delivered the opinion of the court:
Plaintiff Merchants Environmental Industries, Inc. (MEI), appeals from an order of the circuit court of Cook County granting summary judgment in favor of defendants SLT Realty Limited Partnership (SLT) and Iron Mike’s, L.L.C. (Iron Mike’s). In the order appealed from, the court granted summary judgment as to counts I and II of MEI’s amended complaint for foreclosure of a mechanic’s lien in the amount of $219,317.75. Pursuant thereto, the court entered the necessary Supreme Court Rule 304(a) (134 111. 2d R. 304(a)) finding to make its ruling immediately appealable. MEI argues on appeal that summary judgment was improper because there were triable issues as to whether its notice of lien and recording of lien were timely, and whether a waiver of lien filed in August 1997 operated to waive MEI’s lien rights. For the reasons set forth below, we affirm the granting of summary judgment as to
BACKGROUND
On May 13, 1998, MEI filed its amended complaint for foreclosure of mechanic’s lien and other relief against SLT, Iron Mike’s, Tom Gold Construction Company (Gold), MS Tremont, L.P (Tremont), and several other defendants. MEI аlleges that in October 1996 Iron Mike’s leased part of the premises at 100 East Chestnut in Chicago, Illinois (also known as the Tremont Hotel), to be used as a restaurant. At that time the owner of the premises was Tremont, but SLT subsequently became the owner (allegedly on April 8, 1997), and the Iron Mike’s lease was transferred to SLT, which then became the successor landlord. 1 Prior to that purchase, while Tremont was still the owner, MEI alleges that End Zone Enterprises, Inc., the manager of Iron Mike’s, contracted with Gold to act as general contractor in the construction of space in the hotel premises to house Iron Mike’s restaurant. At about the same time (November 1996), MEI avers that it entered into a subcontract with Gold to perform heating, ventilation, and air conditioning (HVAC) work in the Iron Mike’s project for the sum of $115,000.
MEI further alleges that, at the specific request of Gold and the premises owner, it furnished additional duct work, equipment and piping for the project, and that the total amount due for those extras was $210,323.42. According to MEI, as of August 29, 1997, it had completed all work required under the subcontract plus all extra work requested. MEI avers that it has received payments of $106,005.67, leaving a balance due of $219,317.75, which MEI asserts has not been paid despite frequent requests. Therefore, MEI claims a mechanic’s lien on the premises plus “the materials, fixtures, apparatus and machinery furnished by it[,] and upon the moneys or other considerations due or to become due from the Owner to [Gold] for said amounts due the Plaintiff.”
MEI alleges that its notice of mechanic’s lien claim of subcontractor, dated November 6, 1997, was sent within 90 days after its completion of all work and delivery of all materials and thus was timely. In addition, MEI avers that its subcontractor’s claim for lien, recorded December 17, 1997, was timely filed within four months after completion of all work and delivery of all materials.
In count I of the amended complaint, which is designated “Action to Foreclose on Mechanics’ Lien,” MEI seeks execution of its mechanic’s lien “for whatever sum shall be found due *** including statutory interest from August 29, 1997, and its costs herein.” Alternativеly, in count II, designated “Action Against Owner and Contractor Jointly Pursuant to 770 ILCS 60/28,” MEI seeks judgment jointly and severally against SLT and Gold for $219,317.75 plus statutory interest and costs. 2
Attachments to the amended complaint include a copy of the above-mentioned subcontract between Gold and MEI, dated November 22, 1996; a copy of MEI’s notice of mechanics’ lien claim of subcontractor, dated November 6, 1997; and a copy of MEI’s subcontractor’s notice and claim for lien, recorded December 17, 1997.
SLT filed a motion for summary judgment on March 16, 1999, alleging that a waiver of lien to date executed by MEI on August 29, 1997, waived any of MEI’s mechanic’s lien rights up to and including
Attached to the motion is a copy of MEI’s August 29, 1997, “Waiver of Lien to Dаte,” which states that, in consideration of a payment of $31,938, “the receipt whereof is hereby acknowledged,” MEI
“do(es) hereby waive and release any and all lien or claim of, or right to, lien, under the statutes of the State of Illinois, relating to mechanics’ liens, with respect to and on said above-described premises [Iron Mike’s, 100 East Chestnut Street], and the improvements thereon, and on the material, fixtures, apparatus or machinery furnished, and on the moneys, funds or other considerations due or to become due from the owner, on account of labor services, material, fixtures, apparatus or machinery, furnished to this date [August 29,1997] by the undersigned [MEI] for the above-described premises.”
