96 Iowa 652 | Iowa | 1896

Rothrock, C. J.

*6541 *653I. Ellen H. Ballou is the wife of F. B. Ballou, and is the owner of the lot upon which the dwelling house was erected. On the first day of August, 1893, a written contract was entered into between Hopkins and Ellen Ballou, by which Hopkins undertook to furnish the materials, and build and complete the house in four months. The contract price-*654for building the house was four thousand one hundred dollars, and payment was to be made as follows: “At the end of each month, ninety (90) per cent, of the value of the work actually done, to be estimated by the architect in charge of said building, and the balance of ten per cent, shall be paid when the whole work mentioned and described in this contract * * shall have been completed and delivered to said second party, and by said second party or by the architect accepted, and not before.” The said contract also contains the following stipulation: “E. E. Hopkins also agrees to accept an order on E. Plane & Co. for eight hundred dollars as part payment on this contract.” A question in dispute between the parties is whether the order of eight hundred dollars should be held to be a part of the contract price for building the house, in determining the monthly payments to be made to the contractor by the owner. It is contended in behalf of the owner -that the ten per cent, to be held till the completion of the house should be 'estimated upon the balance after deducting the eight hundred dollars. We have set out that part of the contract, and we think it is so plain that the ten per cent, to be retained applies to the whole sum of four thousand one hundred dollars named in the contract that we do not deem it necessary to discuss it. The eight hundred dollars was payment, just the same as if it had been paid in cash, instead of by an order on a third person.

*6552 *654II. Merritt & Allen furnished materials for the building. The house was completed and delivered to Ballou late in the month of December, after the contract was entered into. Ballou made payments from time to time, according to the estimates of the work done, and the whole of such payments amounted to three thousand nine hundred dollars. The last payment was two hundred dollars, on the twelfth day of *655December, 1893. And Merritt & Allen furnished the material for which they claim a lien from time to time during the progress of the Work. The last item was furnished on the twenty-first day of December. The claims for liens were filed at the time following: Merritt & AlleD, January 9, 1894. All of the others were filed on the next day, but that of Primus, which was filed on the eleventh, and Crane on the thirteenth, of that month. The plaintiffs did not serve written notice upon Ballou of the filing of their claim within thirty 'days after it was filed. They commenced this action on the next day after the claim for a lien was filed, and on the next day after that an original notice was served upon Ballou and Hopkins, and some of the other claimants for liens. This original notice was in the usual form in such cases. It stated the amount claimed and described the property upon which the lien was sought, but "made no reference to the filing of ’the claim for a lien. Crane filed his petition on May 3, 1894. He gave no written notice of the filing of his lien. It is required by section 6 of chapter 100, Acts of the Sixteenth General Assembly, that every subcontractor who desires to avail himself of the provisions of the statute “shall file with the clerk of the district court a just and true ■statement or account of the demand, due him, and that * """ such verified statement or account must ’be filed by * * * a subcontractor within thirty days from the date on which the last item of the material shall have been furnished or the last of the labor was performed.” Section 7 of the act provides as follows: “To preserve his lien against the owner and to prevent payments by the latter to the principal contractor or to intermediate subcontractors, but for no other purpose, the subcontractor must within thirty days as provided in section six serve upon the owner, his agent or trustee, a written notice of the filing of such *656claim. * *” In Lonsbury v. Railroad Co., 49 Iowa, 255, it was held that the failure to serve written notice on the owner that a lien had been filed defeats the lien of a subcontractor. And that rule was followed in the late case of Walker v. Queal, 91 Iowa, 704 (58 N. W. Rep. 1083). In Lonsbury’s Case it was said that: “As this is a statutory lien, it matters not what notice or knowledge the owner may have, ’if the required notice is not given, at least in substance. No such thing as constructive notice is known to, or recognized by, the statute.” In that case, as in this, an action was commenced in which an original notice was served, but, as that did not state that a lien was filed, it was ’held that it could not be regarded as a written notice of the filing of the lien. See, also, Steele v. McBurney, 96 Iowa, 449 (65 N. W. Rep. 332). This seems to be conclusive against the establishment of the liens of Merritt & Allen, and the lien claimed by Crane, especially as against the claims of the other subcontractors who complied with the law by giving notice of the filing of their liens.' It is to be remembered that these parties are 'all subcontractors, and the rule adopted in the cited cases is not in conflict with Bissel v. Lewis, 56 Iowa, 240 (9 N. W. Rep. 177). In that case the lien claimed was that of a principal contractor. But it'is claimed in behalf of appellees Merritt & Allen and Crane, that the question of failure to- give written notice of the filing of the lien was not presented in the court below, and that it is introduced 'for the first time in this court. It is true that there was no averment in the petition that written notice'was given. But after all the petitions were filed the owner filed an answer and cross bill against all the claimants,' in which the failure to give notice is charged in substance, if not in express terms. It'perhaps ought to be stated that, in the petition filed by Crane, it was stated that notice-*657of the filing of the claim for'a lien was served on the owner, but there was no evidence showing that service was had. And, as between the subcontractors, the issue of want of notice on the owner was expressly made.

3 III. Having found that Merritt & Allen and Crane have no right to a lien, we now come to consider the rights of the other subcontractors-. Some question is made to the effect‘that Kline’s claim was shown by the evidence not to be a continuous account, but that it was 'founded on two separate contracts. It is true that he worked on the building at one time, and ceased to work,'and then commenced again. There was no such distinct and separate employment as to' defeat his right to file the whole of his claim, and assert it as a lien.

IY. Under the written contract'between Ballou and Hopkins, payment was to be made at the end of each month, but ten per cent was to be retained by Ballou, and was not due and payable until the whole work was completed. This would have amounted to four hundred and ten dollars. If that amount was subject to mechanic's’ lien, it is more than sufficient to pay the several judgments rendered by the district court in favor of the subcontractors who gave notice of the filing of their liens. It is therefore unnecessary to determine the question of priority between them. Indeed, we do not understand that they claim that the district court erred in fixing their'rights, as between them.

*6584 *657Y. It is urged in behalf'of appellant that Ballou assumed the payment of other subcontractors’ claims after December twelfth, and that the obligation to *658them'would materially reduce the amount which the parties to this action have a right to assert as liens. These assumptions of payment appear to be in the 'way of indorsing the principal contractors’ promissory notes. It does not appear that it was in pursuance of any claims for'liens, and they ought not to be allowed to prevail over the liens of the'parties to the action.

5 YI. It is strongly urged in behalf of appellant that there was no evidence from which it should be held that'appellant was 'charged with notice that the labor and materials furnished might be made the subject of liens. It is sufficient to say, without' setting out the testimony of the witnesses, that the owner had every opportunity of knowing, and did know, that these parties might assert their liens within the proper time. The proven facts bring the case within the rule adopted by this court in Lumber Co. v. Murphy, 64 Iowa, 165 (19 N. W. Rep. 898); Winter v. Hudson, 54 Iowa, 336 (6 N. W. Rep. 541); Gilchrist v. Anderson, 59 Iowa, 274 (13 N. W. Rep. 290); Lumber Co. v. Woodside, 71 Iowa, 359 (32 N. W. Rep. 381), and other cases determined by this court. It is to be remembered that this case does not come within that class of cases in which it was held that the owner may pay the contractor according to the strict terms of his contract. In this case the owner should have held the ten per cent, reserved at the end of each month. As to the liens of Merritt & Allen and Crane, the decree of the district court is reversed. As to the otheivliens it is affirmed.

© 2024 Midpage AI does not provide legal advice. By using midpage, you consent to our Terms and Conditions.