17 Pa. Super. 12 | Pa. Super. Ct. | 1901
Opinion by
The plaintiff had a contract with the county commissioners to construct a short piece of road forming the approach to a new bridge over the Susquehanna river at Bloomsburg. The work consisted almost wholly of filling in between the abutment of the bridge and the bank of the defendant railroad. The construction, thus contracted for, was to take the place of part of an old public road, called the Ferry road, which ran under the railroad, then parallel to the railroad embankment for a short distance and thence to a ferry landing. The plaintiff entered upon his work and drew the material to be used in the fill, from a point on the other side of the railroad, using the Ferry road and passing under the railroad bridge. This made but a short haul. He had proceeded thus but a few days when the railroad company, as he alleges, emptied several carloads of earth, old railroad ties, etc., over the side of their bridge, making the Ferry road wholly impassable and compelling the plaintiff to procure materials from a new source at a greater distance and at a greater cost. This conduct on the part of the defendant is alleged to be tortious, and to sustain the verdict rendered in favor of the.plaintiff.
The first proposition advanced by the appellants is, that the
The defendant company further claims that the measure of damages was the cost of the removal of the obstruction alleged to have been placed by the defendant company in the Ferry road to the injury of the plaintiff. The plaintiff admits, on cross-examination, that the cost of such removal would have been, perhaps, $5.00 or $6.00, but he also adds that he was warned by the representatives of the defendant company not to attempt to remove or level the obstruction, and notified that they would persist in maintaining the obstruction. We think the learned judge of the court below was right in his view of the measure of damages, based upon the case of Knowles v. Penna. R. R. Co., 175 Pa. 624. An obstruction in that case was placed in a public road by a railroad company. The plaintiff was hauling dirt and stone, under a contract, for grading and building purposes. By the obstruction the plaintiff’s cost of hauling was largely increased because of the necessitated change of route. This was held to be a loss beyond that suffered by him in common with all others affected by the nuisance. The court say: “ It is clear, therefore, that the plaintiff suffered material loss or damage by reason of the obstruction which was the original subject of complaint in this action.”
The defendant company claims that it had the right to obstruct the old Ferry road because it was on their right of way. The evidence is not conclusive that it was on their right of way. Evidence was submitted by the plaintiff showing that it had been a public road in public use for more than thirty years. The learned trial judge was right in saying that the rights of the defendant company over its right of way did not extend to interference with the public road, although at the time of its obstruction the road was inchoately vacated. The point of charge, which raised this question, might have been refused entirely. We cannot see that any injury was suffered by the defendant company in the explanatory answer made to the point.
Reference to the fact that an injunction was served upon the defendant company is found in the cross-examination of the witnesses for the plaintiff. The defendant company offered in
The defendant company complains that the court below, in charging the jury upon the matter of damages, referred to the amount claimed in the statement of claim, and that this is in violation of the rule laid down in Reese v. Hershey, 163 Pa. 258, in which the trial judge was reversed for reading the plaintiff’s statement to the jury, including the averment of damages. We do not think that the present case comes within the authority cited, although the stress of the opinion is there laid upon the reading of the amount of the damages claimed: Reel v. Martin, 12 Pa. Superior Ct. 345. The statement of claim, in this case, is not well drawn in that it claims a sum of money with interest from a given date. The action is in trespass. The amount of the verdict is approximately the aggregate of the amount of specific damages claimed, plus interest to trial. Interest cannot be recovered as interest, but interest may be allowed as damages: Penna., etc., R. R. Co. v. Ziemer, 124 Pa.-571. The evidence for the plaintiff, if believed by the jury, was sufficient to support a recovery of damages, but not in excess of the gross amount claimed in the statement. There was some testimony which tended to stimulate the jury to the giving of excessive punitive or exemplary damages. The trial judge in referring to the amount claimed as damages, was putting a limit and a check upon the jury. It did not have a tendency to “ get figures and amounts into the jury’s minds without evidence.” See Reese v. Hershey, supra. There was evidence in the case to warrant the recovery of exemplary damages, and the statement of claim setting forth the facts generally, was broad enough to let in the evidence: Kennedy v. Erdman, 150 Pa. 427. The testimony, if believed, warranted the finding that the stoppage of the Ferry road by the railroad company was intentional; that its purpose was to prevent the plaintiff from going forward with his work; and that the motive was the prevention of -a
There remains but one other question, namely, whether there was error in permitting the plaintiff to testify to statements made to him by Ridgely and Kromer. The first was the local supervisor of the railroad, and the latter the conductor of the gravel train. The former took his instructions, in regard to the dumping of the material by the railroad upon the public road, from the assistant engineer of the company. The declarations testified to by the plaintiff and others were when the defendant company’s representatives were engaged in obstructing the highway for the railroad company, and the conversations were held within a short distance of the work itself. The declarations were made by the representatives of the company for the doing of the particular work complained of: Baker v. Westmoreland & Cambria Natural Gas Co., 157 Pa. 600. We think that no error was committed in admitting the testimony.
We can find no reversible error committed and, therefore, the judgment is affirmed.