In addition, the “Contractor’s Affidavit” attached to the waiver states that “all waivers are true, correct and genuine and delivered unconditionally and that there is no claim either legal or equitable to defeat the validity of said waivers.” The affidavit also lists the total contract price (for both plumbing 3 and HVAC work) as $450,120.95, the amount already рaid as $198,835, an amount ($31,938) designated as “this payment,” and the “balance due” as $219,347.95, which is the amount claimed in MEI’s amended complaint.
In support of its allegation that MEI’s lien claim was not timely filed, SLT attached an index of MEI time sheets for the Iron Mike’s project that was included in a report by Joseph Manzi, described by SLT as MEI’s “opinion witness.” The last week listed in that index is the week ending May 13, 1997. SLT also attached what it terms “the very last time sheet of any sort produced by the Plaintiff’ (emphasis in original), which is for the week ending July 29, 1997 (not August 29, 1997). One of the entries on that time sheet shows two hours of work on July 25, 1997, and SLT claims that entry is the only one bearing one of MEI’s project numbers for the Iron Mike’s project. However, that entry states the address as “200 Adams,” which is not the address of the Iron Mike’s property.
In further support of its untimeliness allegation, SLT attaches an MEI invoice to Gold dated June 3, 1997, stating that it is the “[fjinal billing” for the 100 East Chestnut project. The invoice also notes that “this bill does not reflect any change orders that may be in process.” Under the HVAC portion of the June 3 invoice, the аmount of “Work Completed To Date” is shown as $325,335, which is slightly more than the $325,323.42 total amount for subcontract work and extras asserted by MEI in its (subsequent) amended complaint. The invoice also shows “.00” after “Balance to Complete.” Also attached to the summary judgment motion is a letter from MEI to Gold dated July 1, 1997, which refers to the June 3, 1997, bill as “our final invoice for the work completed on the Iron Mike’s Restaurant project.” The letter states that, “[d]ue to the amount of our final payment request, we cannot wait beyond our 30 (thirty) day invoice terms,” adding that MEI has “no choice but to protect our lien rights.”
On March 29, 1999, Iron Mike’s filed its motion for summary judgment, raising the same waiver defenses that SLT did. Iron Mike’s also alleged that MEI’s notice of
In further support of its untiméliness аllegation, Iron Mike’s submitted graphs from the previously mentioned Manzi report, one of which shows labor for the HVAC subcontract, including changes, ending no later than May 4, 1997. Another of the graphs shows the HVAC work ended during the week of August 3, 1997. Iron Mike’s notes that even if the work were completed on that date, it would still be too early for the November 6, 1997, lien notice to have been timely. Also included in the submissions are two MEI time sheets, one allegedly showing that the Iron Mike’s work was finished on May 8, 1997. The other is the same July 29, 1997, time sheet that was included in SLT’s motion.
Finally, Iron Mike’s submitted what it termed Gold’s “last contractor’s sworn statement” indicating a balance due to MEI of $31,938, which is the same amount stated in MEI’s August 29, 1997, “Waiver of Lien to Date.” Iron Mike’s also submitted a copy of its check dated October 17, 1997, payable to MEI for that amount: $31,938.
In its responses to the summary judgment motions, MEI asserted that its last day of work on the project was August 29, 1997, when it installed eight ceiling air diffusers in the first-floor kitchen of the restaurant. MEI therefore averred that both its November 6, 1997, notice of lien claim and its December 17, 1997, recоrded lien were timely filed. MEI also alleged that its August 29, 1997, waiver of lien to date does not bar its lien claim because neither SLT nor Iron Mike’s relied upon that waiver as a final waiver of lien.
