113 Misc. 84 | N.Y. Sup. Ct. | 1920
In December, 1915, the city of Buffalo entered into a contract with the defendant Long for the construction of the city hospital for $407,324.86. The United States Fidelity and Guaranty Company then executed, as surety for Long, a bond in the sum of $191,750, to the city of Buffalo, conditioned upon the performance and completion by Long of his contract, and further conditioned upon Long well and truly paying for all material used and services rendered in the execution of the contract. This last mentioned condition of the bond was written pursuant to the provisions of the charter and ordinances of the city, and was an enforcible provision. Wilson v. Webber, 157 N. Y. 693, affg. 92 Hun, 466, on opinion below.
The contract provided that payments should be made to the contractor as the work progressed, upon
Later in November, the defendant London Guaranty and Accident Company, in suits brought by it against Long, levied two attachments aggregating $5,640.13 and interest, upon any and all debts due Long from the city of Buffalo. On November 19, 1917, the contractor
On December 6, 1917, the board of managers of the hospital adopted resolutions declaring Long in default on his contract, electing on the part of the city to perform and complete the work according to the contract, and notifying the defendant United States Fidelity and Guaranty Company, surety on the contractor’s bond, to complete and perform the contract. The surety company thereupon, as surety for Long and not as an independent contractor, entered upon the completion of the contract and finally completed the same on November 21, 1918, at a total expense to it of $35,-458.32. In addition to this, the surety company paid to various persons who had furnished labor or material to Long on the execution of the contract, and for the payment of which it was obligated under its bond,
The defendant London Guaranty and Accident Company claims $5,640.13 of these moneys, besides interest, by virtue of its two warrants of attachment.
The plaintiff claims that it is entitled to the entire amount paid by the city to the .surety company by virtue of its assignments from Long, and that the payments to the surety company were wrongful and in violation of its contract.
The plaintiff’s claim based upon the assignment contained in the application may first be considered. Before the enactment of the statute now embodied in sections 15 and 16 of the Lien Law, an assignment of moneys due upon a building contract took precedence over the statutory liens of those furnishing labor and material. Bates v. Salt Springs National Bank, 157 N. Y. 322. This situation, with its hardship to this class, was altered by the enactment of the statutes now embodied in the sections of the Lien Law referred to. These sections each provide, the latter in relation to contracts for public improvements, and the other for other improvements, that no assignment of a contract
The assignment to the plaintiff was never filed in the offices specified in section 16 of the Lien Law, and if that section is available to the plaintiff, no right can be claimed by the surety company by virtue of its earlier assignment.
The language of the opinion of the Court of Appeals in Edison Electric Illuminating Co. v. Frick Co., 221 N. Y. 1, must be followed by this court. It was there stated that section 15 of the Lien Law (which in this respect is similar to section 16) was enacted for the protection of a definite class, namely, laborers and material men, and it was there held that it could not be taken advantage of by a judgment or attaching creditor.
The funds advanced by the plaintiff to the contractor in this case are not shown to have been used by the contractor in performing any part of his contract, and the plaintiff, for all that appears, had nothing whatever to do with the city hospital contract. It claims no equity in that respect. It does not come within the class for whose benefit the statute was enacted, as authoritatively determined in the Edison case. The plaintiff urges that the decision in the Edison case relates only to judgment and attaching creditors and not to assignees, and that the language in Armstrong v. Chisolm, 99 App. Div. 465, which case is cited in the Edison case, would include assignees, as well as those furnishing labor and materials, within its protection. But the language in Armstrong v.
Even if what has been said were not so, the defendant’s claim must be sustained upon the doctrine of subrogation. If the city had, itself, completed the contract and made the same payments that the surety company made, there would have been nothing to which the plaintiff’s assignment could attach. When the surety company, pursuant to the obligation of its bond, completed the contract and made the payments to lienors, instead of the city doing so, it stood in the city’s place. Federal Heating Co., Inc., v. City of Buffalo, 182 App. Div. 128, 138.
The case of First National Bank v. City Trust, Safe Deposit & S. Co., 114 Fed. Repr. 529, is in all respects similar to the case at bar.
While the decision in Prairie State Bank v. United States, 164 U. S. 227, is not strictly in point, because the controversy there was between the surety on the contractor’s bond and an assignee of the contractor whose assignment as such was invalid under the statute, but who claimed an equitable lien because the money which he advanced went into the performance
The authorities which are uniformly in accord with the position here taken (except those from the state of Washington as to moneys already earned by, and payable to, the contractor before the surety takes over the contract) are collected in two notes contained in 14 L. R A. 457, and 1918-A. L. R. A. 937.
Edison Electric Illuminating Co., supra, is a conclusive authority against the contention of London Guaranty and Accident Company. The complaint must, therefore, be dismissed, with costs.
Complaint dismissed, with costs.