MENOMINEE INDIAN TRIBE OF WISCONSIN, Plaintiff-Appellant, v. ENVIRONMENTAL PROTECTION AGENCY and UNITED STATES ARMY CORPS OF ENGINEERS, et al. Defendants-Appellees, and AQUILA RESOURCES, INC., Intervening Defendant-Appellee.
No. 19-1130
United States Court of Appeals For the Seventh Circuit
ARGUED SEPTEMBER 5, 2019 — DECIDED JANUARY 27, 2020
Before SYKES, HAMILTON, and SCUDDER, Circuit Judges.
Appeal from the United States District Court for the Eastern District of Wisconsin. No. 1:18-cv-108 — William C. Griesbach, Judge.
Sometime before 2017, the Tribe learned that Aquila Resources intended to embark on a mining project known as the Back Forty alongside the Menominee River and in close proximity to Wisconsin‘s northeast border. Aquila successfully applied for several necessary permits from the state of Michigan. Concerned the project would disrupt and dislocate aspects of tribal life, the Tribe wrote letters to the Environmental Protection Agency and Army Corps of Engineers asking both agencies to reconsider its 1984 decision to allow Michigan, instead of the federal government, to issue certain permits under the Clean Water Act. The EPA and Army Corps responded not by revisiting the prior delegation of permitting authority but instead by informing the Tribe of what it already knew—that Michigan would decide whether to issue a so-called dredge-and-fill permit to authorize Aquila‘s Back Forty project.
The Tribe responded on two fronts—first by commencing an administrative proceeding in Michigan and second by filing suit in federal court in Wisconsin. The district court dismissed the Tribe‘s complaint on the ground that it did not challenge any final action taken by the EPA or Army Corps. The court also denied the Tribe‘s request to amend its complaint. Despite reservations about how the federal agencies responded to the Tribe‘s concerns, we affirm.
I
To open and operate the Back Forty mine, Aquila had to acquire several regulatory permits. The focus here is on Aquila‘s need for a dredge-and-fill permit, which comes under Section 404 of the Clean Water Act,
Section 404 regulation is not an entirely federal undertaking. Although the EPA and Army Corps are tasked with enforcing the Clean Water Act, Congress allows states to apply to assume Section 404 permitting authority over waters in their jurisdictions. See
When a state assumes permitting authority, the federal government is not removed from the Section 404 regulatory process altogether. The EPA maintains an oversight role reviewing state-proposed permits. See
Knowing that Michigan had received authority for dredge-and-fill permitting in 1984, Aquila directed its Section 404 application to Michigan‘s Department of Environmental Quality. The company‘s application, and the Back Forty
In August 2017 the Tribe expressed its concerns in letters to the EPA and Army Corps. The Tribe acknowledged that under the 1984 agreement between the EPA and Michigan, the state took over issuance of dredge-and-fill permits for many of the state‘s waterways, subject to the EPA‘s oversight preserved in the Clean Water Act. See
The Tribe also saw specific procedural and legal benefits to the dredge-and-fill permit being decided by the federal agencies. If the permitting had been handled in the federal system, the Tribe would have enjoyed more participation rights. For example, the National Environmental Policy Act would have applied and likely required the EPA to complete an environmental assessment or impact statement about the Back Forty mine. See
The agencies responded by reinforcing—but not revisiting—the 1984 delegation. For its part, the Corps explained that it could not exercise jurisdiction over the permitting process for the Back Forty mine because permitting for the relevant section of the Menominee River had been assumed by Michigan in 1984. One month later, the Tribe received a six-sentence letter from the EPA not at all addressing its concerns but offering to speak with the Tribe by phone. Neither response addressed the Tribe‘s request for the agencies to reconsider whether changed circumstances warranted the renewed exercise of federal authority over the relevant section
The federal lawsuit did not proceed very far. Aquila intervened in the action and joined the agencies in moving under
At the same time, the Michigan Department of Environmental Quality continued processing Aquila‘s Section 404 permit application. As required under its agreement with the EPA, Michigan submitted its proposed dredge-and-fill permit for Aquila‘s mine to the EPA for federal review. The EPA objected to the permit and asked Michigan for additional information. A few months later, the state submitted a new draft permit. Upon reviewing the new draft and Michigan‘s responses, the EPA withdrew its prior objections on the basis that its concerns had been alleviated. More specifically, the EPA allowed permitting to proceed if certain conditions were included in the final state permit. The state complied and granted Aquila the permit in June 2018. Shortly thereafter the Tribe challenged the permit in Michigan‘s administrative system. That case is still pending.
