*589 Opinion
1. Introduction
Plaintiff Melchor Investment Company (lessor) purports to appeal from the denial of its request to preliminarily enjoin arbitration jointly requested by defendant Rolm Systems (sublessee) and defendant International Business Machines Corporation (sublessor). Lessor claims it is not required to submit to an arbitration demand by sublessee because the lease’s arbitration provision is inapplicable and they have no other arbitration agreement. For the reasons stated below, we will dismiss this matter as nonappealable.
2. Facts
On April 14, 1976, lessor entered into two substantially identical written agreements (collectively the lease) to construct three buildings on two parcels in the City of Santa Clara and lease them to ROLM Corporation (lessee). Lessor promised in paragraph 2 to “design and construct or cause to be designed and constructed, in a good and workmanlike manner” the buildings. The initial term of the lease is 20 years from the earlier of lessee’s occupancy or acceptance of the completed buildings. Rent is due monthly. Lessee began occupancy in early 1977.
In December 1987 lessor was informed that lessee would be merging at the end of the month into sublessor. The lease provides that lessee was entitled to assign its interest to any corporation with which it might merge so long as the assignee agreed to assume and perform all lessee’s obligations under the lease. The lease also provides that its covenants bind and benefit “the parties hereto, their heirs, successors, executors, administrators and assigns.” Upon the merger sublessor assumed lessee’s obligations.
In early September 1989 lessor consented in writing to a proposal by sublessor to sublease the premises to sublessee, a Delaware partnership between wholly owned subsidiaries of Siemens Corporation of Germany. The lease (paragraph 13) provides that lessee must obtain lessor’s consent to any assignment, which consent will not be unreasonably withheld. The proposal stated: “[Sublessee] ROLM Systems agrees to be bound by all the covenants of the current Lease and [sublessor] IBM agrees to remain liable for all of its obligations under the Lease.”
The sublease was entered later in September 1989. Its term is five years. Sublessee is entitled to terminate it upon 60 days’ written notice. The lease *590 terms are incorporated by reference to the extent consistent with the sublease with the terms “lessor” and “lessee” referring to sublessor and sublessee, respectively. Sublessee agreed to assume all of sublessor’s obligations under the lease, except the “obligation to pay rent” and other costs. Sublessee is to pay sublessor rent in the amount due under the lease. Sublessor agrees to perform all terms, covenants, and conditions of the lease that are personal and can only be performed by sublessor. The sublease does not expressly provide for arbitration. For remedies, it provides that sublessor is not responsible if lessor defaults so long as sublessor, at sublessee’s request, demands and pursues lessor’s performance. The cost of such pursuit is allocated by a document not in tibe record.
Sublessee has paid rent directly to lessor for a year.
In November 1990, sublessee as “successor in interest to [lessee] ROLM Corporation” demanded arbitration with lessor about lessor’s breach of lease. There is a roof problem. The lease (paragraph 32) provides: “All disputes, claims or controversies arising out of or under this Lease, or the breach thereof, shall be settled by arbitration and shall be submitted to arbitration in San Francisco, California, for determination by three (3) arbitrators in accordance with the procedure then obtaining of the Commercial Arbitration Rules of the American Arbitration Association, except that the Construction Industry Arbitration Rules shall apply to disputes concerning matters under Paragraph 2 hereof. The decision and award made in any such arbitration proceedings shall be final, binding, and conclusive upon all parties, and judgment upon any award rendered thereon may be entered upon application of either Lessor or Lessee in any court, state or federal, having jurisdiction.”
Lessor resisted arbitration on the grounds it had no lease agreement with sublessee and sublessee was not a successor in interest to lessee. In December 1990 sublessor joined sublessee’s demand for arbitration. On February 19, 1991, the American Arbitration Association scheduled a preliminary hearing for April 20, 1991.
On March 26, 1991, lessor filed this action, seeking an injunction barring arbitration and a declaration that it is not required to arbitrate with sublessee.
At a hearing on April 18, 1991, the court denied lessor’s request for a preliminary injunction. The arbitration hearing was scheduled to begin on July 22, 1991. Lessor filed a notice of appeal on May 21, 1991. On June 19, 1991, this court summarily denied lessor’s alternative requests for a stay of arbitration pending appeal or a writ commanding the trial court to grant a preliminary injunction. (No. H008516.)
*591 3. Is the order appealable?
Defendants contend the order denying lessor’s request to preliminarily enjoin arbitration is tantamount to a nonappealable order compelling arbitration.
In general, orders refusing to grant preliminary injunctions are appealable pursuant to Code of Civil Procedure section 904.1, subdivision (f).
1
As lessor points out, orders refusing preliminarily to enjoin arbitration have been held appealable.
(American Builder’s Assn.
v.
Au-Yang
(1990)
Lessor’s reply brief appropriately notes
International Film Investors
v.
Arbitration Tribunal of Directors Guild
(1984)
We agree an order refusing to enjoin arbitration is tantamount to an order compelling arbitration. Treating the former as appealable would exalt form over substance (Civ. Code, § 3528) and would encourage an unseemly race to the courthouse between arbitration proponents and opponents. Lessor orally argued that no such courthouse race is threatened when the arbitration provision is “self-executing.” Lessor’s premise is that a court order compelling arbitration is unnecessary, if not unavailable, for self-executing arbitration provisions. Lessor’s resistance to what it calls a self-executing arbitration provision undermines this premise. A court order either compelling arbitration or refusing to enjoin arbitration was apparently necessary to bring lessor to the arbitration table. Neither order is appealable.
4. Is arbitration appropriate?
International Film Investors
recognizes that a writ of prohibition is an appropriate remedy if arbitration is unjustifiably ordered. (
Section 1281.2 requires a court to order arbitration pursuant to contract “if it determines that an agreement to arbitrate the controversy exists. . . .” “[T]he existence of an agreement to arbitrate the controversy is . . . a preliminary question to be determined by the court before an order compelling arbitration can be made.”
(Pagett
v.
Hawaiian Ins. Co.
(1975)
Lessor concedes that sublessor can compel it to arbitrate pursuant to the lease. The parties here argue about whether sublessee expressly agreed to be bound by the arbitration provision in the lease, in other words, whether there is contractual privity between lessor and sublessee.
Kelly
v.
Tri-Cities Broadcasting, Inc.
(1983)
5. Disposition
The purported appeal is dismissed.
Agliano, P. J., and Bamattre-Manoukian, J., concurred.
Notes
Unspecified section references are to the Code of Civil Procedure.
Section 1294 provides: “An aggrieved party may appeal from: [|] (a) An order dismissing or denying a petition to compel arbitration. H] (b) An order dismissing a petition to confirm, correct or vacate an award. [5] (c) An order vacating an award unless a rehearing in arbitration is ordered. H] (d) A judgment entered pursuant to this title. [¶] (e) A special order after final judgment.”
