METRO BUILDERS HARDWARE, INC.
v.
BURKO CONSTRUCTION, INC., et al.
Court of Appeal of Louisiana, Fourth Circuit.
*839 Charles W. Nelson, Jr., New Orleans, for plaintiff-appellant.
H. Bruce Shreves, Jay H. Kern, Avis Marie Russell, Simon, Peragine, Smith & Redfearn, New Orleans, for defendants-appellees.
Before BARRY, CIACCIO and LANDRIEU, JJ.
BARRY, Judge.
The sole issue is whether LSA-R.S. 22:1220, which provides a penalty against insurers for failure to timely pay a claim, is applicable on a surety bond which was issued under the Louisiana Public Works Act. We conclude that the Louisiana Public Works Act is exclusive and affirm the denial of a penalty.
FACTS
Burko Construction, Inc. contracted with the Housing Authority of New Orleans (HANO) for a construction project. Metro Builders Hardware, Inc., (plaintiff) supplied materials to Burko, and Amwest Surety Insurance Company furnished a performance and payment bond. Burko failed to make payment for materials in the amount of $8,848.44. Plaintiff filed a materialman's lien and sued Amwest, seeking the principal amount of the claim, attorney fees under LSA-R.S. 38:2246 and penalties under LSA-R.S. 22:1220.
Plaintiff filed for a summary judgment which was granted on the principal amount, but denied (after supplemental briefing) as to attorney fees and penalties. In an effort to obtain a final, appealable judgment, Amwest then moved for a summary judgment to deny attorney fees and penalties. The trial court awarded plaintiff $885.00 in attorney fees but denied penalties, holding that R.S. 22:1220 inapplicable.
ANALYSIS
Plaintiff contends LSA-R.S. 22:1220[1] of the insurance code should be applied because the surety bond is an insurance contract and failure to pay under that contract results in penalties under Section 1220.
The Public Works Act, LSA-R.S. 38:2241 et seq., is sui generis and provides exclusive remedies to parties in public construction work. Martinolich v. Albert,
The Public Works Act provides that a public entity which contracts in excess of $5,000 for the construction, alteration or repair of any public works must require of the contractor a surety bond for payment by the contractor or subcontractor to any claimant as defined therein. LSA-R.S. 38:2241(A). That bond is a statutory bond. Id. LSA-R.S. 38:2241(C) further provides in pertinent part:
... Language in any such bond containing any obligations beyond the requirements *840 set forth in this Part shall be deemed surplusage and read out of such bond. Sureties and contractors executing payment bonds for public works contracts under this Part shall be immune from liability for or payment of any claims not required by this Part. [Emphasis added.]
Attorney fees are recoverable under the statute where payment is not made within thirty days after amicable demand on the principal or surety and the claimant recovers the full amount of the claim. LSA-R.S. 38:2246.[3] Section 2246 is penal in nature, its intent "... to encourage and promote amicable settlement of claims arising from Public Works contracts to the end that persons furnishing materials, supplies, and labor on such projects will be paid promptly, thus avoiding the inconvenience, delay and expense occasioned by litigation." Interstate School Supply Company, Inc. v. Wilson,
Louisiana courts have refused to allow recovery on a statutory bond beyond the provisions in the statute. Pittman Construction Co. v. Housing Authority of New Orleans,
The two cases which plaintiff cites for the proposition that the surety bond is an insurance contract and therefore the surety is subject to the penalty provisions of the insurance code are factually distinguishable. In F. Miller & Sons, Inc. v. Travelers Indemnity Co.,
Because the public contract and bond in this case are governed by the Public Works Act, Amwest is not liable for any claim not provided for in the statute. See Martinolich v. Albert, supra; Coating Specialists, Inc. v. Pat Caffey Contractor, Inc., supra. Accordingly, we hold that LSA-R.S. 22:1220 is inapplicable to plaintiff's claim for penalties.
AFFIRMED.
NOTES
Notes
[1] Section 1220 provides in pertinent part:
A. An insurer, including but not limited to a foreign line and surplus line insurer, owes to his insured a duty of good faith and fair dealing. The insurer has an affirmative duty to adjust claims fairly and promptly and to make a reasonable effort to settle claims with the insured or the claimant, or both. Any insurer who breaches these duties shall be liable for any damages sustained as a result of the breach.
B. Any one of the following acts, if knowingly committed or performed by an insurer, constitutes a breach of the insurer's duties imposed in Subsection A: ...
(5) Failing to pay the amount of any claim due any person insured by the contract within sixty days after receipt of satisfactory proof of loss from the claimant when such failure is arbitrary, capricious, or without probable cause.
C. In addition to any general or special damages to which a claimant is entitled for breach of the imposed duty, the claimant may be awarded penalties assessed against the insurer in an amount not to exceed two times the damages sustained or five thousand dollars, whichever is greater.....
[2] In Martinolich v. Albert, supra, the First Circuit refused to allow the claimant (a furnisher of certain manned equipment rentals in a public contract) to recover from the owner under a quantum meruit theory of recovery.
[3] LSA-R.S. 38:2246(A) provides:
A. After amicable demand for payment has been made on the principal and surety and thirty days have elapsed without payment being made, any claimant recovering the full amount of his timely and properly recorded or sworn claim, whether by concursus proceeding or separate suit, shall be allowed ten percent attorney's fees which shall be taxed in the judgment on the amount recovered.