In support of its responses, MEI submitted an affidavit of Al Kupsik, MEI’s project manager on the Iron Mike’s project. In that affidavit, Kupsik stated that it was MEI’s standard practice to send out a “final” bill before work was completed on a project. “Due to its years in business, MEI is able to determine what it will take to complete the work on a project, and so it prepares a ‘final’ bill although MEI is still on the project. That is what happened on the Iron Mike’s project.” According to Kupsik, “[i]n June, 1997, when the June 3, 1997[,] ‘final’ bill was sent to Tom Gold, MEI still had to install eight (8) ceiling grills in the first floor kitchen.” Kupsik said MEI had expected to be able to install those grills around the time of the June 3 “final” bill but that Iron Mike’s kept rescheduling the work. He said the grills were finally installed on August 29, 1997, adding that those installations “were part of MEI’s base contract work.”
Kupsik also stated in the affidavit that when MEI’s first waiver of lien to date (dаted November 6, 1996) was submitted to Gold, all parties were alerted that the waiver was subject to any pending change orders. He said payment to MEI of $20,160 pursuant to that first waiver of lien to date “was authorized on the basis of the November 6, 1996[,] lien waiver which clearly indicates it does not accurately reflect MEI’s full up-to-date subcontract price.” Kupsik said the same thing about MEI’s second waiver of lien to date for $178,675, dated December 31, 1996.
Kupsik averred that prior to the August 29, 1997, waiver of lien, which was actually submitted on October 20, 1997 (and apparently backdated to August 29), there had been correspondence with Gold and meetings between MEI, Gold and Iron Mike’s “regarding MEI’s claim for additional work under the HVAC contract.” He said that during a meeting on September 29, 1997, “MEI advised, and Iron Mike’s acknowledged, that other money was due and owing to MEI.” Kupsik added that “[ajfter the August 29, 1997[,] waiver of
In support of that last statement, the Kupsik affidavit included a copy of an undated documеnt on Iron Mike’s Grille letterhead addressed to MEI, stating that: “Pursuant to the discussion between Joe Priola [of Iron Mike’s] and A1 Kupsik, it is understood that all invoices are in dispute. The enclosed $31,938 [the amount stated in the August 29, 1997, waiver of lien to date] does not release MEI from any part of the ongoing dispute.” In a handwritten addition, it was noted that neither “Tom Gold Construction [n]or End Zone Enterprises” was released from the dispute as well. The document was signed by both Priola and Kupsik. Also attached to the affidavit was a work ticket dated August 29, 1997, indicating that two men worked eight hours each at Iron Mike’s on that date installing “supply air diffusers in kitchen on 1st floor.”
Other submissions accompanying MEI’s responses included copies of the previously mentioned November 6, 1996, and December 31, 1996, waivers of lien to date, along with copies of a check from Iron Mike’s dated December 12, 1996, for $20,160 (the amount stated in the first waiver) made payable to MEI, and a check from Ticor Title Insurance Company (drawn on Iron Mike’s account) dated January 13, 1997, for $178,675 (the amount of the secоnd waiver) made payable to MEI.
On June 29, 1999, the trial court granted SLT’s and Iron Mike’s motions for summary judgment as to counts I and II of the amended complaint. The court found that although the eight ceiling grills were not installed until August 29, 1997, MEI had “substantially completed its contract work at IRON MIKE’S GRILL [sic]” as of June 3, 1997. 4 The court found further that “[although the installation of the eight ceiling grills in the kitchen was part of plaintiffs base contract work, it involved minor matters better characterized as ‘trivial work.’ ” Thus the trial court found that MEI’s notice of lien, dated November 6, 1997, and its lien claim, recorded December 17, 1997, were untimely, and MEI’s mechanic’s lien therefore was not enforceable against SLT or Iron Mike’s. The instant appeal followed.
DISCUSSION
On appeal, MEI argues that there are genuine issues of material fact as to when MEI completed its work on the project and thus contends that there are triable issues as to whether its noticé of lien and lien claim were timely. Hence, MEI argues that summary judgment was improper. MEI also argues that its August 29, 1997, lien waiver does not offer an alternative bаsis for affirming summary judgment because there are triable issues as to whether SLT and Iron Mike’s reasonably relied upon that lien waiver in making payment.
A. The Timeliness Issue
MEI asserts that the last date it performed work on the Iron Mike’s project was August 29, 1997, when it installed eight ceiling grills in the restaurant’s first-floor kitchen. MEI also argues that, contrary to the trial court’s ruling and the defendants’ contentions, that work was not trivial and therefore established August 29 as the completion date. The defendants question whether' any work was done on August 29, 1997, and if so, whether it was included in the work for which MEI claims a mechanic’s lien. They also argue that if work was done on August 29, it was trivial and therefore did not serve to extend the completion date.
