Mercado v. TPT Brooklyn Associates, LLCMercado v. TPT Brooklyn Associates, LLC
Ordered that the order is affirmed insofar as appealed from, with costs.
The plaintiff commenced this action to recover damages, pursuant to Labor Law §§ 200, 240 (1), and § 241 (6), for injuries he allegedly sustained when a piece of ceiling collapsed and struck him while he was performing interior demolition work. The plaintiff subsequently withdrew his causes of action alleging a violation Labor Law § 240 (1). Thereafter, the owner of the property, the defendant TPT Brooklyn Associates, LLC, and the general contractor for the project, the defendant Great American Construction Corp. (hereinafter together the defendants), successfully moved for summary judgment dismissing the Labor Law §§ 200 and 241 (6) causes of action. We affirm.
The Supreme Court properly granted summary judgment dismissing the Labor Law § 200 cause of action because the plaintiff failed to offer any evidence to rebut the defendants’ prima facie showing that they did not supervise or control the demolition work, or the safety measures employed during that work (see Dennis v City of New York,
The Supreme Court also properly granted summary judgment dismissing the cause of action based upon an alleged failure to comply with Labor Law § 241 (6). In order to establish liability under Labor Law § 241 (6), a plaintiff must demonstrate that the defendant’s violation of a specific rule or regulation was a proximate cause of the accident (see Ross v Curtis-Palmer Hydro-Elec. Co.,