmission line losses”—the energy that dissipates when electricity is transmitted through wires. Although it was undisputed that the RTO imposed those charges as a cost of transmission, the Pennsylvania Public Utility Commission and the court below barred petitioners from recovering those federally imposed costs in retail rates by ruling that "transmission line losses” are generation costs (a cost of producing electricity), not transmission costs. Notwithstanding the filed rate doctrine, they deemed it irrelevant that the RTO had imposed the charges as "transmission” costs. They held that state regulators were free to recategorize the charges because FERC had not "unambiguously” or "explicitly” declared that "transmission line losses” are "transmission costs.” The questions presented are:
1. Whether, contrary to a decision of the Fifth Circuit, the Federal Power Act and filed rate doctrine permit a state public utility commission to deny recovery of FERC-man-*374 dated charges by classifying those costs differently from the entity responsible for administering the federal tariff on the ground that the tariff and FERC's orders do not "unambiguously” or "explicitly” foreclose the State’s chosen classification.
2. Whether, contrary to a decision of the D.C. Circuit, "transmission line losses" reflect the costs of generating electricity rather than the costs of transmitting it.
Petition for Writ of Certiorari, Metro. Edison Co. v. Pa. Pub. Util. Comm’n, - U.S. -,
