140 P. 130 | Utah | 1914
Joseph W. Mellen, the appellant, commenced this action against Vondor-Horst Bros., a corporation, hereafter called the contractor, and against the board of education of Salt Lake City, hereafter designated respondent, to recover the value of labor and material which it is conceded he performed and furnished the contractor for the construction of a certain school building for respondent, as hereinafter stated. Appellant also made the Fidelity & Deposit Company of Maryland, hereafter called surety company, a party to the action, but the court sustained the demurrer of the surety company to the complaint against it, and thus the surety company went out of the case. No service was obtained upon the contractor, which is a nonresident corporation of and absent from the State of Utah. It is not necessary to refer to the pleadings. The respondent and the surety company were represented by the same counsel in the court below. The facts are really quite simple and are not in dispute.
On or about November 2, 1908, the respondent entered into a written contract with the contractor whereby the latter agreed to erect and complete a certain school building in Salt Lake City for the agreed price of $Y1,000. One of the conditions of said contract was that said contractor should furnish a bond, as required by our statute, for the sum of $35,500, conditioned for the faithful performance of said contract, and the surety company executed and delivered the bond aforesaid. After the contract and the bond had been executed and delivered, the contractor in pursuance of said contract, employed the appellant to make the excavation for the basement of the school building and to furnish some sand and gravel, all of which was to be used, and which it is conceded was used, in the construction of said building, and which excavation and material is conceded by respondent to be of the value of $2148.45, and that all was used in
“The board of education of Salt Lake City, Utah, on the evening of the 6th day of April, 1909, at a regular session of said board passed a resolution terminating the employment of Vondor-Horst Brothers, a corporation, under that certain contract made and entered into by and between said Vondor-Horst Brothers, a corporation, with the said board on the 2d day of November, 1908, a copy of which resolution is herewith served upon you, together with a copy of the certificate of said architect made on said 6th day of April, 1909. The said board will therefore proceed in accordance with article five of said contract to complete the work included in said conti’act.”
The surety company on April 11, 1909, replied to said letter as follows:
“As surety upon the bond of said Vondor-Horst Bros, we hereby offer to undertake the construction and completion of the said Jefferson school in accordance with the terms and condition of the contract given by you to said Vondor-Horst Bros, and in accordance with the plans and' specifications referred to in said contract. We will place a reliable contractor upon the work and rush the same to completion. All payments specified in the Vondor-Horst contract shall he made to us (as) they become due and we will settle with the contractor A (Italics ours.)
On the 19th, two days thereafterp the respondent accepted the proposition of the surety company by adopting the following resolution:
The enjoyment of the contractor was terminated by respondent pursuant to certain provisions contained in the contract, which are as follows:
“Article 5. Should the contractors at any time refuse or neglect to supply a sufficiency of properly skilled workmen, or of materials of the proper quality, or fail in any respect to prosecute the work with promptness and diligence, or fail in the performance of any of the agreements herein contained, such refusal, neglect or failure being certified by the architects, the owner shall be at liberty, after three days’ written notice to the contractors, to provide all such labor or materials and deduct the cost thereof from any money then due or thereafter to become due the contractors under this contract; and if the architects shall certify that such refusal, neglect or failure is sufficient ground for such action, the owner shall also be at liberty to terminate the employment of the contractors for the work and to enter upon the premises and take possession, for the purpose of completing the work included under this contract, of all materials, tools and appliances thereof, and to employ any other person or persons to finish the work and to provide the materials therefor ; and in case of such discontinuance of the employment of the contractors they shall not be entitled to receive any further payment under this contract until such work shall be wholly finished, at which time, if the unpaid balance of the amount to be paid under this contract shall exceed all
The surety company, pursuant to the resolution, and with the consent of the respondent, and in accordance with the terms and condition of the contract entered into between the contractor and the respondent,. erected and completed said school building according to the plans a-nd specifications, and in doing so used the excavation made by appellant, and also used' the material furnished by him, and received from respondent certain payments in accordance with the terms of the contract. It also did some extra work for which it was allowed extra pay. The surety company, in completing said school building, however, expended considerable more money than the contract price, for which it has received nothing. While the building was in process of construction, and after the surety company had appropriated appellant’s labor and material, he, pursuant to Comp. Laws 1907, section 1400x, to which we shall refer hereafter, filed a claim with respondent for the amount claimed by him, and asked that his claim be paid out of the money due on the contract. In view of said ■claim, respondent withheld from the contract price approximately $4000, so that, in case it shall be held by the courts that appellant’s claim should be. paid out of the money due on the contract, such might be done without harm to respond■ent. The $4000 is still in the hands of respondent and is by it held until it is determined whether it is all to be paid to the surety company or part thereof to appellant in payment of his claim.
The district court, it seems, proceeded on the theory that in view that there was no privity pf contract between appel
“Any person partnership, 01; corporation who has done work or labor or furnished' materials to any principal contractor for the construction or repair of any public work of any character for any county, town, city, village or school district, may maintain an action therefor in the .county in which such work, labor, or materials were done or furnished, against such principal contractor and such county, town, city, village, or school district, jointly, for the recovery thereof ; but no judgment shall be rendered against any defendant therein, other than such principal contractor, for any amount greater than the amount due from it to such principal contractor at the time of the commencement of such action. Such county, town, city, village, or school district, when served Avith summons in any such action, may give notice thereof to such principal contractor, and on so doing need not further defend such action. On rendition of judgment in such action against such principal contractor, the court may also render judgment against such county, tOAvn, city, village or school district for the amount due from it to such principal contractor at the time of the commencement of such action, or for a sufficient amount to pay the judgment recorded against the principal contractor, and payment thereof shall discharge its indebtedness to. such principal contractor, in the amount so paid.”
