154 Misc. 2d 355 | N.Y. Sup. Ct. | 1992
OPINION OF THE COURT
The plaintiff homeowners contracted with the defendant for
On June 29, 1989, defendant served and filed a second notice of lien, and this filing was perfected as required by statute. This second notice again recites that the last services, labor and materials were furnished on February 15, 1989; and then states that since the contract involved has not been fully performed or completed, then four months have not elapsed since the completion of the contract. After this second notice of lien was filed, plaintiffs’ new counsel sent written notice of July 26, 1989 that plaintiffs considered their contract terminated as of May 9, 1989 (the day of receipt of defendant’s May 8,1989 counteroffer letter).
Plaintiffs now seek to discharge this mechanic’s lien, which on its face, appears to have been untimely filed more than four months after the last services were furnished. Defendant initially argued that since the contract is still not completed, their second notice of lien complies with the statutory require
The court has not found a case precisely on point; neither do the parties provide such a case. As such our analysis starts with the statute, and then looks to judicial interpretation thereof.
Lien Law § 10 (1) provides that notice of lien may be filed at any time: during the progress of the work and furnishing materials; within four months after completion of contract; within four months of final performance of work; within four months of final furnishing of materials.
Lien Law § 19 (6) provides that where it appears "from the public records that such notice [of lien] has not been filed in accordance with the provisions of section ten” the property owner may apply for a discharge of that lien; and upon verified application showing such invalidity, the court shall make an order discharging the lien.
It is fundamental that the court has no inherent power to summarily discharge a mechanic’s lien and that its power to do so is limited exclusively to the grounds enumerated in the Lien Law (Di Camillo v Navitsky, 90 Misc 2d 923, 924 [Sup Ct, Putnam County, June 27, 1977]; Jensen, Mechanics’ Liens §§ 301, 311 [4th ed]).
The courts have also consistently held that where a notice of lien is sufficient, according to its face and any recording data, the court may not pass on disputed issues of fact in order to summarily discharge that lien (Matter of Jory Constr. Corp. [Westchester Sq. Sash & Door Co.], 6 Misc 2d 701, 702). Where it appears that the specific requirements of the statute have been observed, and that there exists no defect upon the face of the notice of lien, then any dispute regarding the validity of the lien must await trial in an action to foreclose that lien (Dember Constr. Corp. v P & R Elec. Corp., 76 AD2d 540, 546; Di Camillo v Navitsky, supra, at 924-925; Matter of Jory Constr. Corp. [Westchester Sq. Sash & Door Co.] supra, at 702).
Looking to the wisdom of these cases, and to the face of the second notice of lien filed by the defendant herein, it would
Looking only to the public records, as mandated by statute and case law stated above, there are no issues of fact concerning the existence of a defect in this second notice of lien, and accordingly, the plaintiffs are entitled to summary discharge of this lien (Di Camillo v Navitsky, supra, at 925).
Concerning defendant’s claim in his answering papers herein, that plaintiffs’ "termination” of the contract on May 9, 1989 is equivalent to "completion” of the contract under the Lien Law, he has submitted no case law to support this position. Defendant cites the Fourth Department case Biondo v City of Rochester (18 AD2d 78) and the First Department case Matter of N. W. Developers v Jeremiah Burns, Inc. (55 AD2d 580) to explain the meaning of "completion” in the Lien Law. However, the court does not find those cases persuasive, since they both deal with section 12 of the Lien Law, which involves public improvements, and require the filing of a lien after completion and acceptance of the construction; and those cases deal with the need to file a certificate of acceptance prior to the time period running. Moreover, in both cases, the courts stated that " '[cjompletion refers to the termination of the physical work; acceptance to the formal act by the * * * public corporation whereby it is recognized that the contractor has performed his contract’ ” (Biondo v City of Rochester, supra, at 84; Matter of N. W. Developers v Jeremiah Burns, Inc., supra, at 581). Here, the physical work was terminated on February 15, 1989; and the plaintiffs never recognized that the defendant performed the contract. In fact, all agree that
Having found the filing of this second notice of lien to be untimely on its face, and having found no question of fact concerning the existence of a defect on the face of this second notice of lien, plaintiffs are entitled to the summary discharge of this lien, and their motion in this regard is granted. The defendants are still entitled to litigate their four remaining counterclaims, sounding in contract.