II
This appeal presents two questions—one narrow and one broad. The first is whether the agency action here is judicially
A
We begin with the narrow question, which returns us to the Tribe‘s complaint. The Tribe invoked the Administrative Procedure Act and alleged that the federal agencies’ decision not to exercise permitting authority over the dredge-and-fill permit for the Back Forty project was arbitrary and capricious and contrary to law. See
The APA limits judicial review to “final agency action[s].”
The district court applied this framework and concluded that the EPA and Army Corps‘s letters did not reflect any final agency decisions. We agree. The EPA and Corps‘s responses did little but restate what the Tribe already knew—that Michigan, as a result of the 1984 delegation, had permitting authority over the section of the Menominee River near the Back
The Tribe understandably will find this conclusion unsettling. Its letters to the EPA and the Army Corps were detailed and specific. The Tribe explained its basis for believing that the relevant part of the Menominee River should be under federal permitting authority. Neither the EPA nor the Corps accepted the Tribe‘s invitation to revisit the 1984 delegation decision in light of the changed commercial circumstances highlighted in the Tribe‘s letters. Indeed, neither agency responded in any way to that contention. This silence is particularly troubling since the agencies asserted for the first time at oral argument that the Tribe could have sought the requested relief by filing a petition for rulemaking under
Although we see nothing standing in the way of the Tribe‘s ability to file a
B
Even if we could somehow treat the agency responses as reflecting final decisions, our next step would be far from clear given parallel proceedings ongoing in Michigan. In addition to filing suit in federal court, the Tribe contested Aquila‘s Section 404 permit before the Michigan Department of Environmental Quality. To our knowledge that proceeding (which is called a contested case hearing) is pending before Michigan‘s Administrative Hearing System. See
Duplicative litigation in state and federal courts can cause coordination problems, interfere with effective government functioning, and lead to conflicting judgments. See, e.g., Colorado River Water Cons. Dist. v. United States, 424 U.S. 800, 817 (1976). The Tribe sees those concerns as overstated because it perceives the scope of the state proceedings to be narrow. It says that there will be no overlap between the state and federal suits because the state administrative proceeding will not entail an adjudication of Michigan‘s dredge-and-fill permitting authority under the Clean Water Act. For support, it notes that in denying a motion for a stay, the administrative law judge ruled on only state-law grounds.
But the administrative law judge has not yet reached a decision on the merits, and after that the Tribe may turn to the state court for relief. As the Tribe acknowledged in its letter to the EPA and the Corps, the definition of “navigability” is ultimately decided by the judiciary. See
III
The Tribe also challenges the district court‘s denial of its motion for leave to amend its complaint. The Tribe sought to add two Administrative Procedure Act claims—one contending that the EPA‘s withdrawal of its objections to Michigan‘s issuance of the permit was arbitrary and capricious, and a second alleging that the agencies failed to consult with the Tribe about the Back Forty mine as Congress required under the National Historic Preservation Act. The district court denied the motion on the basis of futility, reasoning that neither claim would survive a motion to dismiss. We review a denial of a motion for leave to amend for abuse of discretion, while considering any embedded legal questions de novo. See Gandhi v. Sitara Capital Mgmt., LLC, 721 F.3d 865, 868–69 (7th Cir. 2013).
A
To evaluate the Tribe‘s claim that the EPA‘s withdrawal of objections to Michigan‘s proposed permit was arbitrary and
The EPA originally objected to Michigan‘s proposed dredge-and-fill permit for Aquila‘s Back Forty project on multiple grounds and sought more information. Michigan submitted a revised permit and agreed to add additional conditions, including, for example, a requirement that Aquila monitor the effect of dust levels on nearby wetlands. Upon its second review, EPA concluded that its concerns were resolved and allowed the permit to go forward.
In the district court, the Tribe sought leave to amend its complaint to challenge the EPA‘s withdrawal of its objections to the permit that Michigan planned to issue to Aquila. The Tribe asserts that the EPA provided little to no explanation, rendering its decision arbitrary and unsupported. The district court, however, concluded that the proposed claim would fail (and therefore be futile) because the EPA‘s decision was exempt from judicial review as a matter of law. Specifically, the district court reasoned that the EPA‘s decision to withdraw its objections was “committed to agency discretion by law.”