The court therefore, dismissed appellant’s complaint and denied him any relief, and he apj>eals.
This case affords a striking illustration of both the justice and utility of such a construction. Here, notwithstanding the fact that the statute (Comp. Laws 1907, section 1952), pursuant to which the building contract was entered into, provides that the respondent is required to enter into a contract with a “responsible bidder,” it actually entered into a contract with a foreign corporation which, it seems, was hopelessly insolvent, if not at the time the contract was entered into, at least shortly thereafter. Moreover, this foreign corporation was one of which it seems appellant knew nothing, and with which it had no means of communicating, and of whose whereabouts, for some time before its employment under the contract was terminated, respondent-according to its own statements, knew nothing, and, for aught that is made to appear, never knew anything concerning its whereabouts thereafter. If, therefore, the respondent had no means of communicating with its own contractor, which it, tacitly at least, held out as being financially and otherwise responsible by awarding the contract to it, why should a claimant under the statute be compelled to obtain personal service upon such a contractor before he may have recourse to the fund in the hands of respondent which remained unpaid on the contract price of the contract under-which the claimant furnished the materials and performed the labor, all of which was used in the building which was constructed under the contract ? Again, for aught that appears here, the insolvent condition of the contractor may have resulted in a dissolution of that- corporation. In view of all these contingencies, which may arise in any case, we do not think it was contemplated by the statute that a claimant should be required to obtain personal service upon a nonresident defaulting, and, perhaps, defunct corporation before the former can be given any relief against the fund in the hands of the owner of the building constructed under the contract. It abundantly appears from this record that appellant could not obtain personal service upon the contrac
Assuming, however, that respondent had completed the building, the surety company would have been liable on its bond only for the excess over the contract price, if any, that respondent would have been compelled to pay to complete the building in accordance with the terms of the contract ; and, if a new contract had been let, then for the difference, if any, between the contract price of the new contract and the old contract price, if the former was in excess of the latter. In the latter event the respondent would, under the ■statute, again have been required to obtain a new bond for the faithful performance of the second contract, and the surety company could safely have paid the difference, if any, as above indicated, and then would have been discharged from all obligations under its bond. If, however, new bids had been called for, there would have been an entirely new ■contract, and no doubt, under such circumstances, in view of the stipulations in the first contract, which would have been entirely abandoned by all the parties, the appellant’s only remedy would have been against the contractor. In view of what was done, however, the contract in question was not abandoned at all, but was kept alive, and its terms and conditions were performed by the surety company instead of by the contractor. In performing them (that is, in constructing the building), the surety company appropriated and used materials and labor which had been obtained for ■the purpose of completing the contract, but which had not been paid for by the contractor. So long as the surety company merely sustained the relation of a surety, and so long as it claimed neither part nor share in the fruits arising out of the contract, it could say: “I am under no obligation to pay for materials or labor furnished my principal, since I did not undertake to do so.” How can it now claim that no one can prefer any claim against the fund in the hands of respondent for labor and materials which the surety com
That the contract in question, under the circumstances, was not abandoned is, we think, made quite clear in the following cases; Murphy v. Buckman, 66 N. Y. 297; Crawford v. Becker, 13 Hun (N. Y.) 375; Gillen v. Hubbard, 2 Hilt. (N. Y.) 303.
If we pass now to a consideration of the case upon general principles of law and equity, we again arrive at the conclusion that the surety company, under the peculiar facts and circumstances of this case, cannot successfully claim the entire fund as against appellant’s claim. While the law is well settled that, under a contract and bond such as were entered into between the contractor and respondent and between it and the surety company, the latter was not liable on the-bond for any materials or labor not paid for by the contractor, although the same was used in the building, yet it seems such is not the law where, as here, the bondsman steps into the shoes of the defaulting. contractor and assumes the performance of the contract. The law in that regard is tersely, and we think correctly, stated in 6 Cyc. 83, in the following words:
“On default of the builder (contractor), in cases where the contract requires him to pay for all labor and material furnished, a right of action directly against the sureties accrues to unpaid laborers, materialmen, and subcontractors; in the absence, however, of the provision the sureties are not liable, unless they have completed the building on his default, and under an agreement with him collected the price from the owner.”
We have already called attention to the fact that the surety company insisted that the whole contract price should be paid to it. Such was done with the exception of the $4000
The case does not proceed upon an express contract, but it proceeds upon one implied by law, which arises out of the fact that one has voluntarily assumed to complete a certain contract for his own protection, and in doing so has invaded the property rights of another, and the law thus provides a remedy. In the case at bar the surety company not only appropriated the material for its own benefit, and did so to complete the contract of another, but it did so with the express provision that it assumed to perform all the conditions of such contract. The surety company insisted upon receiving the fruits of such contract, and in return for this it also assumed all of the obligations and conditions arising out of the same. One of the conditions imposed by our statute upon such contracts was that the value or price of the material furnished by any one for the construction of a public building might be claimed by the person furnishing the material out of the contract price to be paid to the contractor. If the value of the material thus could have been withheld
In view of the conclusions reached by us, we have not deemed it necessary to allude to any other of the assignments of appellant. None of the errors alleged can arise again, and for that reason we need ' not refer to them specially.
Although this is an equity case where, under ordinary circumstances, we would be empowered to enter a judgment here, yet, in view that the suerty company has not had an opportunity to litigate the reasonableness of appellant’s claim against the fund in question because it was not a party to the action, we deem it but fair and just to remand the cause.
The judgment or decree dismissing appellant’s complaint is therefore reversed, and the cause is remanded to the district court of Salt Lake County, with directions to set aside its findings of fact and conclusions of law, to reinstate the