Under section 24 of the Mechanics Lien Act (Act), a subcontractor must file a notice of lien claim within 90 days after “completion” of his work in order for the
“Sub-contractors, or party furnishing labor or materials, may at any time' after making his or her contract with the contractor, and shall within 90 days after the completion thereof, or, if extra or additional work or material is delivered thereafter, within 90 days after the date of completion of such extra or additional work or final delivery of such extra or additional material, cause a written notice of his or her claim and the amount due or to become due thereunder, to be sent by registered or certified mail, with return receipt requested, and delivery limited to addressee only, to or personally served on the owner of record or his agent or architect, or the superintendent having charge of the building or improvement and to the lending agency, if known ***.” 770 ILCS 60/24 (West 1992).
Thus the notice must be sent within 90 days after completion of the furnishing of labor or materials. MEI’s notice of mechanic’s lien claim, dated November 6, 1997, was sent to Tremont, SLT, Gold, Iron Mike’s, and Iron Mike’s in care of End Zone Enterprises.
Another requirement in the Act applies to actions against third-party purchasers such as SLT. In order for the mechanic’s lien to be enforceable against such a party, either a suit must be filed or the lien claim itself must be recorded within four months after “completion” of the work. This requirement “is a condition of liability itself and not just a limitation on the remedy.” Waldbillig Woodworking, Inc. v. King Arthur’s North, Ltd.,
“No contractor shall be allowed to enforce such lien against or to the prejudice of any other creditor or incumbrancer or purchaser, unless within 4 months after completion, or if extra or additional work is done or material is delivered therefor within 4 months after the completion of such extra or additional work or the final delivery of such extra or additional material, he or she shall either bring an action to enforce his or her lien therefor or shall file in the office of the recorder of the county in which the building, erection or other improvement to be charged with the lien is situated, a claim for lien, verified by the affidavit of himself or herself, or his or her agent or employee, which shall consist of a brief statement of the contract, the balance due after allowing all credits, and a sufficiently correct description of the lot, lots or tracts of land to identify the same.” 770 ILCS 60/7 (West 1992).
Hence, in order for MEFs lien claim to be enforceable against a third party such as SLT, it must have been filed within four months after completion of the work. MEFs lien claim was recorded on December 17, 1997.
If the completion date were August 29, 1997, as MEI claims, then both its notice and lien claim would be timely under the Act. In that regard, the defendants first question whether any work was done on that date, pointing to MEFs billing records and the previously mentioned Manzi report dealing with MEI’s contract performance on the Iron Mike’s project. MEI’s June 3, 1997, invoice to Gold states that it is a “[f]inal billing to provide the necessary labor, material, equipment, tools and supervision to install all of the associated duct-work, gas piping and all H.VA.C. work as well as pеrform the plumbing work.” The June 3 invoice lists under the HVAC portion a total of $325,335 as work completed to date, which is essentially the same as the $325,323.42 HVAC total claimed in MEI’s amended complaint, indicating
The foregoing notwithstanding, we believe that MEI has at least raised a genuine issue of material fact as to whether the ceiling grill work was performed on August 29, 1997. Included in MEI’s submissions in response to the summary judgment motions is a work ticket dated August 29, 1997, indicating that two workers spent eight hours each on that date completing installation of “air diffusers in kitchen on 1st floor” at Iron Mike’s. The air diffusers are also described as “grilles & registers” on the work ticket. In addition, Kupsik’s affidavit states that it is MEI’s “standard practiсe” to send a “final” bill before work is completed on a project. He asserts that such a practice was followed on the Iron Mike’s project, adding that in June 1997, when the June 3, 1997, “final” bill was sent to Gold, “MEI still had to install eight (8) ceiling grills in the first floor kitchen.” He said MEI had expected to be able to install those grills around the time of the June 3 bill but that Iron Mike’s kept rescheduling the work. According to Kupsik, the grills were finally installed on August 29, 1997, as “part of MEFs base contract work.” Kupsik’s affidavit and the August 29 work ticket support a reasonable inference that the ceiling grill work was included in the June 3, 1997, invoice but was not completed until August 29, 1997. The trial court also found that the ceiling grills were installed on that date. Therefore, we find that, at minimum, a genuine issue of material fact exists as to whether the work in question was performed on August 29, 1997.