The Supreme Court has explained that
When deciding whether a decision is committed to agency discretion, we first review the applicable statutes and regulations. See Head Start Family Educ. Program, Inc. v. Coop. Educ. Serv. Agency 11, 46 F.3d 629, 632 (7th Cir. 1995). We examine those measures to see if they contain “judicially manageable standards . . . for judging how and when an agency should exercise its discretion.” Heckler, 470 U.S. at 830; see also Miami Nation of Indians of Ind. v. Dept. of Interior, 255 F.3d 342, 348–49 (7th Cir. 2001) (examining regulations governing the tribal recognition process to determine if they contain criteria that “courts are capable of applying“).
The Tribe does not point to any regulations governing the withdrawal of objections. We searched too and came up empty, finding no statute, regulation, or guideline that instructs the EPA how to decide whether a state has tendered a satisfactory resolution to a previous permitting objection. The Tribe suggests that we fill the gap by looking to the regulations governing the decision to object in the first place. It notes that those regulations require that any objection “be based on the [EPA‘s] determination” that the proposed permit is “outside [the] requirements of the [Clean Water] Act, these regulations, or the 404(b)(1) Guidelines.”
We read the regulatory language another way, though. Remember that the language about objections is permissive, making plain that “[a]ny such objection” the EPA chooses to lodge must be based on certain prescribed factors.
The proper conclusion, then, is that, in the absence of any regulation addressing the basis for the decision to withdraw an objection, the choice is as committed to the agency‘s discretion as the decision to object in the first instance. If the EPA finds a shortcoming in the state‘s response to a particular objection, the agency must again make a judgment call about whether to maintain the objection. The decision may depend on many factors, including the EPA‘s judgment about not only the materiality of the concern that gave rise to the initial objection and the sufficiency of the state‘s responsive measures, but also whether the agency‘s limited time and resources are best used to persist with an objection pertinent to one project when others likewise call for federal attention.
A final and broader point is worth observing. The Clean Water Act‘s regulations allow the EPA to decline to review whole categories of state-issued dredge-and-fill permits through a blanket waiver program. See
B
The Tribe also sought leave to add another APA claim—that the EPA had failed to recognize the Tribe‘s consultation rights conferred by the National Historical Preservation Act. See
The Tribe reads the Preservation Act as obligating the EPA and Army Corps to consult with it about the Back Forty mine project. But that position is mistaken. The Preservation Act applies only to undertakings that are “[f]ederal or federally assisted.” Id.
The Menominee Indian Tribe of Wisconsin‘s sincere efforts to protect its cultural heritage ran into a legal labyrinth and regulatory misdirection. Had the federal agencies provided a meaningful response to the Tribe‘s concerns, perhaps this suit could have been avoided. But in light of the regulatory scheme that we cannot change, the resolution of this case is clear. We cannot review the agency action here. In these circumstances, the Tribe is left to pursue its challenge in the Michigan administrative system and state courts. And we are left to AFFIRM the judgment of the district court.
A delegation of Clean Water Act permitting authority to a state under
First, the Tribe may petition the EPA to reassume federal permitting authority over this stretch of the Menominee River as an amendment to a rule. See
If the Tribe submits such a petition, the EPA will have to answer within a reasonable time. See
Absent periodic review by the EPA, the scope of a Section 404 delegation to a state could quickly fall behind the times and out of legal compliance. This case illustrates that risk. As codified, the Michigan approval incorporated a Memorandum of Agreement signed in the spring of 1984 that retained just a small portion of the Menominee River under federal jurisdiction. See
A reassessment by the EPA to ensure that the scope of the Michigan delegation still complies with the Clean Water Act appears long overdue. I don‘t mean to criticize
The Tribe objects that the Michigan administrative law judge who is hearing the “contested case” has refused to address the questions of federal law, including a challenge to the scope of the federal delegation of permitting authority. See Order on Motion to Stay, Petitions of Thomas Boerner et al., No. 18-013058 at 2–3 (Mich. Admin. Hearing Sys. Jan. 29, 2019) (attached to Appellant‘s Br.). I express no view on the administrative law judge‘s refusal to consider the scope of the delegation as a matter of Michigan administrative law, but limits on the issues that administrative law judges may consider are not unusual. Whether the administrative law judge is right or wrong, however, should not affect the power of Michigan courts of general jurisdiction to address the issue.
If the Tribe seeks judicial review in a Michigan circuit court, see
For now, however, the EPA‘s 1984 delegation of authority over this stretch of the Menominee River to Michigan remains in effect. For that reason, we must affirm. The Tribe must ask the EPA, the Michigan ALJ, and Michigan courts to examine alleged infirmities in the Section 404 permit for the mine.
