136 Ga. 442 | Ga. | 1911
(After stating the fore’going facts.)
If'the jury should find from the attendant circumstances, that, at the time the vendee wrote to his vendors that he would not further perform his contract, 'a reasonable time had elapsed within which the vendors could have removed the encumbrances, then the failure of the vendors to remove the encumbrances from the land within such time would be an unreasonable delay, and the vendors’ dereliction in this .respect would be a breach of the contract. But if at the time the vendee wrote to the vendors that he would abandon the contract the vendors had not breached it,-in that they had a reasonable time after January 1, 1908; to remove the encumbrances on the land, which had not expired, the renunciation of the contract by the vendee, accepted by the vendors, would bar the vendee of an action for its breach. Where both parties to a contract abandon it, one can not recover for its breach by the other. Eaves v. Cherokee Iron Company, 73 Ga. 459.
It is true that the petition does not allege that a reasonable time had elapsed when the plaintiff notified the defendants of his intention to abandon the contract. It is a rule of pleading ■ that where time for the performance is not specified in an agreement, it should be averred that it was to be done within a reasonable time and that such reasonable time had elapsed when performance was required. Osborne v. Lawrence, 9 Wend. 135. But where all the facts of the case are pleaded, the failure to specifically denominate the time appearing from such facts to be a reasonable time does
Judgment reversed.