Even if the work were performed on that date, SLT argues that it was not included in the work for which MEI claims a lien and thus MEI’s lien claim was untimely recorded under section 7 of the Act as to it. “ 1 “[C]ompletion ” as used in section 7 does not refer to completion of the contract. It means completion of the work for which a contractor seeks to enforce his lien. [Citation.]’ [Citation.]” D.M. Foley Co. v. North West Federal Savings & Loan Ass’n,
MEI also argues that the trial court erred when it found that the work done on August 29, 1997, was trivial and thus did not extend the completion date to August 29. MEI contends that there is evidence the work was not trivial and thus there is a triable issue as to whether August 29 was the completion date. We find that argument persuasive.
Under Illinois law, “[w]ork that is trivial and insubstantial, and not ‘essential
Another factor in determining whether work is trivial is whether it was done at the request of the owner. See Alexander Hendry Co. v. Mooar,
In the instant case, the work involved was not a repair or a correction, nor can it be described as maintenance of completed work. Kupsik states in his affidavit that the installation of eight ceiling grills by MEI at Iron Mike’s on August 29, 1997, was “part of MEI’s base contract work.” Kupsik also states that the installations had been rescheduled repeatedly by Iron Mike’s, which is why they were not completed until six months after the restaurant opened in February 1997. That supports a reasonable inference that the August 29, 1997, work was done at the request or demand of Iron Mike’s. In rescheduling the work, Iron Mike’s was in effect stating that they did not want it done at a previously scheduled time but they did want it done at the new time.
Defendants argue that the August 29, 1997, ceiling grill installations should be seen as trivial because they were not necessary to make the building operable or suitable for its intended use. We disagree. As already indicated, while suitability for intended use may be one factor in determining whether work is trivial, it is not the only one. It exists side by side with other factors, including whether the work was requested by the owner and whether it
In support of their suitability argument, defendants attempt to rely upon Du Page Bank, but their reliance is misplaced. In Du Page Bank, the contractor entered into a contract with a property owner in May 1979 to build a rеstaurant. The contractor’s work appeared to be completed on June 25, 1980, but on October 30, 1980, he had a plumber move vent stacks at the request of the owner. The original location of the stacks had resulted in a serious ventilation problem in the restaurant. According to the contractor, he was obligated under the contract “to remedy the defect as a part of his requirement to perform in a good and workmanlike manner.” Du Page Bank,
Du Page Bank does not stand for the proposition that defendants assert. Though suitability for intended use was a factor in the court’s decision, it was not the only one. The court in Du Page Bank also noted that the moving of the vent stacks was substantial, was done at the request of the owner, and was required to complete the contract. As previously noted, in the instant case it is reasonable to infer that MEI’s ceiling grill installations were done at the request of Iron Mike’s and were required to complеte the contract. Further, the work at issue in Du Page Bank, unlike the ceiling grill installations in the instant case, was corrective or remedial in nature and thus under ordinary circumstances would not have been substantial enough to extend the completion date. See Miller Bros.,
Defendants also rely upon De Anguera v. Arreguin,
Moreover, any argument suggesting that only operability or suitability determines whether work is trivial is undercut by Capital Plumbing, to which we have previously referred. In Capital Plumbing, the plaintiff had subcontracted to provide “certain ornamental metal work and air-conditioner stands” for an apartment building that was being constructed.
For the foregoing reasons, we find that MEI has at minimum raised a genuine issue of material fact as to whether its installation of eight ceiling grills on August 29, 1997, was substantial enough to warrant extension of the completion date to August 29. If August 29, 1997, were the completion date for the contract, then MEI’s notice of lien and lien claim would be timely. Hence, there is a triable issue as to whether those lien filings were timely, and summary judgment on that basis was improper.
B. The Lien Waiver Issue
MEI also argues that its August 29, 1997, lien waiver does not offer an alternative basis for affirming the trial court’s granting of summary judgment. MEI contends that there are triable issues as to whether SLT and Iron Mike’s reasonably relied upon that lien waiver as a final release of MEI’s lien claims. If there was no such reliance, MEI argues, then the lien waiver did not function as a final release. Defendants argue initially that because the August 29, 1997, lien waiver is clear and unambiguous, extrinsic evidence as to reliance cannot be considered. We disagree.
“Generally, where the terms of a waiver of lien are clear and unambiguous, extrinsic evidence which varies from or contradicts such terms cannot be considered in order to determine the intent of the parties ***.” Premier Electrical Construction Co. v. La Salle National Bank,
The question of whether there has been innocent reliance in this instance depends upon whether there was a good-faith belief that the August 29, 1997, lien waiver represented a full release of MEI’s lien rights for all work up to that date. MEI contends there was no such belief and that the parties never interpreted MEI’s waivers of lien (to date) in that manner; instead, the waivers were viewed as applying only to the work being paid for at the time they were submitted. Hence, the question becomes whether custom or usage would be helpful in determining how the waivers of lien to date were viewed by the parties. If so, it should be considered, and we think that it should. “Proof of custom or usage is intended as an aid to the interpretation of the intent of the parties at the time the contract was made.” Chicago Bridge & Iron Co. v. Reliance Insurance Co.,
Defendants argue that extrinsic evidence should not be considered, relying uрon Country Service & Supply Co. v. Harris Trust & Savings Bank,
Defеndants note that the lien waivers in Country Service used essentially the same language as those in the instant case. They argue that, just as in Country Service, the lien waivers here are unambiguous and no extrinsic evidence should be considered to determine the intent of the parties. However, Country Service is distinguishable from the case at bar. In Country Service, the defendant submitted affidavits asserting in essence that there was innocent and good-faith reliance on the waivers as complete releases of lien rights. In addition, the plaintiff in effect conceded that there was such reliance on the part of the lender. Here, defendants have submitted no affidavit asserting that there was good-faith reliance, and MEI has not acknowledged that there was such reliance.
Defendants’ reliance upon Miller Bros, also is unavailing. In Miller Bros., the plaintiff filed a complaint to foreclose a mechanic’s lien. Among the evidence before the trial court was a partial waiver of lien executed by the plaintiff stating that in cоnsideration of a payment of $56,851.23, the plaintiff waived and released its lien rights up to January 18, 1967, the date of the waiver. Affidavits were submitted by the plaintiff and by Thomas Cooper, the president of a company that had been a defendant but was subsequently dismissed, stating that “both parties understood that there was a substantial balance owed Miller Bros, on January 18 and that the waiver was partial only and was not intended, despite its language, as a complete waiver for all work done to that date.” Miller Bros.,
As they did with Country Service, defendants argue that here, just as in Miller Bros., the waivers of lien were unambiguous and should not be supplemented with extrinsic evidence. However, Miller Bros. also is distinguishable from the instant case. First, Miller Bros, does not even address the question of good-faith, innocent reliance, which is the central issue here. That is probably because, having been decided in 1969, it came before the reliance issue was emphasized in Illinois lien waiver decisions. Compare, e.g., Premier,
For the foregoing reasons, we find that, in the instant case, extrinsic evidence may be considered as to whether there was such reliance. We turn then to evidence of usage or course of dealing between the parties suggesting that waivers of lien to date were not treated as final releases of lien rights. According to Kupsik’s affidavit, which must be construed strictly against the defendants and liberally in favor of MEI (Lackey & Lackey, P.C. v. Prior,
In addition, there is evidence which further suggests that the August 29, 1997, waiver was not seen as a full release. According to Kupsik’s affidavit, Iron Mike’s acknowledged that MEI’s invoices were still in dispute even after thе August 29, 1997, lien waiver was submitted (on October 20, 1997) to Gold. As noted above, attached to that affidavit is a document on Iron Mike’s Grille letterhead addressed to MEI stating that “it is understood that all invoices are in dispute.” Though the document is undated, the second sentence refers to the “enclosed $31,938,” which is the amount stated in the August 29, 1997, lien waiver and the amount of Iron Mike’s October 17, 1997, check to MEI. That evidence supports a reasonable inference that Iron Mike’s did not consider the August 29, 1997, lien waiver to be a full release of lien rights as to all amounts due for MEI’s work on the project up to that date. See Delaney Electric Co. v. Schiessle,
Lastly, and more overridingly, the Kupsik affidavit also states that prior to the August 29, 1997, lien waiver, there had been correspondence with Gold and meetings between MEI, Gold and Iron Mike’s regarding MEI’s claim for additional work under the HVAC contract. Kupsik also asserts that during a (September 29, 1997) meeting to discuss the additional work done by MEI on the HVAC contract, “MEI advised, and Iron Mike’s acknowledged, that other money was due and owing to MEI.” Again, we think that evidence, taken with the previously mentioned evidence, supports an inference that the defendants did not in good faith rely upon the August 29 waiver as a full release of MEI’s mechanic’s lien rights as to all work performed on the project up to August 29, 1997.
The case of Premier, which was previously discussed, is directly in point. In Premier, the plaintiff, an electrical subcontractor, sought foreclosure of a mechanic’s lien for electrical work it alleged had not been paid for. The trial court granted the defendants’ motion to dismiss on the ground that the plaintiff had executed a final waiver of lien, finding in favor of the defendants despite the plaintiffs allegation that, based upon customary practice between the parties, the defendants knew the lien waiver “was not intended to accurately reflect the full current subcontract price including all extras” (Premier,
Here, just as in Premier, the Kupsik affidavit listed previous instances where, based on customary practice betwеen the parties, MEI’s waivers of lien to date were not viewed as accurately reflecting MEI’s full, up-to-date subcontract price. However, unlike Premier, here there is no affidavit from defendants stating that they did in good faith rely upon MEI’s waiver. If anything, MEI’s argument as to good-faith reliance is stronger here than was the plaintiffs argument in Premier, where the court still found there were triable issues as to reliance.
Therefore, since the issue of whether there has been such innocent, good-faith reliance is a question of fact (Premier,
C. Completion Date
SLT argues separately that MEI’s lien claim is unenforceable against it because MEI’s section 7 lien claim did not contain a completion date.
5
Absent
The decision in Schmidt, upon which SLT principally relies, is most instructive. In Schmidt, the work at issue was done on four separate houses, and the lien claim was filed more than four months after completion of work on three of them but within four months of completion of the fourth house. Our supreme court reversed the trial court and found that the lien could not be enforced. In reaching that decision, the court noted that the lien claim “[did] not designate which portion of the work or material was furnished for any special house, nor the time when such work was performed or the material furnished for each house.” Schmidt,
MEI attempts to distinguish Schmidt from the instant case on the ground that Schmidt involved multiple properties with multiple completion dates, and here the lien claim was filed against a single property, Iron Mike’s restaurant. We find that argument unpersuasive. First, while Schmidt did deal with multiple properties, it required a completion date for each of them. Second, distinguishing on the basis of single property-multiple properties amounts to a distinction without a difference. If, as stated in Schmidt, a purpose
Therefore, for the reasons set" forth above, we affirm the trial court’s granting of summary judgment as to SET, but reverse it as to Iron Mike’s, and remand for further consideration in conformity with this opinion.
Affirmed in part and reversed in part; cause remanded.
COUSINS, P.J., and McBRIDE, J., concur.
Notes
Tremont subsequently moved to be dismissed as a defendant because it no longer had an ownership interest in the 100 East Chestnut premises and therefore was not a necessary party. The motion was granted on July 31, 1998.
Counts III and W designated “Action Against Contractor” and “Action for Quantum Meruit Against Contractor,” were not ruled on by the trial court and are not the subject of this appeal.
MEI also did plumbing work on the project, but it is only its HVAC work that is the subject of the amended complaint.
In the memorandum opinion and order, the date is stated as “June 3, 1999,” but that is undoubtedly a misprint.
This contention is made only by SLT and not by Iron Mike’s ostensibly because the argument has viability only to third parties such as SLT (as explained below) because section 7, pursuant to which this defense is interposed, applies only to third parties.
As noted above, SLT purchased the Tremont Hotel property after MEI entered into its subcontract with Gold to perform HVAC work in the Iron Mike’s project. SLT thus is a third-part; purchaser within the meaning of section 7, which by its terms applies only to third parties. The text of that provision, which is set out more fully earlier, begins: “No contractor shall be allowed to enforce such lien against or to the prejudice of any other creditor or incumbrancer or purchaser ***.” (Emphasis added.) 770 ILCS 60/7 (West 1992).
